[Search for users] [Overall Top Noters] [List of all Conferences] [Download this site]

Conference 7.286::space

Title:Space Exploration
Notice:Shuttle launch schedules, see Note 6
Moderator:PRAGMA::GRIFFIN
Created:Mon Feb 17 1986
Last Modified:Thu Jun 05 1997
Last Successful Update:Fri Jun 06 1997
Number of topics:974
Total number of notes:18843

734.0. "Modifications scheduled to begin on pad 39-B" by PRAGMA::GRIFFIN (Dave Griffin) Mon Jun 17 1991 13:12

6/13/91:  MODIFICATIONS SCHEDULED TO BEGIN ON LAUNCH PAD 39-B

KSC RELEASE NO. 73-91

     Launch pad 39-B will be taken off-line for the remainder of
the year as workers perform modifications to the structure and
associated payload handling facilities.

     Pad 39-B, one of two KSC shuttle launch facilities is in
need of repairs and refurbishment. Work crews are scheduled to
spend the better part of the next six months seeing that the work
is performed in time to support the first launch of the space
agency's newest orbiter, Endeavour, early next year.

     The work on pad 39-B was designed to coincide with the
decision to send the orbiter Columbia to the Rockwell facility in
Palmdale, Calif., for modifications.

     "Columbia's move to California provided the time to work on
the pad," said Mickey Riddle, NASA's pad leader for 39-B. "We are
making modifications to the facility during the time we have a
window to do so," he said.

     Once Columbia is delivered to Palmdale in August of this
year, there will only be two orbiters, Atlantis and Discovery, in
the active launch processing flow. Working with one less pad is
expected to have minimal impact on the agency's launch schedule
for the remainder of the year.

     Launch pad 39-A will remain fully operational and support
the next five scheduled Space Shuttle missions.

     Pad 39-B is expected to be back on line in time for
Endeavour's first launch. Endeavour is currently scheduled to
rollout to the pad in February 1992.


     Several changes are in store for pad 39-B as it is brought
up to generally the same standards at pad 39-A. Lockheed Space
Operations Company will implement the modifications and award 15
different sub-contracts to about eight to 10 companies.

     Contracts will be awarded to perform about 50 modifications
to the structures and processing equipment, improvements to the
environmental control system and work on the hypergolic servicing
system. Work will also be performed in the payload changeout room
involving the CAPS, or the Clean Access Platform System, and
contamination control improvements to the payload handling areas.

     Other modifications include work on the rotating service
structure, hardware and electrical systems improvements, and
structural corrosion control. This period will also provide an
opportunity to make improvements to the safety and overall
efficiency of the facility.

     Estimated cost of the modifications is about $3.3 million.

     Not launching from pad 39-B this year will also offer a by-
product to the local residents -- Playalinda Beach will be open
for most of the summer. The beach, located on the northern
boundary of KSC, normally closes when a vehicle is on pad B due
to security reasons.

     With shuttles being launched for the rest of this year only
from pad 39-A, located further to the south, the beach will not
close until three days before launch. The next launch scheduled
is that of Atlantis on mission STS-43, from pad 39-A, in late
July.
 
T.RTitleUserPersonal
Name
DateLines
734.1Everything you always wanted to know about 39-A & 39-B56821::BATTERSBYThu Oct 20 1994 18:35117
    I pulled this description of the 39-A & 39-B launch Pad facilities
    off the WWW JSC home page from some obscure menu. There's a lot
    of facts & numbers that make for somewhat interesting reading.
    It had to be edited (after being pulled off the WEB server) to fit
    on a normal 80 column text page.
    Happy reading.
    
    -Bob

Launch Complex 39-A & 39-B
--------------------------
Launch Complex 39's Pad A and Pad B were originally designed to support 
the Apollo program and were modified for Space Shuttle launch operations. 
Major changes included the erection of a new Fixed Service Structure (FSS), 
addition of a Rotating Service Structure (RSS), and the replacement of the
Saturn flame deflectors with three new flame deflectors. The upper portion
of the Saturn V Launch umbilical tower was removed from two of the Apollo 
Mobile Launchers and installed at the pad to serve as the FSS. 

Fuel, oxidizer, high pressure gas, electrical, and pneumatic lines connect 
the Shuttle vehicle with ground support equipment and are routed through 
the FSS, RSS and Mobile Launch Platform. 

Space Shuttle access and servicing at the pad are provided by: 
FSS - Gaseous Hydrogen Vent Arm for electrical power and for venting hydrogen 
from the external tank. 
RSS - Mid-Body Umbilical Unit for fuel cell servicing and life support 
functions. 
RSS facilities for loading and off-loading payloads. 
Hypergolic Umbilical System for servicing the Orbiter systems with fluids 
and gases. 
Gaseous Oxygen Vent Arm for preventing ice formation atop the external tank. 
Orbiter Access Arm (OAA) for crew entrance and exit. 
MLP - Tail Service Masts for propellant loading and electrical power. 

