| Date Of Receipt: 28-OCT-1996 11:56:52.30
From: FLUME::"[email protected]" "Susan Schueller USG 28-Oct-1996 1153"
To: Anne Milicia bossec <[email protected]>
CC: [email protected], [email protected], [email protected],
[email protected]
Subj: Re: Steel OS pool open for merge with PTB BL3 - wait on regular?
Hi Anne,
> I've been trying to figure out from the release engineering home page if I
> need to wait to submit a regular srequest I did Friday, until the steel merge
> is over. I just see a green dot by steelos and am not sure.
> So, my first question is should a QAR fix submit srequested Friday afternoon
> wait until this merge is done? If it matters, the srequest was
> steelos-1054-amilicia.
If this is a non-merge srequest, you need to wait until the Steel BL6 /PTB BL3
merge is done. It's currently scheduled to finish this Thursday, 10/31.
>
> My second question is should I have been able to figure this out from a web
> page? If so, would you point me to it?
As far as I know there isn't any merge status information on the
Release Engineering Web Page. During merges, John Flanagan sends
a daily merge / build status to all OSF developers.
I will send a message to OSF developers when the Steel pools are
open for general submits (scheduled for Friday 11/1).
Stay tuned :-)
>
> My third question is I'm also trying to figure out the procedure for submitting
> that same fix to ptb and ptc. I'm trying to determine if I submit to ptb will
> it get merged into ptc, or, do I need to submit to ptc? For both releases I'm
> trying to figure out if I just do an srequest, or, if I ask somebody if they
> want the fix first. For ptb Therese Morin is letting me know if I should
> create the fix. I tried to figure out these answers from web pages. If I
> should have found the answers will you please point me to the correct pages?
I'm not sure about this one. I will forward this to Grant Van Dyck,
who is the Release Engineering Project Leader for PTC.
Sue
>
> Thank-you.
> Anne
>
> > Reply-To: Susan Schueller - Digital UNIX Systems Group <[email protected]>
> >
> > OSF Developers:
> >
> > The Steel OS BL6 pool is open for the merge with PTB BL3.
> >
> > Sue Schueller
> > Steel Release Engineering Project Leader
> >
--
------------------------------------------------------------
Susan Schueller Digital Equipment Corporation
USG Release Engineering MS ZKO3-3/W20
(603) 881-6348 110 Spit Brook Road
[email protected] Nashua, NH 03062-2698
------------------------------------------------------------
|
| Date Of Receipt: 28-OCT-1996 22:25:48.81
From: FLUME::"[email protected]"
To: [email protected] (Anne Milicia bossec)
CC: [email protected]
Subj: Re: Steel OS pool open for merge with PTB BL3 - wait on regular?
> > My third question is I'm also trying to figure out the procedure for submitting
> > that same fix to ptb and ptc. I'm trying to determine if I submit to ptb will
> > it get merged into ptc, or, do I need to submit to ptc? For both releases I'm
> > trying to figure out if I just do an srequest, or, if I ask somebody if they
> > want the fix first. For ptb Therese Morin is letting me know if I should
> > create the fix. I tried to figure out these answers from web pages. If I
> > should have found the answers will you please point me to the correct pages?
>
> I'm not sure about this one. I will forward this to Grant Van Dyck,
> who is the Release Engineering Project Leader for PTC.
>
Unless this is a SS QAR I doubt that PTB will take it, but that's their call.
If it does go into ptb, then ptc will automatically pick it up when we
retarget to ptb.bl4 during the ptc.bl2 time frame.
If they don't, then submit an srequest to PTC.
--
Grant Van Dyck enet: [email protected]
Release Engineering
|