[Search for users] [Overall Top Noters] [List of all Conferences] [Download this site]

Conference 7.286::space

Title:Space Exploration
Notice:Shuttle launch schedules, see Note 6
Moderator:PRAGMA::GRIFFIN
Created:Mon Feb 17 1986
Last Modified:Thu Jun 05 1997
Last Successful Update:Fri Jun 06 1997
Number of topics:974
Total number of notes:18843

662.0. "STS-39 (Discovery)" by 4347::GRIFFIN (Dave Griffin) Mon Oct 29 1990 10:15

This is the placeholder note for space shuttle mission STS-39.  The
vehicle will be Discovery (OV 103).
T.RTitleUserPersonal
Name
DateLines
662.1Shuttle Status for 10/24/90 4347::GRIFFINDave GriffinMon Oct 29 1990 10:1718
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


          KSC SHUTTLE STATUS REPORT - WEDNESDAY, OCT. 24, 1990  10 A.M.

 
                       STS-39 - DISCOVERY (OV 103) - OPF BAY 1

               Deconfiguration of the payload bay from the  STS-41  mission
          is  continuing.  Lube  oil  will be deserviced from the auxiliary
          power units  today.  The  forward  reaction  control  systems  is
          scheduled  to  be removed early Friday morning and transferred to
          the Hypergolic Maintenance Facility for post-flight  inspections.
          Preparations  are underway to offload residual hypergolic propel-
          lants from the orbiter this weekend.


662.2Shuttle Status for 10/26/90 4347::GRIFFINDave GriffinMon Oct 29 1990 10:1820
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


               Friday October 26, 1990                 11:00 a.m. EDT

                     KSC SPACE SHUTTLE PROCESSING STATUS REPORT

          -----------------------------------------------------------------

 
                     STS-39 -- Discovery (OV 103)  -  OPF Bay 1

               Power-on testing is scheduled to begin today, followed by
          hypergolic offload preparations. Hypergols are scheduled to be
          removed from the orbiter's OMS/RCS systems this weekend. The
          Forward Reaction Control System has been re-scheduled to be moved
          to the Hypergolic Maintenance Facility early next week.


662.3Shuttle Status for 11/05/90 4347::GRIFFINDave GriffinTue Nov 06 1990 18:2823
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


          KSC SHUTTLE STATUS REPORT - MONDAY, NOV. 5, 1990  11 A.M.


 
                       STS-39 - DISCOVERY (OV 103) - OPF BAY 1

               Operations  planned  today  include pulling the nose cap for
          structural inspections,  checks of the S-band antenna,  a test of
          the radar altimeter, and thermal protection system operations.

               Last weekend, the right orbital maneuvering system (OMS) pod
          and the forward reaction control system (FRCS) were removed. Both
          vehicle components were transferred to the Hypergolic Maintenance
          Facility for post-flight inspections.

               Heat  shield  removal  is  starting today in preparation for
          removing the three main engines late this week.


662.4Shuttle Status for 11/06/90 4347::GRIFFINDave GriffinTue Nov 06 1990 18:3025
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


          KSC SHUTTLE STATUS REPORT - TUESDAY, NOV. 6, 1990  10 A.M.


 
                       STS-39 - DISCOVERY (OV 103) - OPF BAY 1

               Operations planned today include pulling the  nose  cap  for
          structural   inspections  and  preparations  to  remove  inertial
          measurement unit #1.  Functional testing of the waste containment
          system is scheduled this week.

               Preparations  are underway to perform tests on the right or-
          bital maneuvering system (OMS) pod at the Hypergolic  Maintenance
          Facility.

               Heat  shield  removal  has begun in preparation for removing
          the three main engines on Friday. The engines will be transferred
          to the engine shop in the Vehicle Assembly  Building  for  refur-
          bishment.


662.5Noone sent a memo about this to my desk!37448::FMUDGETTJust how bad was it working?Wed Nov 07 1990 23:419
    Greetings,
    
    Have I missed something or what? Discovery sounds like it's in 
    pretty bad shape, 3 engines removed the nosecap removed etc.
    Is this a planned refurbishment or something? I seem to recall
    the post-flight saying that this last mission had the fewest 
    problems yet. 
    
    Fred Mudgett
662.6Routine Maintenance2631::DAHLTom Dahl, CDMSThu Nov 08 1990 10:195
RE:      <<< Note 662.5 by 37448::FMUDGETT "Just how bad was it working?" >>>

All this sort of stuff is very routine.  Especially engine change-outs and
OMS pod switches.
						-- Tom
662.7Shuttle Status for 11/09/90 4347::GRIFFINDave GriffinSat Nov 10 1990 12:5527
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


          KSC SHUTTLE STATUS REPORT - FRIDAY, NOV. 9, 1990  10 A.M.


 
                       STS-39 - DISCOVERY (OV 103) - OPF BAY 1

               Engine  drying  operations are complete and preparations are
          underway to remove the three SSMEs tomorrow.  They will be trans-
          ferred  to  the main engine shop in the Vehicle Assembly Building
          for refurbishment.

               Freon coolant loop number 1 was deserviced  last  night  and
          the  radiator is scheduled to be removed tonight.  Inspections of
          the payload bay doors are planned after this work.

               Testing is continuing on the right orbital maneuvering  sys-
          tem (OMS) pod at the Hypergolic Maintenance Facility. A new test,
          called  a  screen  test,  to check the propellant tanks' internal
          screen is scheduled next week.  A dry run of the  test  was  com-
          pleted yesterday.


 
662.8Cargo Manifest4347::GRIFFINDave GriffinSat Nov 10 1990 17:2417
    For those of you following along at home...
    
    STS-39 is the former STS-51: Department of Defense Mixed Cargo Flight
    
    I haven't been able to find out much about it, but the following
    manifest items may help decode the acronyms:
    
    o Infrared Background Signature Survey
    o Air Force Program-675
    o Space Test Program
    o Multi-Purpose Experiment Canister
    
    
    Almost back-to-back DOD flights.  How dull.  At least this one appears
    to be less "hush hush".
    
    - dave
662.9It will be interesting for DEC37090::KILGOREDan @ WashingtonThu Nov 15 1990 17:0113
    Ah,  but the exciting part of STS-39 is the experiment canister. This
    flight will be testing the "SpaceVAX".  A modified Raytheon Mil-spec
    VAX that will run a robotic experiment with the VAX exposed to the
    open cargo bay environment.  This is a joint experiment effort between
    the National Robotics Lab at Goddard and Digital.  I have been working
    the past 2 years to get this experiment into space.
    
    The SpaceVAX is configured with Raytheon Model 860.(This is a VAX 6210
    technology)  It has 16MB, a BI, ethernet controller, SCSI board, and 
    a 1553B board.   It is running VMS and the experiment is written is
    VAX Ada.
    
    Dan, (who is GSG SpaceVAX program manager)
662.10PAXVAX::MAIEWSKIFri Nov 16 1990 13:0210
    Dan,

    If you are planning any more SpaceVAX activity you might want to consider
using VAX/ELN instead of VMS. It's a real time operating system, as apposed to
a time sharing operating system and it's very easy to use. It's great for
dedicated applications where you want to switch the machine on and have it do
it's thing. You don't have to log in, set up accounts, etc. 

    Let me know if you need more info,
    George
662.11Shuttle Status Report 11/16/904347::GRIFFINDave GriffinSat Nov 17 1990 09:5521
From: NASA Spacelink
Date: 17-Nov-1990


KSC SHUTTLE STATUS REPORT - FRIDAY, NOV. 16, 1990  10 A.M.

 
             STS-39 - DISCOVERY (OV 103) - OPF BAY 1

     This week,  five new general purpose computers  (GPCs)  were
installed  in  the  vehicle.  STS-39 will be the first use of the
upgraded GPCs.  Today,  an ammonia boiler and the Ku-Band antenna
drive assembly will be replaced.

     A  screen  test  of  the  fuel  tanks  on  the right orbital
maneuvering system (OMS) pod will be  conducted  again  today.  A
retest  is necessary because data collected from Wednesday's test
is not fully understood.  The pod is located  at  the  Hypergolic
Maintenance Facility.

 
662.12Upgraded GPCs (before you ask)4347::GRIFFINDave GriffinSun Nov 18 1990 20:063
    See note 95.1 for a summary of the upgraded GPCs.
    
    - dave
662.13Shuttle Status Report - 11/21/904347::GRIFFINDave GriffinSun Nov 25 1990 01:5825
From: NASA
Organization: NASA

           KSC SPACE SHUTTLE PROCESSING STATUS REPORT

   Wednesday November 21, 1990                 11:00 a.m. EST

-----------------------------------------------------------------

 
             STS-39 -- Discovery (OV 103)  -  OPF Bay 1

     Ammonia boiler decay checks continue today on the orbiter
Discovery in the Orbiter Processing Facility. The left hand
brakes and wheels have been installed on the vehicle and the
freon coolant line will be brazed into place today. The main
engines are scheduled for installation following the Thanksgiving
Holidays.

     At the Hypergolic Maintenance Facility, screen tests
continue on the reaction control systems. In the Vehicle Assembly
Building, a small imperfection was discovered on the left forward
solid rocket booster segment between the propellant and the
inhibitor. The segment will be moved outside the VAB where crews
will repair the problem.
662.14Shuttle Status - 10/26/904347::GRIFFINDave GriffinTue Nov 27 1990 23:2326
From: NASA SpaceLink
Organization: NASA


     Monday November 26, 1990                 10:00 a.m. EST

           KSC SPACE SHUTTLE PROCESSING STATUS REPORT

-----------------------------------------------------------------


 
             STS-39 -- Discovery (OV 103)  -  OPF Bay 1

     Ammonia boiler freon loop decay checks were performed over
the weekend on the orbiter Discovery in the Orbiter Processing
Facility. Bubble soap leak checks were conducted with several
leaks identified near the cold plate manifold. Work will continue
today to replaced the cold plate manifold seals.

     X-rays of the orbiter body flap have been completed and
routine work on the wheels and tires will continue today.



 
662.15Shuttle Status - 11/27/904347::GRIFFINDave GriffinTue Nov 27 1990 23:2426
From: NASA SpaceLink
Organization: NASA


    Tuesday November 27, 1990                 10:00 a.m. EST

           KSC SPACE SHUTTLE PROCESSING STATUS REPORT

-----------------------------------------------------------------


 
              STS-39 -- Discovery (OV 103)  -  OPF Bay 1

     Ammonia boiler freon loop decay checks are continuing today
and work to replace the cold plate manifold seals is underway.

     The nose landing gear doors have been lowered and brake and
tire installations are proceeding.

     In the Hypergolic Maintenance Facility, a test of the
screens in Discovery's OMS pods was conducted yesterday. A
follow-on test will take place today.


 
662.16Shuttle Status - 11/29/904347::GRIFFINDave GriffinThu Nov 29 1990 18:5427
From: NASA SpaceLink
Organization: NASA

KSC SHUTTLE STATUS REPORT - THURSDAY, NOV. 29, 1990  11 A.M.


 
                  STS-39 - DISCOVERY (OV 103) - OPF BAY 1

     Main engines 1, number 2026, and 2, number 2030,   have been
installed  in  the vehicle.  Engine 3,  number 2029,  will be in-
stalled tomorrow.  Seven of 12 seals have been  replaced  in  the
freon cooling system.

     A  screen test of the right orbital maneuvering system (OMS)
pod  is  continuing  this  week  at  the  Hypergolic  Maintenance
Facility.

                      -- STS-39 BOOSTERS - VAB


     STS-39 booster stacking operations  are  continuing  in  the
VAB. The right aft center segment was transferred to the VAB late
last night and will be lifted to the high bay tomorrow.


 
662.17Shuttle Status - 12/3/90PRAGMA::GRIFFINDave GriffinTue Dec 04 1990 00:0329
From: NASA Spacelink
Organization: NASA

   KSC SHUTTLE STATUS REPORT - Monday, Dec. 3, 1990  9:30 a.m.


 
                 STS-39 - DISCOVERY (OV 103) - OPF BAY 1

     Both freon cooling loops passed leak tests this weekend  and
freon servicing is planned this week. The three main engines have
been installed in the vehicle. Operations scheduled this week in-
clude tests of the Ku-band antenna,  servicing of the water spray
boilers, and a functional test of the waste containment system.

     Tests of the right orbital maneuvering system (OMS)  pod  to
verify  the  internal  screens  in the propellant tanks have been
successful at the Hypergolic Maintenance  Facility  (HMF).  Tests
will continue this week with the pod in a horizontal position.

               ## STS-39 SOLID ROCKET BOOSTERS - VAB

     Stacking operations are continuing in the VAB. The right aft
center  segment is being pinned today.  The right forward segment
will be  transferred  from  the  Rotation  Processing  and  Surge
Facility to the VAB tonight.


 
662.18Shuttle Status - 12/4/90PRAGMA::GRIFFINDave GriffinTue Dec 04 1990 18:3528
From: NASA Spacelink
Organization: NASA

  KSC SHUTTLE STATUS REPORT - Tuesday, Dec. 4, 1990  9:30 a.m.


 
             STS-39 - DISCOVERY (OV 103) - OPF BAY 1

     Freon servicing is planned this week.  Operations  scheduled
this week include tests of the Ku-band antenna,  servicing of the
water spray boilers,  and a functional test of the waste contain-
ment system.

     Tests  of  the right orbital maneuvering system (OMS) pod to
verify the internal screens in the  propellant  tanks  have  been
successful  at  the Hypergolic Maintenance Facility (HMF).  Tests
will continue this week with the pod in a horizontal position.

               ## STS-39 SOLID ROCKET BOOSTERS - VAB

     Stacking operations are continuing in the VAB. The right aft
center segment was mated shortly after midnight.  The right  for-
ward  center segment was transferred from the Rotation Processing
and Surge Facility to the VAB and stacking  of  that  segment  is
scheduled to begin today.