The FSS is topped by a 24.4 meter (80ft) tall fiberglass lightning mast 
grounded by 335 meter (1,100ft) cables that are anchored north and south 
of the pad. The Mast provides lighting protection for pad structures and 
the Space Shuttle. 

The RSS accommodates the loading of payloads vertically at the pad. It is 
mounted on a semi-circular track which allows it to rotate through an arc 
of 120 degrees on a radius of 36.6 meters (120 ft). The RSS pivots from a 
hinge on the FSS until the RSS spacecraft changeout room fits flush with 
the Orbiters's cargo bay. This room allows payloads to be installed or 
serviced under contamination-free or "clean room" conditions.

Blast-protected hypergolic storage and supply systems are provided at each 
pad, and the Launch Processing System (LPS) is used to monitor all aspects 
of vehicle and payload operations. The LPS system interconnects to the MLP 
through Hardware Interface Modules (HIM's) located in Pad Terminal 
Connection Rooms beneath the pads. 

Pad's 39-A and 39-B are virtually identical and roughly octagonal in shape. 
The distance between pads is 2,657 meters (8,715 ft). The pad base contains 
52,000 cubic meters (68,000 cubic yards) of concrete. The ramp leading up 
to the pad is inclined at a 5% grade. The flame trench is 13 meters (42 ft) 
deep, 137 meters (450ft) long and 18 meters (58 ft) wide. The orbiter flame 
deflector is 11.6 meters (38ft) high, 22 meters (72 ft) long and 17.5 
meters (57.6 ft) wide. It weights 590,000 kg (1.3 million lbs). The SRB
deflector is 12.95 meters (42.5 ft) high, 12.8 meters (42 ft) long and 17.4 
meters (57 ft) wide. It weights 499,000 kg (1.1 million lbs). The Sound 
Suppression Water System is used to protect the launch structure from the 
intense sound pressure of liftoff. It's water tank is 88.9 meters (290ft) 
high and has a capacity of 1,135,000 liters (300,000 gallons). 

There are 6 permanent and 4 extensible pedestals that are used to support 
the MLP at the pad.
Dynamic loads at rebound are 3,175,200 kg (7,000,000 lbs) to 4,762,800 kg 
(10,500,000lb) at liftoff. The pad is lit with 5 clusters of Xenon 
high-intensity searchlights (total searchlights: 40) around the pad 
perimeter. 

The height of the Fixed Service Structure (FSS) is 105.7 meters (347ft) 
to the top of the lightning mast (referenced to the pad base) and the 
Rotating Service Structure (RSS) is 57.6 meters (189ft) high. The Fixed 
Service Structure (FSS) and Rotating Service Structure (RSS) on Pad 39A 
underwent a renovation between June and September 1993. Some 13,773 gallons 
of paint were used on two coats and 1,866 tons of sand were used in the 
sandblasting operation. 

The LC-39 Launch complex also contains large liquid oxygen (LOX) and 
Liquid Hydrogen (LH2) storage tanks. These are large ball-shaped vacuum 
jacketed dewar bottles used to store supercold cryogenic propellants for 
the shuttle external tank. The LOX tank, located at the northwest corner 
of the pad stores 3,406,500 liters (900,000 gallons) of liquid oxygen at 
a temperature of minus 183 degress C (-298 F). The LH2 tank is located at 
the northeast corner of the pad and stores 3,218,250 liters (850,000 
gallons) of liquid hydrogen at a temperature of minus 253 degrees C 
(-423 degrees F). 

The Weather Protection System protects orbiter tiles from wind blown 
debris, rain and hail. Wheeled metal doors that ride on steel beams are 
attached to the Rotating Service Structure and the Fixed Service Structure. 
Doors slide together (to within 3 inches of each other) between the 
orbiter's belly and the external tank, providing protection for the lower 
portion of the orbiter. 
East Door, attached to the RSS measures 16 meters (53 ft) long, 8 meters 
(27 ft) tall and weighs 19 metric tons (42,000 lbs). 
West Door, attached to the FSS measures 13 meters (43 ft) long, 11.6 meters 
(38ft) tall and weighs 21 metric tons (46,000 lbs) 

The top of the orbiter is shielded by an inflatable seal extending from 
the Payload Changeout Room forming a semi-circle covering 90 degrees of 
arc between the orbiter and its external tank. The sides of the orbiter, 
between the vehicle and the external tank, are protected by a series of 
20 metal bi-fold doors that fold out from the Payload Changeout Room. 
The doors measure 24.4 meters by 1.2 meters (80ft x 4ft). 

There is approximately 1.25 million feet of tubing and piping at Launch 
Complex 39, varying in sizes from .25 inches to 114 inches in diameter. 
This is enough pipe to reach from Orlando to Miami. 


__________________________________________________________________ 
Last Updated Thu Oct 28 17:06:51 EDT 1993 
Jim Dumoulin ([email protected])