113.0. "Scheduled interruptions" by FOOT::THOMPSON () Fri Jan 22 1988 14:34

    This note is for announcements concerning scheduled interruptions
    to services used by ADG
T.RTitleUserPersonal
Name
DateLines
113.26th Feb No power DECpark IFOOT::THOMPSONFri Jan 22 1988 14:465
    On 6th Feb (Saturday) all power in DEC Park 1 computer room will
    be switched off. There will therefore be no DECnet/LAT connections
    to Acre Rd. from outside the building. 
    
    Internal networking/LAT connections won't be affected.
113.3MVAX shutdown, 30th JanFOOT::THOMPSONTue Jan 26 1988 10:4413
    On Friday 30th Jan, power to the microvax room will be switched
    off so that safety equipment can be installed over the weekend.
    
    The following nodes will be shut down until Mon morning
    PERKY
    CUCKOO
    HAND
    CALF
    SOOTY
    SWEEP
    HAIR
    FINGER
        
113.46th Feb - power offFOOT::THOMPSONWed Jan 27 1988 18:0411
    Ye power down on 30th Jan has been rescheduled.....again.

    On 6th Feb (Saturday) all power to Acre Rd computer room 1 will
    be switched off so that essential maintenance work can be carried
    out.
    
    There will be no power from 08:00 to 17:30



    
113.5U43 down 21st AprilCHEST::THOMPSONMon Apr 18 1988 11:293
    On Thursday 21st April RDGE43 will be unavailable because of scheduled
    Preventative Maintenance and a Field Change Order. It will be down
    from 09:00 until 17:30.
113.6PM calender April-June 1988CHEST::THOMPSONMon Apr 18 1988 11:4113
    
    	Scheduled Preventative Maintenance Calender
    	-------------------------------------------
    
    	CHEST	Thursday 19th May
    	RDGE39	Friday   20th May
        MAIDEN  Tuesday  24th May
    	SEPTIC	Friday   27th May
    	RDGE00	Thursday  2nd June
    	RDGE03	Friday   10th June
    	ADGV01	Tuesday  14th June
    
    
113.7RDGE00::RUSSELLOh good, not long until EOY/BOY......Tue Apr 19 1988 09:357
    Jerry, do we need all these PM's so near to the move?
    
    Surely FS will be doing a "super" PM in the tear-down/rebuild of
    these system...
    
    Peter.
    
113.8Certain shutdown or perhaps a crashNECK::THOMPSONThu Apr 21 1988 13:1714
    I see your point Peter, but I think what will happen is that as
    you say the machines will be given a thorough once over when they're
    installed at the Crescent and the PM's will consist of looking
    in the error logs for anything unusual since the installation date.
    If there appears to be a potential problem then FS will take the
    machine and fix it. If there are no problems then FS won't take
    the machine down. 
    
    If I cancel these PM's then the period until the next scheduled
    PM will be longer than normal and the risk of having unscheduled
    downtime will increase.
    
    If you want to cancel the PM on SEPTIC and accept this increased
    risk then let me know.