 
662.19Shuttle Status for 12/05/90 PRAGMA::GRIFFINDave GriffinWed Dec 05 1990 15:3923
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


           KSC SHUTTLE STATUS REPORT - Wednesday, Dec. 5, 1990  9:30 a.m.

 
                       STS-39 - DISCOVERY (OV 103) - OPF BAY 1

               Operations  scheduled  this  week  include  freon servicing,
          tests of the Ku-band antenna,  Tacan system tests,  and tests  of
          the main propulsion system pneumatic system.

               Tests  are  continuing to verify the internal screens of the
          right orbital maneuvering system (OMS) at  the  Hypergolic  Main-
          tenance Facility (HMF).  Tests are continuing  this week with the
          pod in a horizontal position.

               A getaway special beam is being installed in the payload bay
          today. Preparations are underway to braze in gaseous helium check
          valves for engines 2 and 3 this week.

 
662.20Shuttle Status for 12/06/90 PRAGMA::GRIFFINDave GriffinThu Dec 06 1990 18:4532
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


            KSC SHUTTLE STATUS REPORT - Thursday, Dec. 6, 1990  9:30 a.m.

 
                       STS-39 - DISCOVERY (OV 103) - OPF BAY 1

               Servicing of freon loop 2 was completed,  and  servicing  of
          loop 1 is scheduled today.  Tests of the Ku-band antenna are con-
          tinuing.  Activation and a self  test  of  the  Tacan  system  is
          scheduled.  Torque  checks  of  main  engine pumps are being per-
          formed.

               Tests are continuing to verify the internal screens  of  the
          right  orbital  maneuvering  system (OMS) at the Hypergolic Main-
          tenance Facility (HMF).  A test of the  reaction  control  system
          screens is planned today with the pod in a horizontal position.

               Installation of a getaway special beam in the payload bay is
          continuing.  Preparations are underway to braze in gaseous helium
          check valves for engines 2 and 3 today.

                         # STS-39 SOLID ROCKET BOOSTERS - VAB

               Stacking  operations  are  continuing  in  the VAB.  A minor
          debond between the inhibitor and case was acceptable on the right
          forward center segment.  The segment was lifted to the  high  bay
          early this morning for mating.

 
662.21Shuttle Status Report - 12/07/90PRAGMA::GRIFFINDave GriffinMon Dec 10 1990 09:5632
From: NASA SpaceLink
Organization: NASA

  KSC SHUTTLE STATUS REPORT - FRIDAY, DEC. 7, 1990  10:25 A.M.


 
             STS-39 - DISCOVERY (OV 103) - OPF BAY 1

     The orbiter is scheduled to be powered up later today. Tacan
activation  and self-test will continue through tonight.  Forward
yoke installation work continues, as does tile maintenance work.

     Hydraulic water spray boiler checkouts  are  scheduled  over
the weekend, as are checkouts of the main propulsion system (MPS)
helium  system  and the Ku-band antenna.  Leak and pressurization
tests on various lines in the  iquid  hydrogen  system  are  also
scheduled.

     Several  brazing  operations were completed overnight on the
main propulsation system.  Installation of  electronic  boxes  on
cold  plates  continues.  At  the Hypergolic Maintenance Facility
(HMF),  screen tests of the right-hand orbital manuevering system
(OMS) continue. Final manifold drain is scheduled for next week.

               ## STS-39 SOLID ROCKET BOOSTERS - VAB

     Stacking operations continue.  Range safety  ground  support
equipment validations are scheduled for next week.


 
662.22Shuttle Status - 12/10/90PRAGMA::GRIFFINDave GriffinTue Dec 11 1990 20:1329
From: NASA Spacelink
Organization: NASA

KSC SHUTTLE STATUS REPORT - Monday, Dec. 10, 1990  11:30 a.m.

 
             STS-39 - DISCOVERY (OV 103) - OPF BAY 1

     The orbiter was powered up Friday night and the  new general
purpose computers operated without incident.  The fourth tank set
for the power reactant storage and distribution  system  was  in-
stalled.

     Tests  have been successfully completed to verify the inter-
nal screens of the right orbital maneuvering system (OMS) at  the
Hypergolic Maintenance Facility (HMF).  Routine tests  of the pod
will begin soon.

     Two of three getaway special canisters have  been  installed
in the payload bay.

               ## STS-39 SOLID ROCKET BOOSTERS - VAB

     Stacking  operations  are  continuing in the VAB.  The right
forward segment was pinned to the stack this  weekend.  The  left
forward  segment was transferred to the VAB and is being prepared
for stacking.

 
662.23Shuttle Status - 12/11/90PRAGMA::GRIFFINDave GriffinTue Dec 11 1990 20:1520
From: NASA Spacelink
Organization: NASA

   KSC SHUTTLE STATUS REPORT - TUES. DEC. 11, 1990  10:25 A.M.

 
             STS-39 - DISCOVERY (OV 103) - OPF BAY 1

     Powered-up  testing  was  briefly  interrupted  when a power
supply went down. However, backup power was brought on-line,  and
testing continued without furthur incident.

       Freon  cooling loop #1 is undergoing vacuuming and drying.
Workers are preparing for a main  engine  Flight  Readiness  Test
(FRT) on Friday.




 
662.24Shuttle Status for 12/12/90 PRAGMA::GRIFFINDave GriffinWed Dec 12 1990 17:5936
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


            KSC SHUTTLE STATUS REPORT - Wednesday, Dec. 12, 1990  10 a.m.


 
                       STS-39 - DISCOVERY (OV 103) - OPF BAY 1

               The fourth oxygen tank set for the  power  reactant  storage
          and  distribution  system has been installed.  Checks of the main
          propulsion system are continuing.  Technicians are  scheduled  to
          install the nose cap today.  Checks of the left orbital maneuver-
          ing system pod are underway.

               A test of the nose wheel steering system and a  brake  anti-
          skid  test are planned tomorrow.  The orbiter hydraulic system is
          being prepared for these tests.

               Discovery is being prepared for rollover to the Vehicle  As-
          sembly Building the end of January.


                       ## STS-39 SOLID ROCKET BOOSTERS - VAB

               Stacking operations are continuing in the VAB. The left for-
          ward  segment was pinned to the stack.  The left forward assembly
          is scheduled to be mated today and the right forward assembly  is
          ready to be mated tomorrow. Closeouts are underway on all joints.

               The  external  tank is scheduled to be mated to the boosters
          on Dec. 18.


 
662.25Shuttle Status for 12/13/90 PRAGMA::GRIFFINDave GriffinThu Dec 13 1990 17:4019
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


            KSC SHUTTLE STATUS REPORT - Thursday, Dec. 13, 1990  10 a.m.


 
                       STS-39 - DISCOVERY (OV 103) - OPF BAY 1

               Technicians are scheduled to install  the  nose  cap  today.
          Checks of the left orbital maneuvering system pod are underway. A
          test  of  the  nose  wheel steering system is set for today and a
          brake anti-skid test is  planned  tomorrow.  Discovery  is  being
          prepared for rollover to the Vehicle Assembly Building the end of
          January.


 
662.26Shuttle Status for 12/14/90 PRAGMA::GRIFFINDave GriffinMon Dec 17 1990 17:4734
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


             KSC SHUTTLE STATUS REPORT - FRIDAY, DEC. 14, 1990  10 a.m.


 
                       STS-39 - DISCOVERY (OV 103) - OPF BAY 1

               Yesterday, technicians installed the nose cap. Checks of the
          left orbital maneuvering system pod are underway.  A test of  the
          nose  wheel  steering  system  was  conducted yesterday.  A brake
          anti-skid test is planned today and an  engine  flight  readiness
          test is planned this weekend. During this test, the engine valves
          will be cycled and sensors will be calibrated.  This test is also
          conducted after the vehicle arrives at the launch pad.

               Discovery's right orbital maneuvering system  pod  is  being
          tested at a maintenance facility on base. While that testing con-
          tinues,  Atlantis'  right  OMS pod will be installed on Discovery
          this weekend.  Discovery is being prepared for  rollover  to  the
          Vehicle Assembly Building the end of January.

                        ## STS-39 SOLID ROCKET BOOSTERS - VAB

               Booster stacking operations have been  completed. Overnight,
          the right forward assembly was mated to the stack.  Closeouts are
          underway on all joints.

               The  external  tank is scheduled to be mated to the boosters
          on Dec. 18.

 
662.27Shuttle Status for 12/17/90 PRAGMA::GRIFFINDave GriffinMon Dec 17 1990 17:4833
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


               Monday December 17, 1990                 9:00 a.m. EST

                     KSC SPACE SHUTTLE PROCESSING STATUS REPORT

          -----------------------------------------------------------------


 
                     STS-39 -- Discovery (OV 103)  -  OPF Bay 1

               The orbiter Discovery experienced an emergency power down
          over the weekend due to a small electrical fire Friday night in
          the uninterruptable power source (UPS) relay transformer on the
          first floor of the Launch Control Center room 1P4. Power was
          restored at about 1:45 p.m. Saturday. No severe damage to the UPS
          was reported and orbiter processing with power-on testing
          continues today.

               The STS-39 payload integration verification test continues
          today in the Orbiter Processing Facility. The right hand orbital
          maneuvering system pod is scheduled to be installed on the
          vehicle tonight and the forward reaction control system will be
          positioned and installed later this week. Freon coolant loops one
          and two will be sampled today. The main engine frequency response
          test has been completed and the nose cap installation is
          complete, pending final duct installation.


 
662.28Shuttle Status for 12/18/90 PRAGMA::GRIFFINDave GriffinTue Dec 18 1990 18:3429
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


              Tuesday December 18, 1990                 11:00 a.m. EST

                     KSC SPACE SHUTTLE PROCESSING STATUS REPORT

          -----------------------------------------------------------------


 
                     STS-39 -- Discovery (OV 103)  -  OPF Bay 1

               The STS-39 payload integration verification test continues
          in the Orbiter Processing Facility. The right hand orbital
          maneuvering system pod was lifted to the vehicle last night and
          installation procedures are continuing today. The forward
          reaction control system will be positioned and installed Thursday
          night. Mass spectrometer leak checks of the main propulsion
          system have been completed. Nose cap installation is complete,
          pending final duct installation.

               In the Vehicle Assembly Building, the STS-39 external tank
          is being lifted to the twin solid rocket boosters. Mating
          operations will commence late this afternoon.


 
662.29Shuttle Status for 12/19/90 PRAGMA::GRIFFINDave GriffinFri Dec 21 1990 09:4233
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


             Wednesday December 19, 1990                 10:00 a.m. EST

                     KSC SPACE SHUTTLE PROCESSING STATUS REPORT

          -----------------------------------------------------------------


 
                     STS-39 -- Discovery (OV 103)  -  OPF Bay 1

               The right hand orbital maneuvering system pod was attached
          to the vehicle last night. Electrical mates are continuing today
          and are scheduled to be completed by Friday. The forward reaction
          control system will be positioned and installed tomorrow evening.
          Nose cap installation is complete. Main engines two and three
          helium purge check valves will be installed today. Tile
          waterproofing and lazer step and gap operations are in work.
          Hydraulic operations to position the aerospace surfaces will be
          conducted prior to power down operations, now scheduled for
          Friday midnight.

               In the Vehicle Assembly Building, the STS-39 external tank
          was lifted to the twin solid rocket boosters. Mating operations
          to attach the ET to the SRBs were completed last night.
          Electrical and mechanical hardmate verification operations will
          continue today.


 
662.30Shuttle Status for 12/21/90 PRAGMA::GRIFFINDave GriffinFri Dec 21 1990 17:4424
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


               Friday December 21, 1990                 11:00 a.m. EST

                     KSC SPACE SHUTTLE PROCESSING STATUS REPORT

          -----------------------------------------------------------------

 
                     STS-39 -- Discovery (OV 103)  -  OPF Bay 1

               The payload bay doors on Discovery were closed earlier this
          morning. Hydraulic operations to reconfigure the aerosurfaces and
          landing gear have been completed. Electrical checks of the right
          hand orbital maneuvering system pod will continue today.
          Installation operations of the forward reaction control system on
          the nose of the vehicle will continue today. Power down of the
          vehicle for the holidays remains scheduled for end of first shift
          today.


 
662.31Some additional details on the mission.PRAGMA::GRIFFINDave GriffinThu Dec 27 1990 10:0952
    Re: .8
    
    With the help of the mixed-fleet manifest, we get the following
    additional information on the STS-39 payload:
    
    AFP-675 (Air Force Program-675)
       Collects infrared data to support Strategic Defense Initiative
       program.  Formerly, Cryogenic Infrared Radiance Instrument for the
       Shuttle (CIRRIS).
    
    IBSS (Infrared Background Signature Survey)
       Obtains infrared measurements on racket plumes, shortwave infrared
       Earth-limb, Shuttle environment, and chemical release from the
       payload bay while detached from the Orbiter.
    
    STP-01 (Space Test Program-01)
       STP-xx are a series of payloads which included DOD STP secondary
       experiments.  [This is being carried on a Hitchhiker-M carrier.]
    
    MPEC (Multi-Purpose Experiment Canister)
       An extended Hitchhiker-G.  Gas can capable of deploying an internally
       stowed payload.   [Hitchhiker-G is a shuttle cargo bay sidewall
       mounted carrier for small experiments, developed by the Goddard
       center.  Hitchhiker-M is the Marshall version of this concept.]
    
    
    ... And on the mid-deck ...
    
    CLOUDS-1A-1
       Hand-held 35mm photography for observations of cloud formation,
       dissipation, and opaqueness.
    
    RME IIIP03 (Radiation Monitoring Experiment)
       Measures gamma radiation levels in the Shuttle environment.
       [I think this is the instrumented human skull  -dg]
    
    
    This flight will be at 140 miles and an inclination of 57 degrees
    (would anybody care to comment on the potential visibility in the more
    northerly latitudes?).
    
