Title: | CMP |
Notice: | Welcome to the CMP notesfile |
Moderator: | FABSIX::B_TOWER LLE |
|
Created: | Tue Oct 31 1995 |
Last Modified: | Fri Jun 06 1997 |
Last Successful Update: | Fri Jun 06 1997 |
Number of topics: | 94 |
Total number of notes: | 6381 |
66.0. "FY97 PM SCHEDULE (with corrected system name)" by SUBPAC::TOOKER () Tue Aug 27 1996 13:46
FY97 FAB6 CMP PM SCHEDULE PLANNER FY97
FIRST QUARTER DAY SYSTEM AND TYPE OF PM
____________________________________|___________________________________________
WEEK # S M T W T F S | A1 A2 B1 B2 B3 S1 S2 S3 SC1-7 C1-7
------------------------------------|-------------------------------------------
JULY (4 WEEKS)
1 30 1 2 3 4 5 6 W W S W W W W - - -
2 7 8 9 10 11 12 13 W M W M W W W - - -
3 14 15 16 17 18 19 20 M W W W M W W - - -
4 21 22 23 24 25 26 27 W W W W W W W W - -
AUGUST (4 WEEKS)
5 28 29 30 31 1 2 3 W W M W W W W W - -
6 4 5 6 7 8 9 10 W M W M W Q W W - -
7 11 12 13 14 15 16 17 M W W W M W W W - -
8 18 19 20 21 22 23 24 W W W W W W W Q W W
SEPTEMBER (5 WEEKS)
9 25 26 27 28 29 30 31 W W W S W W W W W M
10 1 2 3 4 5 6 7 W M M W W W W W W W
11 8 9 10 11 12 13 14 W W W W M W S W W W
12 15 16 17 18 19 20 21 A W W W W W W W W W
13 22 23 24 25 26 27 28 W W W W W W W W S M
SECOND QUARTER DAY SYSTEM AND TYPE OF PM
___________________________________|____________________________________________
WEEK # S M T W T F S | A1 A2 B1 B2 B3 S1 S2 S3 S4-7 C1-7
-----------------------------------|--------------------------------------------
OCTOBER (4 WEEKS)
14 29 30 1 2 3 4 5 W W M W W W W W W W
15 6 7 8 9 10 11 12 W M W M W W W W W W
16 13 14 15 16 17 18 19 M W W W W W W W W W
17 20 21 22 23 24 25 26 W W W W W W W W W M
NOVEMBER (4 WEEKS)
18 27 28 29 30 31 1 2 W W M W W W W W W W
19 3 4 5 6 7 8 9 W M W M W S W W W W
20 10 11 12 13 14 15 16 M W W W M W W W W W
21 17 18 19 20 21 22 23 W W W W W W W S W M
DECEMBER (5 WEEKS)
22 24 25 26 27 28 29 30 W W M W W W W W W W
23 1 2 3 4 5 6 7 W S W M W W W W W W
24 8 9 10 11 12 13 14 W W W W M W Q W W W
25 15 16 17 18 19 20 21 M W W W W W W W W S
26 22 23 24 25 26 27 28 W W W W W W W W Q W
THIRD QUARTER DAY SYSTEM AND TYPE OF PM
___________________________________|____________________________________________
WEEK # S M T W T F S | A1 A2 B1 B2 B3 S1 S2 S3 S4-7 C1-7
-----------------------------------|--------------------------------------------
JANUARY (4 WEEKS)
27 29 30 31 1 2 3 4 W W S W W W W W W W
28 5 6 7 8 9 10 11 W M W M W W W W W W
29 12 13 14 15 16 17 18 M W W W M W W W W W
30 19 20 21 22 23 24 25 W W W W W W W W W M
FEBUARY (4 WEEKS)
31 26 27 28 29 30 31 1 W W M W W W W W W W
32 2 3 4 5 6 7 8 W M W M W Q W W W W
33 9 10 11 12 13 14 15 M W W W M W W W W W
34 16 17 18 19 20 21 22 W W W W W W W Q W M
MARCH (5 WEEKS)
35 23 24 25 26 27 28 1 W W W S W W W W W W
36 2 3 4 5 6 7 8 W M M W W W W W W W
37 9 10 11 12 13 14 15 W W W W M W S W W W
38 16 17 18 19 20 21 22 S W W W W W W W W M
39 23 24 25 26 27 28 29 W W W W W W W W S W
FOURTH QUARTER DAY SYSTEM AND TYPE OF PM
___________________________________|____________________________________________
WEEK # S M T W T F S | A1 A2 B1 B2 B3 S1 S2 S3 S4-7 C1-7
-----------------------------------|--------------------------------------------
APRIL (4 WEEKS)
40 30 31 1 2 3 4 5 W W M W W W W W W W
41 6 7 8 9 10 11 12 W M W M W W W W W W
42 13 14 15 16 17 18 19 M W W W M W W W W W
43 20 21 22 23 24 25 26 W W W W W W W W W M
MAY (4 WEEKS)
44 27 28 29 30 1 2 3 W W M W W W W W W W
45 4 5 6 7 8 9 10 W M W W S S W W W W
46 11 12 13 14 15 16 17 M W W M W W W W W W
47 18 19 20 21 22 23 24 W W W W W W W S W M
JUNE (5 WEEKS)
48 25 26 27 28 29 30 31 W W M W W W W W W W
49 1 2 3 4 5 6 7 W A W M W W W W W W
50 8 9 10 11 12 13 14 W W W W M W Q W W W
51 15 16 17 18 19 20 21 M W W W W W W W W A
52 22 23 24 25 26 27 28 W W W W W W W W Q W
================================================================================