206.0. "VCS/PCM on Alpha ??" by TOOHOT::LEEDS (From VAXinated to Alphaholic) Thu Mar 10 1994 05:16

We have a customer who has been quoted a DEC 3000-300 AXP to be their
"VCS" console for a CI cluster and some other systems by their VAR. My
understanding is that VCS is not being ported to Alpha so this will
not work. However, they could use PCM. The customer requires the
workstation to run OpenVMS, so they have to wait 'til June for V1.1. 

First - is the above correct ??

Second - if they need VCS functionality on a VMS system by the end of 
March, is their only choice to order a VAXstation and VCS ??

Thanks

Arlan
T.RTitleUserPersonal
Name
DateLines
206.1OPG::PHILIPAnd through the square window...Thu Mar 10 1994 09:5219
Arlan,

>>We have a customer who has been quoted a DEC 3000-300 AXP to be their
>>"VCS" console for a CI cluster and some other systems by their VAR. My
>>understanding is that VCS is not being ported to Alpha so this will
>>not work. However, they could use PCM. The customer requires the
>>workstation to run OpenVMS, so they have to wait 'til June for V1.1. 
>>
>>First - is the above correct ??

  Yes.

>>Second - if they need VCS functionality on a VMS system by the end of 
>>March, is their only choice to order a VAXstation and VCS ??

  Yes.

Cheers,
Phil
206.2Is this a Budget requiremnent??OPG::SIMONThu Mar 10 1994 10:1413
    Is the end of March because of Financail Year end and budget deadlines,
    or for a technical reason?
    
    If it is the former then you may be able to be creative with your
    customer ( order now for delivery later). 
    
    Bear in mind that at some time in the future the customer will need to
    migrate to PCM as VCS will be retired and PCM is the upgrade path!!
    
    Will it be better to go through the implimentation once rather than
    impliment VCS and then go through the migration.
    
    Cheers simon....
206.3technical reasons...TOOHOT::LEEDSFrom VAXinated to AlphaholicThu Mar 10 1994 14:5912
Unfortunatly - it's a technical reason - they're adding some remote 
systems and they wanted to manage those via VCS by tying the console 
ports into the network. Their MIS group is here in Phoneix, but one 
system will be in Texas and one in Ohio with no local system 
management in either site. Their intention was to replace the 3 
consoles they currently have on their CI cluster with VCS and add the 
two consoles for the remote sites. These other two systems will arrive 
this month.

Thanks for the input.