    Crew of 7, duration is 8 days.
       CDR: Michael Coats
       PLT: Blaine Hammond
       MS:  Guion Bluford
       MS:  Gregory Harbaugh
       MS:  Richard Hieb
       MS:  Donald McMonagle
       MS:  Charles Veach
    
    
    
662.32visible <15 degrees from track 42326::TRAVELLJohn T, UK_Remote_Services_SupportSat Dec 29 1990 11:2424
< Note 662.31 by PRAGMA::GRIFFIN "Dave Griffin" >
>    This flight will be at 140 miles and an inclination of 57 degrees
>    (would anybody care to comment on the potential visibility in the more
>    northerly latitudes?).

    According to my (admittedly primitive) satellite visibility program,
  something orbitting at 140 miles should be visible on or above the horizon
  within 14.9 degrees either side of it's orbital track. This does not cater
  for local seeing conditions or terrain. 

  I believe an approximate calculation is as follows:-

  Angle = ArcCOS ( Radius of planet / ( Radius of planet + height of orbit ))

  or approx:-	14.9 = ACOS(4000/(4000+140)

    As to whether you may be able to see it, you need to know both the 
  latitude at which it crosses your longitude, and how close to the horizon 
  can you see objects in space.

    i.e. if you are at 50 degrees, & it crosses your latitude at 35 degrees, 
  tough... the planet gets in the way!

				John Travell. 
662.33Shuttle Status for 01/02/91 PRAGMA::GRIFFINDave GriffinThu Jan 03 1991 18:2829
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


              Wednesday January 2, 1991                 10:00 a.m. EST

                     KSC SPACE SHUTTLE PROCESSING STATUS REPORT

          -----------------------------------------------------------------

 
                     STS-39 -- Discovery (OV 103)  -  OPF Bay 1

               Power up of Discovery's electrical system is scheduled for
          later this afternoon, followed by the opening of the payload bay
          doors. The main propulsion system check valves have been
          installed and a high pressure test on the MPS system is scheduled
          for later this week.

               The forward reaction control system was not installed prior
          to the holidays as scheduled, but will be mated to the vehicle
          later this week.

               In the Vehicle Assembly Building, closeouts of the solid
          rocket boosters, previously mated with the external tank,
          continue today in high bay 1.


 
662.34Shuttle Status for 01/04/91 PRAGMA::GRIFFINDave GriffinTue Jan 08 1991 19:4028
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA
 
 
              KSC SHUTTLE STATUS REPORT - FRIDAY, JAN. 4, 1991  10 a.m.
 
 
 
                       STS-39 - DISCOVERY (OV 103) - OPF BAY 1
 
               The forward reaction control  system  (FRCS)  was  installed
          overnight.  An  interface  test  of the FRCS is planned tomorrow.
          Today,  the payload bay doors are opened and the Ku-band  antenna
          is deployed for checks.
 
               Engineers are evaluating a problem with the pilot's attitude
          director  indicator  (ADI),  a navigation aid that gives the crew
          information about the orbiter's attitude in terms of  pitch,  yaw
          and roll. Exhaust  ducts  of the three auxiliary power units were
          tested and the data are being evaluated.
 
               This  weekend,  the  crossfeed  lines  between  the  orbital
          maneuvering system pods are scheduled to be connected.
 
               Discovery  is being prepared for rollover to the Vehicle As-
          sembly Building the end of this month.
 
 
662.35Shuttle Status for 01/07/91 PRAGMA::GRIFFINDave GriffinTue Jan 08 1991 21:3021
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


              KSC SHUTTLE STATUS REPORT - MONDAY, JAN. 7, 1991  10 a.m.


 
                       STS-39 - DISCOVERY (OV 103) - OPF BAY 1

               Checkout of the forward reaction control  system  (FRCS)  is
          underway today.   Crossfeed lines between the orbital maneuvering
          system pods are being connected this week.   Tests of  the  power
          reactant  storage  and  distribution  system are scheduled.  Heat
          shields are being installed around the main engines.

               Discovery is being prepared for rollover to the Vehicle  As-
          sembly Building the end of this month.


 
662.36Shuttle Status for 01/08/91 PRAGMA::GRIFFINDave GriffinThu Jan 10 1991 13:1822
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


             KSC SHUTTLE STATUS REPORT - TUESDAY, JAN. 8, 1990  10 a.m.


 
                       STS-39 - DISCOVERY (OV 103) - OPF BAY 1

               Checkout of the forward reaction control  system  (FRCS)  is
          continuing. Checks of the orbital maneuvering system pods are un-
          derway. Tests of the power reactant storage and distribution sys-
          tem  are  scheduled.  Heat shields are being installed around the
          main engines.  Tests of the closed circuit television system  are
          underway.

               Discovery  is being prepared for rollover to the Vehicle As-
          sembly Building the end of this month.


 
662.37Shuttle Status for 01/09/91 PRAGMA::GRIFFINDave GriffinThu Jan 10 1991 13:2029
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


            KSC SHUTTLE STATUS REPORT - WEDNESDAY, JAN. 9, 1990  10 a.m.


 
                       STS-39 - DISCOVERY (OV 103) - OPF BAY 1

               Leak and functional tests of the three auxiliary power units
          are planned.  Checkout of the  forward  reaction  control  system
          (FRCS)  is  continuing.  Checks of the orbital maneuvering system
          pods are underway.  Tests of the power reactant storage and  dis-
          tribution system are scheduled.  Heat shields are being installed
          around the main engines.   Tests of the closed circuit television
          system were completed.

               Interface  tests  between  the  Critical Ionization Velocity
          system and the Chemical Release Observation have been  completed.
          These  experiments  already installed in the payload bay are part
          of the Infrared Background Signature  Survey  for  the  Strategic
          Defense Initiative.

               Discovery  is being prepared for rollover to the Vehicle As-
          sembly Building the end of this month.


 
662.38Shuttle Status for 01/10/91 PRAGMA::GRIFFINDave GriffinThu Jan 10 1991 18:0128
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


              Thursday January 10, 1991                 10:00 a.m. EST

                     KSC SPACE SHUTTLE PROCESSING STATUS REPORT

          -----------------------------------------------------------------

 
                     STS-39 -- Discovery (OV 103)  -  OPF Bay 1

               Power on testing continues today. The high point bleed valve
          on the orbital maneuvering system pods have been checked and
          verifications of the electrical connections are continuing. Water
          spray boiler servicing and potable water servicing continues
          today. The power reactant and storage distribution system's
          hydrogen line inspections continue today. Elevon cove leak checks
          and auxiliary power unit functional tests will continue today.
          Leak checks on the main propulsion system have been completed. S-
          band communications systems checks are scheduled for tomorrow.

               Members of the STS-39 crew are scheduled to arrive KSC this
          weekend for a scheduled crew equipment interface test.


 
662.39Shuttle Status for 01/11/91 PRAGMA::GRIFFINDave GriffinMon Jan 14 1991 08:5430
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


               Friday January 11, 1991                 10:00 a.m. EST

                     KSC SPACE SHUTTLE PROCESSING STATUS REPORT

          -----------------------------------------------------------------

 
                     STS-39 -- Discovery (OV 103)  -  OPF Bay 1

               Power on testing continues today. Ammonia boiler servicing
          is scheduled to resume today. The high bay will be cleared for
          this operation. Results of the routine leak checks on the main
          propulsion system are reported good. Auxiliary power unit leak
          and functional checks indicate possible lube oil seepage around
          APU number 2. Repressurization tests and additional analysis will
          be performed. Potable water servicing and main engine heatshield
          and carrier panel installation continues in work today. Elevon
          cove leak checks are complete. OMS pod verifications are
          scheduled to continue this weekend. Rollover to the VAB is
          scheduled for the end of January.

               Members of the STS-39 crew are scheduled to arrive KSC this
          weekend for a scheduled crew equipment interface test on Sunday.


 
662.40Shuttle Status for 01/15/91PRAGMA::GRIFFINDave GriffinThu Jan 17 1991 19:2127
From: NASA SpaceLink
Organization: NASA

     Tuesday January 15, 1991                 9:30 a.m. EST

           KSC SPACE SHUTTLE PROCESSING STATUS REPORT

-----------------------------------------------------------------

 
           STS-39 -- Discovery (OV 103)  -  OPF Bay 1

     Scheduled operations continue in the Orbiter Processing
Facility this week. Cross feed lines of the orbital maneuvering
system pods have been connected and leak check operations on
those lines will continue today. Final checks of the power
reactant storage and distribution system (PRSD) and water spray
boiler will also be conducted today. Following final tests on the
auxiliary power units, all three APUs have been cleared for
flight with final pressurization decay checks to continue as
scheduled. Potable water sampling tests will take place today.
Several days of hydraulic operations are scheduled for this week.
Rollout of the vehicle to the VAB is scheduled for no earlier
than January 29.


 
662.41Shuttle Status for 01/16/91PRAGMA::GRIFFINDave GriffinThu Jan 17 1991 19:2326
From: NASA SpaceLink
Organization: NASA

    Wednesday January 16, 1991                 9:30 a.m. EST

           KSC SPACE SHUTTLE PROCESSING STATUS REPORT

-----------------------------------------------------------------

 
           STS-39 -- Discovery (OV 103)  -  OPF Bay 1

     Scheduled operations continue in the Orbiter Processing
Facility this week. Leak and functional tests on the auxiliary
power units have been completed. Checks of Discovery's twin
orbital maneuvering system pods cross feed lines continue today.
The OMS actuator was checked out yesterday without any problems
identified. Extensive integrated orbiter hydraulic operations are
underway and are expected to last throughout the week. Hydraulic
operations today include functional testing of the landing gear,
brakes and nose wheel steering. Rollout of the vehicle to the
Vehicle Assembly Building is scheduled for no earlier than
January 29.


 
662.42Shuttle Status for 01/17/91PRAGMA::GRIFFINDave GriffinThu Jan 17 1991 19:2628
From: NASA SpaceLink
Organization: NASA

     Thursday January 17, 1991                 9:30 a.m. EST

           KSC SPACE SHUTTLE PROCESSING STATUS REPORT

-----------------------------------------------------------------

 
           STS-39 -- Discovery (OV 103)  -  OPF Bay 1

     Scheduled operations continue in the Orbiter Processing
Facility today. Water spray boiler servicing is complete and
hydraulic operations continue in progress. Yesterday, brake anti-
skid tests and landing gear functional tests were completed.
Discovery's twin orbital maneuvering system pods will continue to
be checked today. Sleep station installation operations are
currently in work. During helium purge operations last night,
engineers determined there may have been hydraulic fluid
introduced into the high pressure oxidizer turbopump on main
engine number three. Crews will analyze the potential problem and
make further evaluations tomorrow. Rollout of the vehicle to the
Vehicle Assembly Building remains scheduled for no earlier than
January 29.


 
662.43Shuttle Status for 01/18/91 PRAGMA::GRIFFINDave GriffinMon Jan 21 1991 10:1428
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


                Friday January 18, 1991                 9:30 a.m. EST

                     KSC SPACE SHUTTLE PROCESSING STATUS REPORT

          -----------------------------------------------------------------

 
                     STS-39 -- Discovery (OV 103)  -  OPF Bay 1

               Operations continue in the Orbiter Processing Facility today
          to prepare the orbiter Discovery for the next Space Shuttle
          mission. Crossfeed leak checks between the twin orbital
          maneuvering system pods and the forward reaction control system
          will be checked today. Final hydraulic checkouts are scheduled to
          be completed early today with flight controls and main engines
          undergoing final cycling operations. Following this, the main
          engine locks will be placed on the three engines to allow workers
          an opportunity to further check the high pressure oxidizer
          turbopump on engine number 3 for possible hydraulic fluid
          contamination. Results of this inspection are expected tonight.
          Rollout of the vehicle to the Vehicle Assembly Building is
          currently assessed to be near the end of the month.

 
662.44Payload Status Report - 01/17/91PRAGMA::GRIFFINDave GriffinMon Jan 21 1991 10:5524
From: [email protected] (Peter E. Yee)
Date: 18 Jan 91 18:47:46 GMT
Organization: NASA Ames Research Center, Moffett Field, CA

                              KSC PAYLOAD STATUS REPORT
                                  January 17, 1991


          Mitch Varnes
          407/867-2468
          FTS 823-2468
          ----------------------------------------------------------------
                             STS-39 (Late February 1991)

          Pre-flight checkouts and testing of the STS-39 payloads  continue
          to  proceed  on  schedule in both the Orbiter Processing Facility
          (OPF) and the Vertical Processing Facility (VPF).   The  CRO  and
          MPEC  payloads  are mounted in the forward section of Discovery's
          payload bay and  undergoing  checkouts  in  the  OPF.    AFP-675,
          IBSS/SPAS-2  and  STP-1  are  hanging vertially in the VPF.   The
          IBSS/SPAS-2 End-to-End Test and Interface Verification  Test  and
          STP-1  End-to-End  test  were  all  satisfactorily completed this
          week.   These three payloads are scheduled to be transported from
          the VPF to the launch pad on February 1.
662.45Shuttle Status for 01/22/91 PRAGMA::GRIFFINDave GriffinTue Jan 22 1991 17:1930
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


                 KSC SHUTTLE STATUS REPORT - TUESDAY, JAN. 22, 1991

 
                       STS-39 - DISCOVERY (OV 103) - OPF BAY 1
                            LAUNCH - FEBRUARY/MARCH 1991

          WORK COMPLETED:
          - Ku-band antenna stowed for flight.
          - Primary and  secondary  seals  in  orbital  maneuvering  system
          crossfeed lines replaced after failing leak checks.
          - All swab samples taken of main engine drain lines passed.
          - Wing structural leak check.
          - Forward reaction control system leak checks.

