1326.0. "Sizing info for MCC on Ultrix platform" by ONOIS1::GAIRNS () Fri Aug 09 1991 13:58

    I'm working on a project here in France with a major telecoms manufacturer (both 
national and international) who will select a network management platform for 
his whole line of products.
The contenders are DECMCC and OPENVIEW.
The prospect develops both sophisticated switches destined for PTTs and a whole 
line of X25 products for private and public networks.
We have been asked to estimate the configuration required for:
    
    A single network management platform under ULTRIX with 20 attached graphics 
    terminals capable of managing a 500 node network.
    
    Extrapolating a current PTT installation, there will be on average 1.15 
    events per second and 11.5 events at peak to be processed by the platform.
    
    The management protocols will be based on CMIS/CMIP.
    
    Can anyone give me an idea of the hardware platform that is required and 
    memory requirements (ball park figures with reserves where necessary and 
    what your figures are based on)?

The project represents hundreds of platforms per year.

We are in contact with PNMP.

Thanks for your help

Ian Gairns
    
T.RTitleUserPersonal
Name
DateLines
1326.1BSYBEE::EGOLFJohn C. Egolf LKG2-2/T02 x226-7874Mon Aug 12 1991 21:2520
	Ian,

	I just  wantde  to post this note so you know where we stand on
	this...

	I'm checking around  to  see  what  the people here think.  The
	bottom line is that  we  don't have any performance or capacity
	number on our Ultrix system  at  this time.  While I would hope
	that  a DECstation 5000 with some  amount  (ie:32M)  of  memory
	should be a good platform that could grow (more memory and more
	disk), we just don't know yet.

	What is your time frame for needing your  response?    How firm
	does it have to be.  What is HP recommending?

	We'll be back intouch.

	JCE


1326.2further infoONOIS1::GAIRNSTue Aug 20 1991 09:1615
John,

Sorry, but we don't have the HP figures.

The customer will choose between the two competing platforms wihin the next two 
weeks and he is pressing us for information for the end of this week.

As the customer will use our figures to cost the product, and will use them in
an future contract, we cannot afford to be wildly out, even though he accepts
that netwok management is not an exact science.

Can you give me an idea of the disk requirements for DECmcc on a risc platform
(basic product and database)?

What reservations would you recommend that we write into our answer.