1204.0. "Modifying script to exclude days." by KAOT01::GU_LAROCQUE () Mon Feb 03 1997 18:44


	I looked in the previous notes, was not able to find the answer.
Also tried accessing the documentation in 
MUZICK::SYS$PUBLIC:[SCHEDULER.RELEASE.DOC], but was unable to.


Just looking for a quick answer.
Customer has an existing procedure that is set to run 7 days a week,
wants to make a modification so that it nolonger runs on the weekend.
How does he make the change?

	Pls if there is a quick answer to this I would appreciate it, else,
if you can point me to where I can find a user guide online.


		Thank You.
			/Guy
T.RTitleUserPersonal
Name
DateLines
1204.1It's all in the manualHLFS00::ERIC_SEric Sonneveld MCS - B.O. IS HollandThu Feb 06 1997 05:307
    if the job interfal is e.g. D 10:00 (run daily at 10:00) currently the
    days on the job will say 'all'.
    
    Simply issue the command $sched mod 'job' /day=(nosat,nosun) and the
    job will run at weekdays only
    
    Eric
1204.2KAOT01::GU_LAROCQUEThu Feb 06 1997 13:185

	Thanks very much for the information...

		/Guy