          WORK IN PROGRESS:
          - Tests of orbital maneuvering system crossfeed lines.
          - Fitting the thermal barrier between the external tank doors.
          - Final tire pressure measurements.
          - Potable water servicing.
          - Flush of the auxiliary power units lube oil system.

          WORK SCHEDULED:
          -  Closeouts  to  prepare  for  rollover  to the Vehicle Assembly
          Building the end of the month

 
662.46Shuttle Status for 01/23/91 PRAGMA::GRIFFINDave GriffinWed Jan 23 1991 17:4843
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


                KSC SHUTTLE STATUS REPORT - WEDNESDAY, JAN. 23, 1991

 
                     STS-39 - DoD - DISCOVERY (OV 103) - OPF BAY 1
                            LAUNCH - FEBRUARY/MARCH 1991

          WORK IN PROGRESS:
          - Tests of orbital maneuvering system crossfeed lines.
          - Fitting the thermal barrier between the external tank doors.
          - Potable water servicing.
          - Flush of the auxiliary power units lube oil system.

          WORK COMPLETED:
          - Auxiliary power unit leak and functional tests.

          WORK SCHEDULED:

          - Structural leak checks of the orbiter this weekend.
          - Final payload bay door closure this weekend.
          - Closeouts to prepare  for  rollover  to  the  Vehicle  Assembly
          Building the end of the month.


               ## STS-39 SOLID ROCKET BOOSTERS/EXTERNAL TANK - VAB

          WORK IN PROGRESS:
          - Transfer of the right forward segment to the  Vehicle  Assembly
          Building.
          - Preparations for mating the right forward segment.
          - Closeouts of all booster field joints.

          WORK COMPLETED:
          - Right forward center stacked and mated.

          WORK SCHEDULED:
          - Mate of the right forward assembly to the booster next week.


 
662.47Shuttle Status for 01/25/91 PRAGMA::GRIFFINDave GriffinMon Jan 28 1991 19:0336
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


                  KSC SHUTTLE STATUS REPORT - FRIDAY, JAN. 25, 1991

 
                     STS-39/DoD - DISCOVERY (OV 103) - OPF BAY 1
                            LAUNCH - FEBRUARY/MARCH 1991

          WORK IN PROGRESS:
          - Leak tests of two  orbital  maneuvering  system  thrusters  and
          checks of the nozzle to body welds on a third thruster.
          - New thermal barrier in cure in the nose landing gear area.
          - Potable water servicing.
          - Flush of the auxiliary power units lube oil system.
          - Connections of ordnance devices for the remote manipulator sys-
          tem.
          - Leak checks of the main engines' hot gas system.
          - Cycling of the aerosurfaces, brakes and main engine thrust vec-
          tor control system.

          WORK COMPLETED:
          - Crew hatch cycle and leak check.

          WORK SCHEDULED:

          - Structural leak checks of the orbiter this weekend.
          - Final payload bay door closure this weekend.
          -  Closeouts  to  prepare  for  rollover  to the Vehicle Assembly
          Building the end of the month.


                              KSC PAYLOAD STATUS REPORT
                                  January 25, 1991
 
662.48Shuttle Status for 01/25/91 PRAGMA::GRIFFINDave GriffinMon Jan 28 1991 19:0422
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


                  KSC SHUTTLE STATUS REPORT - FRIDAY, JAN. 25, 1991

 
                             STS-39 (Late February 1991)

          The STS-39 Payload Readiness Review  (PRR)  Flight  Certification
          Review (CFR) was held at KSC on January 24.  No major issues were
          raised during the meeting,  and all members of the STS-39 payload
          community agreed that the payloads are ready to be transported to
          the  launch  pad.     CLOUDS-1A  and  RME-III  are  situated   in
          Discovery's  mid-deck  in the Orbiter Processing Facility.   CRO,
          CIV and MPEC are also in the OPF and mounted inside  the  forward
          section of Discovery's payload bay.   AFP-675, IBSS and STP-1 are
          in the Vertical Processing Facility and scheduled to be taken  to
          Pad 39-A on or about February 3.


 
662.49Shuttle Status for 01/28/91 PRAGMA::GRIFFINDave GriffinMon Jan 28 1991 19:0735
From: [email protected] (Ron Baalke)
Organization: Jet Propulsion Laboratory, Pasadena, CA.
Nntp-Posting-Host: mars.jpl.nasa.gov

                  KSC SHUTTLE STATUS REPORT - MONDAY, JAN. 28, 1991
 
 
                     STS-39/DoD - DISCOVERY (OV 103) - OPF BAY 1
                            LAUNCH - FEBRUARY/MARCH 1991
 
          WORK IN PROGRESS:
          - Assessment of tests of two orbital maneuvering system thrusters
          and  inspections of the nozzle to body welds on a third thruster.
          - Checks of the flipper doors and elevons.
          - Cleaning of the payload bay.
          - Closeouts of the aft compartment.
 
          WORK COMPLETED:
          - Leak tests of two orbital maneuvering system thrusters and weld
          checks of a third thruster.
          - Connections of ordnance devices for the remote manipulator sys-
          tem.
          - Auxiliary power unit lube oil flush.
 
          WORK SCHEDULED:
          - Structural leak checks of the orbiter in the next few days.
          - Final payload bay door closure as early as tonight.
          - Closeouts to prepare  for  rollover  to  the  Vehicle  Assembly
          Building the end of the month.
 
          CONCERNS:
          -  Thruster  leak  rate  and  nozzle  to  body  welds  of another
          thruster. Possible replacement of thrusters.
 
 
662.50Shuttle Status for 01/29/91 PRAGMA::GRIFFINDave GriffinTue Jan 29 1991 18:4339
From: [email protected] (Ron Baalke)
Organization: Jet Propulsion Laboratory, Pasadena, CA.


                 KSC SHUTTLE STATUS REPORT - TUESDAY, JAN. 29, 1991
 
 
                     STS-39/DoD - DISCOVERY (OV 103) - OPF BAY 1
                                 LAUNCH - MARCH 1991
 
          WORK IN PROGRESS:
          - Preparations to replace three thrusters on orbital  maneuvering
          system pods.
          - Main propulsion system gaseous oxygen system leak checks.
          - Cleaning of the payload bay.
          - Closeouts of the aft compartment.
          - External tank door functional test.
 
          WORK COMPLETED:
          - Leak tests of two orbital maneuvering system thrusters and weld
          checks of a third thruster.
          - Water spray boiler steam vent nozzle replaced.
          - Check out of the flipper doors.
 
          WORK SCHEDULED:
          - Installation of three OMS thrusters on Thursday.
          - Structural leak checks of the orbiter in the next few days.
          - Final payload bay door closure tomorrow.
          -  Closeouts  to  prepare  for  rollover  to the Vehicle Assembly
          Building next week.
 
          CONCERNS:
          - Two thrusters on the left pod will be replaced because  of  out
          of  specification leakage.  One thruster on the right pod will be
          replaced because of suspect nozzle to body welds.  New  thrusters
          are  being  checked today at the Hypergolic Maintenance Facility.
          Rollover to the VAB is now targeted for Feb. 7.
 
 
662.51Shuttle Status for 01/30/91 PRAGMA::GRIFFINDave GriffinWed Jan 30 1991 18:0540
From: [email protected] (Ron Baalke)
Organization: Jet Propulsion Laboratory, Pasadena, CA.

                KSC SHUTTLE STATUS REPORT - WEDNESDAY, JAN. 30, 1991
 
 
                     STS-39/DoD - DISCOVERY (OV 103) - OPF BAY 1
                                 LAUNCH - MARCH 1991
 
          WORK IN PROGRESS:
          - Preparations to replace three thrusters on orbital  maneuvering
          system pods.
          - Main propulsion system gaseous hydrogen system leak checks.
          - Cleaning of the payload bay.
          - Closeouts of the aft compartment.
          - Checks of the inboard flipper doors.
 
          WORK COMPLETED:
          - Checks of three orbital maneuvering system thrusters at the Hy-
          pergolic Maintenance Facility to be installed on Discovery.
          - Main propulsion system gaseous oxygen system leak checks.
 
          WORK SCHEDULED:
          - Installation of three OMS thrusters on Thursday.
          - Structural leak checks of the orbiter in the next few days.
          - Final payload bay door closure tonight.
          -  Closeouts  to  prepare  for  rollover  to the Vehicle Assembly
          Building next week.
 
          CONCERNS:
          - Two thrusters on the left pod will be replaced because  of  out
          of  specification leakage.  One thruster on the right pod will be
          replaced because of suspect nozzle to body welds.  New  thrusters
          have  been  checked  and will be delivered to the OPF today.  Re-
          placement operations are scheduled to begin at midnight and  will
          continue  through  tomorrow.  Thruster connections and retest ac-
          tivities are scheduled to be complete by Sunday.  Rollover to the
          VAB is targeted for Feb. 7.
 
 
662.52Shuttle Status for 01/31/91 PRAGMA::GRIFFINDave GriffinThu Jan 31 1991 19:4627
From: [email protected] (Ron Baalke)
Organization: Jet Propulsion Laboratory, Pasadena, CA.


                 KSC SHUTTLE STATUS REPORT - THURSDAY, JAN. 31, 1991
 
 
                     STS-39/DoD - DISCOVERY (OV 103) - OPF BAY 1
                                 LAUNCH - MARCH 1991
 
          WORK IN PROGRESS:
          - Replacement of three thrusters on  orbital  maneuvering  system
          pods.  The high bay is cleared of all non-essential personnel for
          this activity. The bay will be opened tomorrow morning for normal
          work.
 
          WORK COMPLETED:
          - Payload bay cleaning and door closure last night.
          - Midbody closeouts.
 
          WORK SCHEDULED:
          - Structural leak checks of the orbiter next week.
          - Weight and center of gravity checks.
          - Closeouts to prepare  for  rollover  to  the  Vehicle  Assembly
          Building on Feb. 7.
 
 
662.53Shuttle Status for 02/01/91 PRAGMA::GRIFFINDave GriffinMon Feb 04 1991 18:2136
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


                  KSC SHUTTLE STATUS REPORT - FRIDAY, FEB. 1, 1991

 
                     STS-39/DoD - DISCOVERY (OV 103) - OPF BAY 1
                                 LAUNCH - MARCH 1991

          WORK IN PROGRESS:
          - Replacement of a third thruster on the right orbital  maneuver-
          ing  system  pod.  The bay is opened for limited access today and
          will be reopened for normal work tomorrow.
          - Pressurization of the main landing gear struts.
          - Thermal protection system operations.
          - As part of the troubleshooting of the waste water  dump  system
          problem  experienced on STS-35,  technicians removed and replaced
          the filter package on Discovery.  The three polyurethane  filters
          in the package removed from Discovery were found to be in various
          states  of  degradation.  The  degradation  appears to be natural
          deterioration due to age.  The filter package currently installed
          in  Discovery  is new and there are no concerns about its perfor-
          mance.

          WORK COMPLETED:
          - Replacement of two thrusters on the  left  orbital  maneuvering
          system pod.

          WORK SCHEDULED:
          -  Structural  leak checks of the orbital maneuvering system pods
          this weekend.
          - Structural leak checks of the orbiter next week.
          - Weight and center of gravity checks.

 
662.54Shuttle Status for 02/04/91 PRAGMA::GRIFFINDave GriffinTue Feb 05 1991 15:4732
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


                  KSC SHUTTLE STATUS REPORT - MONDAY, FEB. 4, 1991

 
                     STS-39/DoD - DISCOVERY (OV 103) - OPF BAY 1
                                 LAUNCH - MARCH 1991

          WORK IN PROGRESS:
          - Evaluation of a heater on the newly replaced thruster, R3A.
          - Thermal protection system operations.
          - Removal  of  platforms  in  the  aft  compartment  as  part  of
          closeouts.

          WORK COMPLETED:
          - Replacement and retest of three thrusters on the left and right
          orbital maneuvering system pods.
          - Successful flushes of the waste water system.
          - Removal of the payload bay door strongbacks.

          WORK SCHEDULED:
          -  Structural  leak checks of the orbital maneuvering system pods
          this week.
          - Structural leak checks of the orbiter.
          - Weight and center of gravity checks.
          - Rollover to the Vehicle Assembly Building no earlier than
            Feb. 7.


 
662.55Shuttle Status for 02/05/91 PRAGMA::GRIFFINDave GriffinTue Feb 05 1991 18:0428
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


                  KSC SHUTTLE STATUS REPORT - TUESDAY, FEB. 5, 1991

 
                     STS-39/DoD - DISCOVERY (OV 103) - OPF BAY 1
                                 LAUNCH - MARCH 1991

          WORK IN PROGRESS:
          - Repair of a heater wire for thruster R3A.
          - Thermal protection system operations.
          - Preparations for the positive pressure structural leak test.
          - Vehicle closeouts in preparation for transfer to the VAB.
          - Closeouts of the flipper doors which protect  elevon  actuators
          and hinges.

          WORK COMPLETED:
          - Final tire checks of the nose landing gear.

          WORK SCHEDULED:
          - Structural leak checks of the orbiter.
          - Weight and center of gravity checks.
          -  Rollover to the Vehicle Assembly Building targeted for late on
          Feb. 8.

 
662.56Shuttle Status for 02/06/91 PRAGMA::GRIFFINDave GriffinWed Feb 06 1991 18:1141
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


                 KSC SHUTTLE STATUS REPORT - WEDNESDAY, FEB. 6, 1991

 
                     STS-39/DoD - DISCOVERY (OV 103) - OPF BAY 1
                                 LAUNCH - MARCH 1991

          WORK IN PROGRESS:
          - Retest of a replaced heater wire for thruster R3A.
          - Preparations for the positive pressure structural leak test.
          - Vehicle closeouts in preparation for transfer to the VAB.
          - Closeouts of the flipper doors which protect  elevon  actuators
          and hinges.

          WORK COMPLETED:
          - Repair of the heater wire for thruster R3A.
          - Replacement of the left hand nose landing gear tire and top off
          of the tire pressure.
          -  Replacement of the thermal barrier near the left external tank
          door foward hinge.

          WORK SCHEDULED:
          - Structural leak checks of the orbiter later today.
          - Weight and center of gravity checks.
          - Rollover to the Vehicle Assembly Building targeted for Feb. 9.

          ## STS-39 BOOSTERS/TANK - VAB

          WORK IN PROGRESS:
          - Preparations to mate the orbiter Discovery Saturday.
          - Final walkdown for mate.

          WORK SCHEDULED:
          - Retraction of platforms away from the vehicle elements.
          - Mating the orbiter Saturday.


 
662.57Shuttle Status for 02/07/91 PRAGMA::GRIFFINDave GriffinThu Feb 07 1991 21:5130
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


                 KSC SHUTTLE STATUS REPORT - THURSDAY, FEB. 7, 1991

 
                     STS-39/DoD - DISCOVERY (OV 103) - OPF BAY 1
                                 LAUNCH - MARCH 1991

          WORK IN PROGRESS:
          - Troubleshooting of the heater for one of the thrusters (R3A) on
          the right orbital  maneuvering  system  pod.  The  heater  failed
          retests.
          -  Positive  pressure  structural  leak test of the orbiter's aft
          compartment.
          - Vehicle closeouts in preparation for transfer to the VAB.

          WORK COMPLETED:
          - Positive pressure structural leak test of the orbital maneuver-
          ing system pods.
          - Closeouts of the elevon flipper doors.
          - Air Force Program 675 payload arrived at Pad  A  at  3:35  a.m.
          today.

          WORK SCHEDULED:
          - Weight and center of gravity checks.
          - Rollover to the Vehicle Assembly Building targeted for Feb. 9.

 
662.58Shuttle Status for 02/08/91 PRAGMA::GRIFFINDave GriffinFri Feb 08 1991 19:1744
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


                  KSC SHUTTLE STATUS REPORT - FRIDAY, FEB. 8, 1991

 
                     STS-39/DoD - DISCOVERY (OV 103) - OPF BAY 1
                                 LAUNCH - MARCH 1991


          WORK IN PROGRESS:
          - Orbiter weight and center of gravity determination.
          - Vehicle closeouts in preparation for transfer to the VAB.

          WORK COMPLETED:
          - Positive pressure structural leak test of the aft compartment.
          - Troubleshooting of the heater for a thruster on the right orbi-
          tal maneuvering system pod revealed that the heater is good.  The
          problem  has  been isolated to a cable harness routed between the
          logic control assembly and  the  thruster.  More  troubleshooting
          work  will be performed in the Vehicle Assembly Building once ac-
          cess to the aft compartment can be obtained.

          WORK SCHEDULED:
          - Attaching the orbiter to the transporter.
          - Rollover to the Vehicle Assembly  Building  tomorrow  afternoon
          and mate to the external tank.

          ## STS-39 BOOSTERS/TANK - VAB

          WORK COMPLETED:
          - Retraction of platforms away from the boosters and tank.
          - Preparations  to  mate  the  external  tank  and  solid  rocket
          boosters with the Orbiter Discovery.

          WORK SCHEDULED:
          - Mating the orbiter to the external tank this weekend.
          - Shuttle Interface Test next week.
          - Rollout to Launch Pad 39-A targeted for Feb. 15.



 
662.59Shuttle Status for 02/11/91 PRAGMA::GRIFFINDave GriffinTue Feb 12 1991 18:5527
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


            KSC SHUTTLE STATUS REPORT - MONDAY, FEB. 11, 1991 - 9:30 a.m.

 
                        STS-39/DoD - DISCOVERY (OV 103) - VAB
                                 LAUNCH - MARCH 1991

          WORK IN PROGRESS:
          - Electrical mates between the orbiter and external tank.
          - Preparations for the  Shuttle  Interface  Test  which  verifies
          critical  connections between the vehicle elements and the launch
          platform.
          - Installation of platforms in the aft compartment.

          WORK COMPLETED:
          - Transferred to the VAB Saturday afternoon.
          - Discovery hard mated to the external tank 8:57 p.m. last night.

          WORK SCHEDULED:
          - Troubleshooting cable harness between the  orbital  maneuvering
          system thrusters and the logic control assembly.
          - Rollout to Launch Pad 39-A Friday morning.

 
662.60Shuttle Discovery hauled to launch padPRAGMA::GRIFFINDave GriffinSat Feb 16 1991 14:2846
From: [email protected] (WILLIAM HARWOOD, UPI Science Writer)
Date: 15 Feb 91 12:15:47 GMT

	CAPE CANAVERAL, Fla. (UPI) -- The shuttle Discovery was hauled to its
oceanside launch pad Friday for blastoff March 9 on an unclassified
eight-day ``Star Wars'' research mission to learn more about detecting
missiles in flight.
	Mounted atop a ponderous crawler-transporter, Discovery and its
mobile launch stand began the six-hour trip from the Vehicle Assembly
Building to launch pad 39A at 12:43 a.m.
	Engineers planned to install experimental Air Force and Strategic
Defense Initiative -- ``Star Wars'' -- instruments in Discovery's cargo
bay Saturday, but deteriorating weather could hamper other weekend work
at the launch complex.
	High winds were expected Friday afternoon and temperatures at the
sprawling shuttleport were expected to plunge to 23 degrees by Sunday
morning.
	``It's going to be uncomfortable for the people working out there,''
said NASA spokeswoman Lisa Malone.
	Nonetheless, Discovery's crew plans to fly to the Kennedy Space
Center on Monday for a dress-rehearsal countdown Tuesday and Wednesday
that will end with the simulated ignition and shutdown of the shuttle's
main engines.
	Sources said Vice President Dan Quayle, chairman of the National
Space Council, plans to visit the spaceport Wednesday for a tour of
agency facilities.
	An official launch date will not be set until after top NASA managers
hold a flight readiness review Feb. 26 and 27 but engineers are shooting
for a March 9 liftoff at 3:49 a.m. to end a winter lull in shuttle
missions. The last flight came in December.
	The goal of the 14th post-Challenger shuttle mission, the first of
seven planned for 1991, is to learn more about how to detect rockets in
flight, a critical element of the Strategic Defense Initiative missile
defense program.
	Discovery's seven-man crew will work around the clock in two shifts
throughout the busy mission, launching and retrieving one satellite and
deploying three other smaller ``sub-satellites'' during the course of
the flight.
	Commander Michael Coats, 45, a Navy captain, co-pilot Blaine Hammond,
39, a lieutenant colonel in the Air Force, Richard Hieb, 35, and Charles
Lacy Veach, 46, will staff Discovery during the overnight, or ``red,''
shift.
	Gregory Harbaugh, 34, Air Force Col. Guion Bluford, 48, and Air Force
Lt. Col. Donald McMonagle, 38, make up the daytime ``blue'' shift.
	Assuming an on-time launch, landing is scheduled for 11:14 a.m. on
March 17 at Edwards Air Force Base, Calif.
662.61Fuel Line Crack?LANDO::STONETue Feb 19 1991 12:244
    I heard on the radio this morning that a "crack" was found in a LH2 
    line.  No details were given as to its location or what impact this
    was going to have on the schedule.  The countdown demonstration test
    was going to proceed as planned today.
662.62Shuttle Status for 02/12/91 PRAGMA::GRIFFINDave GriffinTue Feb 19 1991 17:3622
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA

           KSC SHUTTLE STATUS REPORT - TUESDAY, FEB. 12, 1991 - 9:30 a.m.

 
                        STS-39/DoD - DISCOVERY (OV 103) - VAB
                                 LAUNCH - MARCH 1991

          WORK IN PROGRESS:
          - Electrical connections between the orbiter and external tank.
          - Preparations to power up the orbiter today.
          - Start of the Shuttle Interface  Test  which  verifies  critical
          connections between the vehicle elements and the launch platform.
          - Installation of platforms in the aft compartment.

          WORK SCHEDULED:
          -  Troubleshooting  cable harness between the orbital maneuvering
          system thrusters and the logic control assembly.
          - Rollout to Launch Pad 39-A targeted for Friday at 12:01 a.m.

 
662.63Shuttle Status for 02/13/91 PRAGMA::GRIFFINDave GriffinTue Feb 19 1991 17:3727
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


          KSC SHUTTLE STATUS REPORT - WEDNESDAY, FEB. 13, 1991 - 9:30 a.m.

 
                        STS-39/DoD - DISCOVERY (OV 103) - VAB
                                 LAUNCH - MARCH 1991

          WORK IN PROGRESS:
          - Closeouts of the electrical monoball  connections  between  the
          orbiter and external tank.
          - Replacement of the load control assembly, the electronic box in
          the aft compartment,  which controls the power load for the orbi-
          tal maneuvering system thruster heaters.

          WORK SCHEDULED:
          - Rollout to Launch Pad 39-A targeted for Friday at 12:01 a.m.
          - Terminal Countdown Demonstration Test Feb. 19-20.
          - Flight Readiness Review Feb. 26-27.

          WORK COMPLETED:
          - Electrical connections between the orbiter and external tank.
          - Critical parts of the Shuttle Interface Test.

 
662.64Shuttle Status for 02/14/91 PRAGMA::GRIFFINDave GriffinTue Feb 19 1991 17:3934
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


           KSC SHUTTLE STATUS REPORT - THURSDAY, FEB. 14, 1991 - 9:30 a.m.


 
                        STS-39/DoD - DISCOVERY (OV 103) - VAB
                                 LAUNCH - MARCH 1991

          WORK IN PROGRESS:
          - Power down the orbiter and prepare to roll to the launch pad.

          WORK SCHEDULED:
          - Rollout to Launch Pad 39-A targeted for Friday at 12:01 a.m.
          - Install payload in Discovery's payload bay Saturday.
          - Terminal Countdown Demonstration Test Feb. 19-20.
          - Flight Readiness Review Feb. 26-27.
          - Replacement of the load control assembly (LCA),  the electronic
          box in the aft compartment, which controls the power load for the
          orbital maneuvering system thruster heaters.  Rails used to lower
          the unit out of the aft compartment were not  in  place  by  late
          yesterday  when  power  up  was  scheduled.  Officials decided to
          proceed on with planned power up tests,   reconnect the  old  LCA
          unit and replace it on Sunday.

          WORK COMPLETED:
          -  Electrical monoball connections between the orbiter and exter-
          nal tank.
          - Critical parts of the Shuttle Interface Test.


 
662.65Multiple cracks found in Discovery fuel line doorPRAGMA::GRIFFINDave GriffinTue Feb 19 1991 17:4269
From: [email protected] (WILLIAM HARWOOD, UPI Science Writer)
Date: 19 Feb 91 18:26:47 GMT

	CAPE CANAVERAL, Fla. (UPI) -- Three cracked hinges in two critical
fuel line doors threaten a major delay for the shuttle Discovery's
planned March 9 takeoff on an eight-day ``Star Wars'' research mission,
NASA officials said Tuesday.
	Agency managers held out hope that Discovery could be launched as is
-- or quickly repaired at the pad -- keeping the year's first shuttle
mission on schedule for liftoff at 3:49 a.m. EST March 9.
	But because of concern about verifying the success of any such repair
job, a reliable source said a roll back to the hangar for repairs was 
``a strong possibility'' and that launch could be delayed up to a month,
after a mission by the shuttle Atlantis in late March or early April.
	Why the cracks were not detected before Discovery's roll out to pad
39A Friday was not immediately clear. In any case, a decision on how to
proceed was expected by late Wednesday or early Thursday.
	In the meantime, engineers at the Kennedy Space Center started a two-
day practice countdown for Discovery Tuesday, a major milestone in a
shuttle's launch processing.
	The shuttle's seven-man crew -- commander Michael Coats, 45, co-pilot
Blaine Hammond, 39, Gregory Harbaugh, 34, Charles Lacy Veach, 46, Guion
Bluford, 48, Richard Hieb, 35, and Donald McMonagle, 38 -- planned to
strap in aboard the shuttle Wednesday for the final hours of the mock
countdown.
	The crack problem, which is unrelated to the fuel leaks that plagued
NASA last year, came to light amid preparations for a visit by Vice
President Dan Quayle, chairman of the National Space Council. Quayle
planned to chat with the astronauts by radio during a visit to the
launch control center Wednesday.
	With Discovery already running 11 days behind schedule because of
work to replace three leaky steering rockets, a quality inspector Monday
discovered a 1-inch L-shaped crack in the hinge of a critical 50-inch-
square fuel line door located in the belly of the shuttle.
	By early Tuesday, engineers had found that three of four hinges used
with two such doors had cracks, two of them measuring 1 inch long and 0.
1 inch wide. And inspectors found what appeared to be a hairline crack
in one of the fuel line doors used by the shuttle Atlantis.
	While Discovery's cracks are small, they involve critical mechanisms.
The doors, which act something like protective gas cap lids, are located
in the belly of the shuttle where 17-inch-wide liquid oxygen and liquid
hydrogen fuel lines from the ship's external tank enter the orbiter's
engine room.
	After the shuttle reaches orbit, the external tank is jettisoned and
the doors, which are covered with heat-shield tiles, close over the
openings. Failure of either door to close tightly could prove disastrous
during re-entry, when the shuttle's belly is subjected to extreme heat.
	``The linkage of those doors is a pretty big deal,'' said a shuttle
manager. ``The failure mode would be if the door wouldn't close.''
	Engineers are trying to determine whether the cracks were present in
earlier flights and whether it might be safe to launch Discovery as is.
Another repair option would be to bolt the cracked hinge mechanisms
together.
	But the only way to prove the doors would work properly after any
such repair job would be to close them and check. But that cannot be
done without first removing the shuttle from its external tank, a
procedure that can only be accomplished inside the Vehicle Assembly
Buildling.
	In the meantime, Discovery remains tentatively scheduled to take off
at 3:49 a.m. EST March 9 to kick off an eight-day mission devoted to
gathering data about how to detect enemy missiles in flight, a key
element of the Strategic Defense Initiative -- ``Star Wars'' -- missile
defense program.
	Working around the clock in two shifts, Discovery's crew plans to
launch and retrieve one satellite and to deploy three small ``sub-
satellites'' before landing at Edwards Air Force Base, Calif., to close
out the 39th shuttle mission.


662.6619576::FISHERPursuing an untamed ornothoidTue Feb 19 1991 18:038
BTW, I discovered over the weekend that I know the Principal Investigator
for the IR Background Survey experiment!  I saw him with an STS-39 sweater
on and asked him about it.

Interesting stuff, even though I'm not an especially gung-ho military-loving
person.

Burns
662.67Shuttle Status for 02/19/91 PRAGMA::GRIFFINDave GriffinWed Feb 20 1991 20:1745
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


           KSC SHUTTLE STATUS REPORT - TUESDAY, FEB. 19, 1991 - 9:30 a.m.

 
                        STS-39/DoD - DISCOVERY (OV 103) - VAB
                                 LAUNCH - MARCH 1991

          WORK IN PROGRESS:
          - Evaluation of cracks in hinges for the external tank right  and
          left doors. (See concerns.)
          -  Helium  signature leak test of the three main engines and main
          propulsion system.
          - Terminal Countdown Demonstration Test Feb.   began this morning
          and  will  culminate  with  a  simulated engine cutoff at 11 a.m.
          tomorrow.
          - Interface verification tests between the payload  and  the  or-
          biter.
          - Retest of the load control assembly.

          WORK COMPLETED:
          -  Installation  of  the  STS-39  payload into Discovery's bay on
          Saturday.
          - Replacement of the load control assembly, the electronic box in
          the aft compartment,  which controls the power load for the orbi-
          tal maneuvering system thruster heaters.
          - STS-39 flight crew arrived yesterday morning.
          - Successful tests of the new gaseous nitrogen hydrogen dispersal
          system on the mobile launcher platform.

          WORK SCHEDULED:
          - Flight Readiness Review Feb. 26-27.

          CONCERNS:
          -  During closeout inspections of Discovery's external tank doors
          yesterday morning, several cracks were discovered.  There are two
          hinges  per door.  Cracks have been detected in three of the four
          hinges.  Two of the cracks have been described as being 2  inches
          long  by  approximately  one-tenth  inch wide.  Engineers will be
          evaluating data over the next few  days  to  determine  the  best
          course of action.

 
662.68Discovery cracks studiedPRAGMA::GRIFFINDave GriffinThu Feb 21 1991 19:4781
From: [email protected] (WILLIAM HARWOOD, UPI Science Writer)
Date: 21 Feb 91 17:38:45 GMT
Lines: 78

	CAPE CANAVERAL, Fla. (UPI) -- NASA is readying the shuttle Discovery
for takeoff March 9, hopeful tests will show the ship can be safely
launched without time-consuming work to fix cracks in critical hinges,
officials said Thursday.
	At least one of two large cracks may have been caused by a bolt
lodged in the hinge mechanism of a critical fuel line door last summer
when Discovery was being prepared for an October flight. But engineers
cannot explain what might have caused a similar crack in a second such
door.
	Based on metallurgical analysis, ``They have conclusive evidence that
the cracks have been there for a while,'' said NASA spokesman James
Hartsfield. ``They don't have conclusive evidence that the bolt caught
in the right-hand door caused the problem.''
	Engineers are studying a test using the shuttle Columbia in which an
undamaged hinge mechanism would be modified to simulate a worst-case
crack. If the door still works properly, and many engineers believe it
will, NASA managers could elect to launch Discovery as is and on time.
	As for NASA's other two shuttles, Columbia and Atlantis, engineers
have found no signs of cracking, although evidence of fatigue and stress
are evident.
	In the meantime, engineers continued routine launch processing,
including plans to pump liquid oxygen and liquid hydrogen on board
Discovery late Thursday to power the ship's electrical generators.
	Pending resolution of the crack issue, launch on an eight-day ``Star
Wars'' research mission, the first of seven flights planned for 1991,
remains scheduled for 3:49 a.m. EST March 9.
	The cracks -- there are three in all -- involve eighth-of-an-inch-thick
plates in the hinge mechanisms of two fuel line covers in the belly of
the orbiter. The doors must close properly after the ship's external
fuel tank is jettisoned in space to allow a safe re-entry into Earth's
atmosphere.
	The hinge assemblies in question do not hold the doors on the shuttle
and do not bear any weight on the launch pad. Rather, they involve the
drive mechanisms that must shut the doors in the weightlessness of
space.
	Troubleshooters and agency officials are debating three options:
launching Discovery as is, attempting an on-the-pad repair job or
ordering a roll back to the hangar, a move that likely would delay
takeoff until after an early-April flight by the shuttle Atlantis.
	No decisions on how to proceed are expected until after ground tests
are conducted. Hartsfield said the proposed test using Columbia could
resolve the matter.
	``The theory is the door will still open and shut fine,'' Hartsfield
said. ``The test they're doing is real conservative. They're going to
test it as if it completely failed. If you pass that, you've got a lot
of options. But that's not to say a roll back isn't a possibility.
You've still got three options.''
	But NASA managers Thursday were clearly more optimistic about
avoiding a schedule-wrecking rollback than when the crack issue first
surfaced Monday.
	Hartsfield said the bolt lodged in Discovery's right-side door last
July was noticed when the panel was 20 degrees away from being fully
closed. The door-closing procedure was stopped immediately and the bolt
was removed.
	At the time, officials said no damage resulted and Hartsfield said
there was no proof the incident had anything to do with the large crack.
	As for the left-side door, engineers had problems getting it closed
during recent processing, before Discovery was attached to its external
tank, and it was slammed shut with more force than usual. But again, no
problems were evident.
	``They measured all the hinge mechanisms ... to see if they were
extended or distended and they meet specifications completely,''
Hartsfield said.
	Still, proving Discovery can be safely launched without repairs
represents a daunting engineering challenge because the doors cannot be
directly tested at the launch pad.
	Before the shuttle reaches orbit, the doors are locked open so 17-
inch fuel lines can enter the ship's engine room. After reaching orbit,
the external tank is jettisoned and the doors, which are covered with
heat-shield tiles, close over the fuel line openings.
	Failure of either door to tightly close could result in the
destruction of a shuttle during re-entry, when the belly of the ship is
exposed to extreme temperatures because of atmospheric friction.
	With the 17-inch fuel lines in the way, Discovery's doors cannot be
closed to ensure proper operation. The only way to ``cycle'' the doors
is to first remove the ship from the external tank, a move that requires
a trip back to the Vehicle Assembly Building.
662.69Utah State University payload set to launch on Space ShuttlePRAGMA::GRIFFINDave GriffinFri Feb 22 1991 18:2661
From: [email protected] (LANCE GURWELL)
Date: 21 Feb 91 23:38:38 GMT

	SALT LAKE CITY (UPI) -- One of the payloads the crew of the space
shuttle Discovery will put into orbit next month is composed mostly of
equipment and experiments constructed at Utah State University -- whick
is better known for its agriculture department.
	While much of USU's research is on making farm crops grow better, one
NASA official has dubbed it ``Utah Space University.''
	While problems might cause a delay on the next launch of the shuttle,
set for March 9, USU students and faculty are excited about one of its
primary payloads.
	CIRRIS 1A, an infrared sensor designed and manufactured at the Space
Dynamics Lab at USU for the Air Force Geophysics Laboratory, Hanscom Air
Force Base, Mass.
	CIRRIS stands for Cryogenic Infrared Radiance Instrument for Shuttle.
A cryogenically-cooled optical instrument, CIRRIS's telescope portion
measures 9 feet in length, and will examine the upper reaches of the
Earth's atmosphere and the aurora so scientists can determine their
makeup and dynamic behavior.
	It's one of three experiments built by USU's space lab, and it weighs
about two tons.
	The telescope will also have unnamed applications to the nation's
Strategic Defense Initiative, or ``Star Wars'' program, said Frank Redd,
director of the school's Center for Space Engineering.
	Also on board will be the Infrared Background Signature Survey and
the Shuttle Kinetic Infrared Test. The IBSS was built in Germany and
calibrated at USU; SKIRT was made by Space Systems Engineering, a USU
spinoff firm located at the university's Research and Technology Park.
	IBSS has a purpose similar to CIRRIS, but it will look at the
atmosphere from a vantage point outside the shuttle, while CIRRIS
remains inside the shuttle cargo bay. IBSS will also look at the shuttle
itself to map the infrared emission from shuttle thrusting systems.
	SKIRT will measure the infrared signature of the ``shuttle glow''
which was first discovered in 1982 during deployment of a USU experiment
on the third shuttle flight.
	Scientists do not know just what causes ``shuttle glow,'' Redd said,
and it ishoped SKIRT will help explain the phenomenon. Additionally,
scientists may learn that objects have unique infrared signatures that
can be measured and used to identify objects in space.
	``We're interested in finding out how big it is, how far it extends
beyond the spacecraft,'' Redd said.
	CIRRIS will help scientists understand the makeup of the upper
atmosphere, Redd said, and therefore scientists will better understand
the dynamics of atmospheric phenomenon and be able to discriminate
objects in high atmospheric, or low orbits, from their backgrounds.
	It is cryogenically cooled to temperatures just degrees above
absolute zero because the infrared sensors are so sensitive that any
heat produced by CIRRIS itself would mask the signals, Redd said.
	The aurora borealis is seen in the northern hemisphere and is
believed to be produced by atomic particles striking atoms in the
ionosphere about 35 miles above the Earth.
	When scientists can understand details of the upper atmosphere, they
will be able to better detect other objects against that background,
including missiles.
	Two teams of scientists from the Space Dynamics Lab and the Air Force
Geophysics Lab will be in Houston and in constant contact with the
shuttle crew during the mission, Redd said.
	The experiments will be operated from the shuttle deck by astronauts
Guion S. Bluford, Jr., and Charles L. ``Lacy'' Veach, who have been
trained by the project teams.
662.70Shuttle Status for 02/22/91 PRAGMA::GRIFFINDave GriffinFri Feb 22 1991 18:2840
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


            KSC SHUTTLE STATUS REPORT - FRIDAY, FEB. 22, 1991 - 9:30 a.m.

 
                       STS-39/DoD - DISCOVERY (OV 103) - PAD A
                                 LAUNCH - MARCH 1991

          WORK IN PROGRESS:
          - Evaluation of cracks in hinges for the external tank right  and
          left doors. (See concerns.)
          -  Loading hypergolic propellants onboard the orbiter was delayed
          while a hypergolic valve on support equipment was  replaced.  Hy-
          pergolic loading is scheduled to start this morning. The pad will
          be  cleared of all non-essential personnel for this operation and
          will remain closed until Saturday.

          WORK COMPLETED:
          - Retest of the thruster heater on the right orbital  maneuvering
          system pod.
          - Part two of the hydrogen dispersal system blowdown.

          WORK SCHEDULED:
          - Main engine flight readiness test on Monday.
          - Flight Readiness Review Feb. 26-27. The review may begin on the
          27th  to  allow  officials  time  to evaluate data on the cracked
          hinges.

          CONCERNS:
          - Tests are planned this weekend on the orbiter Columbia  to  try
          to duplicate the situation on Discovery. Columbia's external tank
          doors will be cycled several times and evaluated.  After the test
          scheduled this weekend, and analysis of the results by early next
          week,  officials will determine the best course of  action.  Pre-
          launch  activities  for STS-39 will continue as scheduled until a
          determination is made.

 
662.71STS-39 Press Kit AvailablePRAGMA::GRIFFINDave GriffinFri Feb 22 1991 19:5913
The STS-39 Press Kit is available from:

   Pragma::Public:[NASA]STS-39.ps


This and other NASA press kits are available from this area.


- dave

[I have released the press kit without the mission patch.   If all goes well,
 the updated document will be there after 10:00 AM monday morning (25-Feb)
 with the STS-39 mission logo  -dg]
662.72NASA debates Discovery launchPRAGMA::GRIFFINDave GriffinMon Feb 25 1991 18:2967
From: [email protected] (WILLIAM HARWOOD, UPI Science Writer)
Date: 25 Feb 91 18:20:36 GMT

	CAPE CANAVERAL, Fla. (UPI) -- Weekend tests involving the shuttle
Columbia went well, officials said Monday, raising hopes the shuttle
Discovery can take off on time March 9, without any time-consuming work
to fix a pair of cracked hinges.
	But NASA officials said a final decision on whether to proceed with
Discovery's launch or to delay the flight for repairs, possibly until
after an early April mission by the shuttle Atlantis, would not be made
until after a two-day flight readiness review Wednesday and Thursday.
	Still, sources said, agency managers were increasingly hopeful about
the possibility of launching Discovery on time, without any major
repairs.
	``We're cautiously optimistic,'' said one manager. ``But we have more
analysis and reviews to get through before we can make that
announcement.''
	Engineers planned to hold a cross-country teleconference Monday
afternoon to discuss the tests with Columbia and what to do about the
cracks in the hinge mechanisms of two critical fuel line doors in
Discovery's belly that must close properly before the ship re-enters
Earth's atmosphere.
	Three options have been under study: launching Discovery as is,
fixing the cracks at the launch pad or rolling the shuttle back to its
hangar for repairs, a move that would delay the mission until after an
April 4 takeoff by Atlantis.
	To find out how serious the problem is, engineers ran a series of
tests over the weekend in which similar hinges on the shuttle Columbia
were modified to simulate a worst-case failure.
	While the tests continued Monday, the door in question appeared to
work properly despite the deliberate flaws, officials said.
	NASA managers, however, refused to rule out any options until
complete test results were in, saying no final decisions on when
Discovery might be launched would be made until after the flight
readiness review later this week.
	In the meantime, engineers and technicians at launch pad 39A pressed
on with work to ready Discovery for blastoff March 9 at 3:49 a.m. EST to
kick off an unclassified eight-day ``Star Wars'' research mission to
learn more about how to detect enemy missiles in flight.
	Discovery's flight is the first of seven planned for 1991 and many
agency observers believe a rollback to the hangar for repairs would push
at least one mission into 1992.
	But given the critical nature of the fuel line doors, NASA managers
stressed that Discovery will not be cleared for launch until engineers
are satisfied it is safe to do so.
	The doors, covered with heat-shield tiles, are folded back and locked
open during launch, allowing 17-inch-wide fuel lines from the external
tank to deliver propellant to Discovery's three main engines.
	After the shuttle reaches orbit, the tank is jettisoned and the doors
are closed over the fuel line connectors. Because the belly of the
orbiter bears the brunt of re-entry heating, the doors must close
properly to prevent possibly catastrophic damage to the shuttle
fuselage.
	``It's a (major) failure,'' said a NASA manager. ``There's nothing
that we know of that you can go do if that door doesn't close.''
	The cracks involve eighth-of-an-inch-thick plates in the hinge
mechanisms of the two doors. The hinge assemblies in question do not
hold the doors on the shuttle and do not bear any weight on the launch
pad. Rather, they involve the drive mechanisms that must shut the doors
in the weightlessness of space.
	At least one of two large cracks may have been caused by a bolt
lodged in the hinge mechanism of one of the doors last summer when
Discovery was being prepared for an October mission. But engineers have
no ready explanation for what might have caused a similar crack in the
other door.
	Two smaller cracks were found in fuel line doors aboard Columbia but
none was found with Atlantis.
662.73Shuttle Status for 02/25/91 PRAGMA::GRIFFINDave GriffinMon Feb 25 1991 18:3135
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


            KSC SHUTTLE STATUS REPORT - MONDAY, FEB. 25, 1991 - 9:30 a.m.

 
                       STS-39/DoD - DISCOVERY (OV 103) - PAD A
                                 LAUNCH - MARCH 1991

          WORK IN PROGRESS:
          - Evaluation of cracks in hinges for the external tank right  and
          left umbilical doors. (See concerns.)
          - Main engine flight readiness test.

          WORK COMPLETED:
          - Loading of hypergolic propellants on board the orbiter was com-
          pleted Saturday.
          -  Retest of the thruster heater on the right orbital maneuvering
          system pod.
          - Part two of the hydrogen dispersal system blowdown.

          WORK SCHEDULED:
          - Installation of ordnance devices on Wednesday.
          - Flight Readiness Review this week.

          CONCERNS:
          - Tests are underway on the orbiter  Columbia  to  duplicate  the
          cracked  hinge  situation on Discovery.  Columbia's external tank
          doors will be cycled several times and  evaluated.  Test  results
          will  be analyzed and officials will determine the best course of
          action.   Pre-launch  activities  for  STS-39  will  continue  as
          scheduled until a determination is made.

 
662.74UPI: NASA debates Discovery launchPRAGMA::GRIFFINDave GriffinTue Feb 26 1991 18:1864
From: [email protected] (WILLIAM HARWOOD, UPI Science Writer)
Date: 25 Feb 91 20:46:57 GMT

	CAPE CANAVERAL, Fla. (UPI) -- Preliminary test results indicate the
shuttle Discovery can be safely launched March 9 without taking time to
fix cracks in key hinge assemblies, but more study is needed before a
final decision is made, officials said Monday.
	Dan Germany, a top manager at the Johnson Space Center in Houston,
said the cracks in two fuel line doors apparently happened as a result
of unexpected metal fatigue due to ground crews repeatedly opening and
closing the panels between missions as part of routine processing.
	He said preliminary test results involving the shuttle Columbia
indicate the doors will close propely in orbit despite the cracks,
raising the possibility Discovery can be launched as is, without time-
consuming repairs.
	``Right now, from the orbiter project point of view ... we're
starting to feel reasonably comfortable with the recommendation (to
launch Discovery as is),'' Germany told reporters at a televised news
conference. ``But we've still got some more work to do.''
	A final decision on whether to proceed with Discovery's launch or to
delay the flight for repairs, possibly until after an early April
mission by the shuttle Atlantis, is not expected until after a two-day
flight readiness review Thursday and Friday.
	Engineers held a cross-country teleconference Monday to discuss the
tests with Columbia. The issue is critical because the doors in question
must close properly in space before the ship can safely re-enter Earth's
atmosphere.
	Two options were under study: launching Discovery as is or rolling
the shuttle back to its hangar for repairs, a move that would delay the
mission until after an April 4 takeoff by Atlantis. Germany said a third
option, fixing the cracks on the launch pad, had been ruled out.
	Engineers ran a series of tests over the weekend in which similar
hinge mechanisms on the shuttle Columbia were modified to simulate a
worst-case failure. The door in question appeared to work properly
despite the deliberate flaws.
	``We've been trying to develop an analysis that will demonstrate
whether or not the (cracks are) stable and whether we have enough margin
that in the subsequent flight there will be no problem closing the
doors,'' Germany said.
	``From a technical point of view, it looks like we do have a stable
system. There are adequate margins with the existing cracks that we have
noted to safely close the doors.''
	In the meantime, engineers and technicians at launch pad 39A pressed
on with work to ready Discovery for blastoff March 9 at 3:49 a.m. EST to
kick off an unclassified eight-day ``Star Wars'' research mission to
learn more about how to detect enemy missiles in flight.
	The fuel line doors, covered with heat-shield tiles, are folded back
and locked open during launch, allowing 17-inch-wide fuel lines from the
external tank to deliver propellant to Discovery's three main engines.
	After the shuttle reaches orbit, the tank is jettisoned and the doors
are closed over the fuel line connectors. Because the belly of the
orbiter bears the brunt of re-entry heating, the doors must close
properly to prevent possibly catastrophic damage to the shuttle
fuselage.
	``It's a (major) failure,'' said a NASA manager. ``There's nothing
that we know of that you can go do if that door doesn't close.''
	The cracks involve eighth-of-an-inch-thick plates in the hinge
mechanisms of the two doors. The hinge assemblies in question do not
hold the doors on the shuttle and do not bear any weight on the launch
pad. Rather, they involve the drive mechanisms that must shut the doors
in the weightlessness of space.
	Three such cracks were found in lugs that are part of Discovery's
door-closing mechanisms while two smaller cracks were found aboard
Columbia. NASA's third shuttle, Atlantis, appears to be crack-free.
662.75Shuttle Status for 02/26/91 PRAGMA::GRIFFINDave GriffinTue Feb 26 1991 18:2027
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


           KSC SHUTTLE STATUS REPORT - TUESDAY, FEB. 26, 1991 - 9:30 a.m.

 
                       STS-39/DoD - DISCOVERY (OV 103) - PAD A
                                 LAUNCH - MARCH 1991

          WORK IN PROGRESS:
          - Payload end-to-end test.
          - Preparations for ordnance activities.
          - Purge of the cavity between the orbiter and external tank  liq-
          uid hydrogen umbilical.

          WORK COMPLETED:
          - Main engine flight readiness test.

          WORK SCHEDULED:
          - Installation of ordnance devices on Wednesday.
          - On Thursday, installation of two extravehicular space suits for
          contingency purposes.
          - Flight Readiness Review on Thursday and Friday.
          - Purges of the external tank on Friday.

 
662.76On the new GPCs...PRAGMA::GRIFFINDave GriffinWed Feb 27 1991 18:1029
From: [email protected] (John F. Woods)
Date: 27 Feb 91 20:49:42 GMT

The Electronic Engineering Times for 25 February 1991 has an article about
the new shuttle computers which are scheduled to fly on Discovery "next week."
The new AP101S computers use static-RAM memory and Schottky logic, replacing
the old core-memory AP101B computers.  A summary of the differences:

	       Memory					         First
	Memory  tech-     CPU       Size,    			 Shuttle
Computer size  nology     Speed     Weight    Power   MTBF	 Flight
AP101S  128Kx2 Radiation  1.2 Mips  1 box,    550W  20,000+ hrs. 3/91 STS-39
	32-bit resistant	    10x9x18'
	words  CMOS SRAM            64 pounds
AP101B  104Kx1 Ferrite    0.4 Mips  2 boxes,  650W   5,200 hrs.  4/81 STS-1
        32-bit cores		    10x8x19'
	words                       120 pounds

(I'm suspicious of the size figures; I'd expect them to be the same size,
and I have quite carefully preserved the single-tick foot unit indicator,
even though the box obviously does not dwarf the technicians next to it in
the front page photo... :-)

To improve the radiation resistance of the "radiation resistant" SRAMs,
they use 25 check-bits for each 16-bit halfword, and a background task
scrubs out soft ECC errors from all of memory every two seconds.

The article also includes a sidebar on complaints by IBM about how silly
NASA is about specifications and obsolete component qualification methods.
662.77Shuttle Status for 02/27/91 PRAGMA::GRIFFINDave GriffinThu Feb 28 1991 12:0834
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


          KSC SHUTTLE STATUS REPORT - WEDNESDAY, FEB. 27, 1991 - 9:30 a.m.

 
                       STS-39/DoD - DISCOVERY (OV 103) - PAD A
                                 LAUNCH - MARCH 1991

          WORK IN PROGRESS:
          - Last part of the retest for the load control assembly.
          - Leak checks of the liquid hydrogen monoball connection.
          - Payload operations.

          WORK COMPLETED:
          - Payload end-to-end test.
          - Part one of ordnance activities.
          - Purge of the cavity between the orbiter and external tank  liq-
          uid hydrogen umbilical.

          WORK SCHEDULED:
          - Closeouts of the aft compartment for flight.
          - On Thursday, installation of two extravehicular space suits for
          contingency purposes.
          - Flight Readiness Review no earlier than March 4-5.
          - Purges of the external tank on Friday.

          CONCERNS:
          -  Managers  want more time to continue their analysis of the ex-
          ternal tank umbilical door hinges before  conducting  the  Flight
          Readiness Review.

 
662.78STAR::HUGHESYou knew the job was dangerous when you took it Fred.Thu Feb 28 1991 13:595
    Clarinet reports that NASA have decided to haul Discovery back to the
    VAB to repair the hinges, delaying liftoff until April (after the GRO
    mission).
    
    gary
662.79UPI: Discovery shuttle mission delayedPRAGMA::GRIFFINDave GriffinThu Feb 28 1991 17:4580
From: [email protected] (WILLIAM HARWOOD, UPI Science Writer)
Date: 28 Feb 91 19:11:38 GMT

	CAPE CANAVERAL, Fla. (UPI) -- Playing it safe, NASA managers Thursday
delayed launch of the shuttle Discovery from next week to late April,
after a flight by the shuttle Atlantis, because of cracked hinges in
critical fuel line doors.
	The decision to roll Discovery back to its hangar to fix the cracks
likely will result in reducing the number of space shuttle flights
planned for 1991 from seven to six in another sign of the conservative
post-Challenger shuttle program's difficulty meeting proposed launch
schedules.
	But William Lenoir, NASA's associate administrator for space flight,
said the space agency's top priority is safety and that while Discovery
probably could have been launched safely without any time-consuming
repairs, enough unknowns were present to justify caution and delay.
	``I don't think it sends a negative message at all,'' Lenoir said of
the decision to move Discovery back to the hangar. ``If anything, I
think it should send a positive message that says we do have a process
that works. We are being careful. We're not taking excessive chances.''
	Discovery and its seven-man crew had been scheduled to blast off on
the year's first shuttle mission at 3:49 a.m. EST on March 9 to kick off
an eight-day ``Star Wars'' research mission, NASA's first since early
December.
	Instead, agency engineers will haul Discovery off its launch pad next
week and move Atlantis to nearby pad 39B for takeoff at 9:20 a.m. April
4 on a mission to carry the $550 million Gamma Ray Observatory into
orbit, a Hubble Space Telescope-class astronomical satellite.
	Space agency managers hope to make another attempt to launch
Discovery roughly three weeks after Atlantis's launch, around April 25,
assuming the hinge problem can be quickly corrected. The shuttle
Columbia then will be launched on a Spacelab life sciences mission in
late May.
	The cracks in question were found last week in the hinge assemblies
of two 50-square-inch fuel line doors in Discovery's belly that must
close properly after launch to permit a safe re-entry into Earth's
atmosphere.
	Earlier this week, many NASA engineers concluded Discovery could be
safely launched without repairs after tests in which one of the shuttle
Columbia's fuel line doors was modified to simulate a worst-case
failure. The door worked properly.
	But in the end, Lenoir said, engineers were unable to prove what
caused the cracks in the first place, although two incidents are under
study. In one incident, a wingnut was found jammed in a hinge. In the
other incident, a door was ordered closed when it was still latched
open.
	``We have tried and tried in our safety-oriented process to get
ourselves convinced the analysis says it's OK and it will work (as is),''
he said.
	``We have confirmed it with tests but nonetheless, the unknowns of
not knowing exactly what it was that broke these leads us to the
conclusion that prudence calls for us to roll back and fix it.''
	On the launch pad and during ascent, the doors, covered with heat-
shield tiles, are folded back against the belly of the orbiter and
locked open to allow 17-inch fuel lines to enter the shuttle from its
external tank.
	Electric motors drive the doors closed after the tank is jettisoned
in space. Failure of either door to close properly could result in the
destruction of the shuttle due to extreme heating during re-entry.
	Smaller stress cracks have also been found in the hinges used by
Columbia but not in those aboard Atlantis.
	At a news conference, Lenoir said he was confident Discovery could
have been safely launched on schedule, without any repairs, had the
mission warranted such action.
	``If there were some crtical reason, national defense or some
emergency reason, why we needed to go fly (Discovery), I don't think any
of us would have any hesitiation to go fly this bird,'' he said. ``We're
being conservative.''
	To fix Discovery's cracks, the shuttle must first be taken off its
external fuel tank and moved into a special processing hangar. Lenoir
said the repair work, expected to take about a month, will involve
either replacing the cracked parts or the entire hinge mechanism.
	Depending on which course of action is selected, parts may be taken
off the new shuttle Endeavour, which has been cannibalized before to
keep NASA's operational shuttles flying. Endeavour is scheduled to be
delivered to the Kennedy Space Center in May for a maiden flight in
1992.
	Engineers believe Discovery's cracks grew from small stress fractures
in an aluminum plate where the hinge mechanism is anchored to the
shuttle fuselage.
662.80Shuttle Status for 03/01/91 PRAGMA::GRIFFINDave GriffinTue Mar 05 1991 09:1832
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


            KSC SHUTTLE STATUS REPORT - FRIDAY, MAR. 1, 1991 - 9:30 a.m.

 
                       STS-39/DoD - DISCOVERY (OV 103) - PAD A
                           LAUNCH - LATE APRIL, EARLY MAY


          WORK IN PROGRESS:
          - Preparations for rolling back to the Vehicle Assembly  Building
          no earlier than 12:01 a.m. March 7.
          - Demate the orbiter midbody umbilical unit.
          - Payload electrical demates.

          WORK SCHEDULED:
          - Disconnection of ordnance devices on Monday.
          -  Transferring  the  STS-39  Air  Force Program 675 payload from
          Discovery's payload bay to the Payload Changeout Room on Monday.
          - Offloading hypergolic propellants from the orbital  maneuvering
          system and reaction control system on Tuesday.

          CONCERNS:
          -  Shuttle officials decided yesterday to roll Discovery back for
          repairs to the cracked hinges for  the  external  tank  umbilical
          door  drive  mechanism.  Repairs  will  be  made  in  the Orbiter
          Processing Facility.


 
662.81Shuttle Status for 03/04/91 PRAGMA::GRIFFINDave GriffinTue Mar 05 1991 09:1932
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


            KSC SHUTTLE STATUS REPORT - MONDAY, MAR. 4, 1991 - 9:30 a.m.


 
                       STS-39/DoD - DISCOVERY (OV 103) - PAD A
                           LAUNCH - LATE APRIL, EARLY MAY


          WORK IN PROGRESS:
          -  Preparations for rolling back to the Vehicle Assembly Building
          at 12:01 a.m. March 7.
          - Transferring the STS-39 Air  Force  Program  675  payload  from
          Discovery's payload bay to the Payload Changeout Room.
          - Preparations to offload hypergolic propellants from the orbital
          maneuvering system and reaction control system.

          WORK COMPLETED:
          - Disconnection of ordnance devices on the vehicle.
          - Removed the two spacesuits from the airlock.
          - Demated the orbiter midbody umbilical unit.

          WORK SCHEDULED:
          - Offloading oxidizer and fuel from the orbiter's onboard storage
          tanks tomorrow.  The pad will be closed to all non-essential per-
          sonnel during this operation.


 
662.82Shuttle Status for 03/05/91 PRAGMA::GRIFFINDave GriffinTue Mar 05 1991 19:1626
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


             KSC SHUTTLE STATUS REPORT - TUESDAY, MAR. 5, 1991 - 10 a.m.


 
                       STS-39/DoD - DISCOVERY (OV 103) - PAD A
                           LAUNCH - LATE APRIL, EARLY MAY


          WORK IN PROGRESS:
          - Preparations for rolling back to the Vehicle Assembly  Building
          no earlier than 2 a.m. March 7.
          -  Offloading hypergolic propellants from the orbital maneuvering
          system and reaction control system on Tuesday.

          WORK COMPLETED:
          - Disconnection of ordnance devices.
          - Transferring the STS-39 Air  Force  Program  675  payload  from
          Discovery's payload bay to the Payload Changeout Room on Monday.



 
662.83Shuttle Status for 03/06/91 PRAGMA::GRIFFINDave GriffinThu Mar 07 1991 09:3325
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


          KSC SHUTTLE STATUS REPORT - WEDNESDAY, MAR. 6, 1991 - 11 a.m.

 
                       STS-39/DoD - DISCOVERY (OV 103) - PAD A
                           LAUNCH - LATE APRIL, EARLY MAY


          WORK IN PROGRESS:
          - Preparations for rolling back to the Vehicle Assembly  Building
          at 2 a.m. tomorrow.
          - Final power down.
          -  Rotating Service Structure move away from the vehicle at about
          5:30 p.m.

          WORK COMPLETED:
          - Offloading hypergolic propellants from the orbital  maneuvering
          system and reaction control system.



 
662.84Shuttle Status for 03/07/91 PRAGMA::GRIFFINDave GriffinFri Mar 08 1991 09:3324
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


          KSC SHUTTLE STATUS REPORT - THURSDAY, MAR. 7, 1991 - 11 a.m.

 
                        STS-39/DoD - DISCOVERY (OV 103) - VAB
                           LAUNCH - LATE APRIL, EARLY MAY


          WORK IN PROGRESS:
          -  Rolling  back  from  pad 39-A.  First motion came at 5:14 a.m.
          after problems with the crawler transporter's jack  and  leveling
          system  were  corrected.  Orbiter was at the VAB doorway by about
          10:30 a.m.

          WORK SCHEDULED:
          - Preparations to demate the orbiter from the external tank.  Ac-
          tual demate is planned next week after Atlantis is mated.



 
662.85Shuttle Status for 03/08/91 PRAGMA::GRIFFINDave GriffinFri Mar 08 1991 17:3923
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


          KSC SHUTTLE STATUS REPORT - FRIDAY, MAR. 8, 1991 - 9:30 a.m.

 
                        STS-39/DoD - DISCOVERY (OV 103) - VAB
                           LAUNCH - LATE APRIL, EARLY MAY

          WORK IN PROGRESS:
          - Putting platforms in place around the vehicle.
          - Demate preparations.

          WORK COMPLETED:
          - Rollback from the launch pad.  Discovery was hard down  in  the
          VAB by 11:30 a.m. yesterday.

          WORK SCHEDULED:
          - Demate is planned next week after Atlantis is mated.
          - Transfer to the OPF is planned next week.

 
662.86Shuttle Status for 03/12/91 PRAGMA::GRIFFINDave GriffinTue Mar 12 1991 18:3332
From: [email protected] (Ron Baalke)
Organization: Jet Propulsion Laboratory, Pasadena, CA.


          KSC SHUTTLE STATUS  -  TUESDAY, MARCH 12, 1991  ---   10:30 a.m.
          _________________________________________________________________


 
                   STS-39/DoD  -  DISCOVERY (OV 103)  -  VAB HB 1
                          LAUNCH  --  LATE APRIL, EARLY MAY


          WORK IN PROGRESS:
          *  Installation of aft access doors
          *  Sling lift and build up for demate scheduled to begin late
               this afternoon

          WORK COMPLETED:
          *  Electrical monoball connections and T-0 umbilical demate
               operations

          WORK SCHEDULED:
          *  Demate scheduled for late Tuesday afternoon
          *  Replace flight nose wheel tire with rollover wheel tire in
               transfer aisle
          *  Rollover to Orbiter Processing Facility Thursday morning
          *  Replace ET door hinge mechanism with one from Endeavour once
               in the Orbiter Processing Facility


 
662.87Shuttle Status - March 13ADVAX::KLAESAll the Universe, or nothing!Thu Mar 14 1991 10:4136
From: [email protected] (Ron Baalke)
Newsgroups: sci.space,sci.space.shuttle
Subject: Shuttle Status for 03/13/91 (Forwarded)
Date: 13 Mar 91 18:38:23 GMT
Sender: [email protected]
Organization: Jet Propulsion Laboratory, Pasadena, CA.
  
          KSC SHUTTLE STATUS  -  WEDNESDAY, MARCH 13, 1991  ---  10:30 a.m.
          _________________________________________________________________
 
                   STS-39/DoD  -  DISCOVERY (OV 103)  -  VAB HB 1
                          LAUNCH  --  LATE APRIL, EARLY MAY
 
          WORK IN PROGRESS:
          *  Lifting orbiter to transfer aisle
 
          WORK COMPLETED:
          *  Installation of aft access doors
          *  Sling lift and build up and orbiter demate operations
 
          WORK SCHEDULED:
          *  VAB orbiter hydraulic operations
          *  Replace flight nose wheel tire with rollover wheel tire in
               VAB transfer aisle
          *  Rollover to Orbiter Processing Facility bay 2 Thursday morning
               at 8:30 a.m.
          *  Replace ET door hinge mechanism with one from Endeavour once
               in the Orbiter Processing Facility
 
      ___    _____     ___
     /_ /|  /____/ \  /_ /|      Ron Baalke         | [email protected]
     | | | |  __ \ /| | | |      Jet Propulsion Lab | 
  ___| | | | |__) |/  | | |___   M/S 301-355        | Change is constant. 
 /___| | | |  ___/    | |/__ /|  Pasadena, CA 91109 | 
 |_____|/  |_|/       |_____|/                      | 

662.88Shuttle Status - March 14ADVAX::KLAESAll the Universe, or nothing!Thu Mar 14 1991 13:3732
From: [email protected] (Ron Baalke)
Newsgroups: sci.space,sci.space.shuttle
Subject: Shuttle Status for 03/14/91 (Forwarded)
Date: 14 Mar 91 16:21:25 GMT
Sender: [email protected]
Organization: Jet Propulsion Laboratory, Pasadena, CA.
  
          KSC SHUTTLE STATUS REPORT - THURSDAY, MAR. 14, 1991 - 9:30 a.m.
 
                        STS-39/DoD - DISCOVERY (OV 103) - VAB
                           LAUNCH - LATE APRIL, EARLY MAY
 
          WORK IN PROGRESS:
          -  Installing  the roll around tires in place of the nose landing
          gear flight tires.
          - Preparations for tow to the OPF about midday.
 
          WORK COMPLETED:
          - Demate Discovery from the external tank and lower to the trans-
          fer aisle.
 
          WORK SCHEDULED:
          - Removal of the external tank door hinge drive  mechanism  hous-
          ings beginning Sunday.
 
      ___    _____     ___
     /_ /|  /____/ \  /_ /|      Ron Baalke         | [email protected]
     | | | |  __ \ /| | | |      Jet Propulsion Lab | 
  ___| | | | |__) |/  | | |___   M/S 301-355        | Change is constant. 
 /___| | | |  ___/    | |/__ /|  Pasadena, CA 91109 | 
 |_____|/  |_|/       |_____|/                      | 

662.89Shuttle Status for 03/18/91PRAGMA::GRIFFINDave GriffinTue Mar 19 1991 09:4720
From: [email protected] (Ron Baalke)
Organization: Jet Propulsion Laboratory, Pasadena, CA.


          KSC SHUTTLE STATUS REPORT - MONDAY, MAR. 18, 1991 - 10  a.m.
 
 
                     STS-39/DoD - DISCOVERY (OV 103) - OPF BAY 2
                           LAUNCH - LATE APRIL, EARLY MAY
 
          WORK IN PROGRESS:
          -  Replacement  of  the  external  tank  door hinge housings with
          modified beefed up housings from Columbia.
          - Thermal protection system operations.
 
          WORK COMPLETED:
          - Removal of the external tank door hinge housings on Saturday.
 
 
 
662.90Shuttle Status Reports - 3/19/91 - 3/25/91PRAGMA::GRIFFINDave GriffinTue Mar 26 1991 09:5762
     KSC SHUTTLE STATUS REPORT - TUESDAY, MAR. 19, 1991 - 10  a.m.

                     STS-39/DoD - DISCOVERY (OV 103) - OPF BAY 2
                           LAUNCH - LATE APRIL, EARLY MAY

          WORK IN PROGRESS:
          - Replacement of the  external  tank  door  hinge  housings  with
          modified beefed up housings and cycling of the doors to retest.
          - Thermal protection system operations.

          WORK SCHEDULED:
          - Roll to the Vehicle Assembly Building early next week.


          KSC SHUTTLE STATUS REPORT - WEDNESDAY, MAR. 20, 1991 - 10  a.m.

                     STS-39/DoD - DISCOVERY (OV 103) - OPF BAY 2
                           LAUNCH - LATE APRIL, EARLY MAY

          WORK IN PROGRESS:
          - Rigging of the right hand external tank door hinge housings and
          cycling of the doors to retest.
          - Thermal protection system operations.

          WORK SCHEDULED:
          - Roll to the Vehicle Assembly Building early next week.

 
     KSC SHUTTLE STATUS REPORT - THURSDAY, MAR. 21, 1991 - 10  a.m.

                     STS-39/DoD - DISCOVERY (OV 103) - OPF BAY 2
                           LAUNCH - LATE APRIL, EARLY MAY

          WORK IN PROGRESS:
          - Rigging of the right hand external tank door hinge housings and
          cycling of the doors to retest.
          - Thermal protection system operations.
          - Functional tests of the external tank doors.

          WORK SCHEDULED:
          - Roll to the Vehicle Assembly Building Monday.


     KSC SHUTTLE STATUS REPORT - MONDAY, MAR. 25, 1991 - 10  a.m.

                      STS-39/DoD - DISCOVERY (OV 103) - OPF BAY 2
                           LAUNCH - LATE APRIL, EARLY MAY

          WORK IN PROGRESS:
          -  Preparations to transfer to the Vehicle Assembly Building at 6
          p.m. tonight.

          WORK COMPLETED:
          - Functional tests of the external tank doors.
          - Weight and center of gravity checks.
          - Orbiter attached to transporter.

          WORK SCHEDULED:
          - Mate Discovery to the external tank.
          - Rollout to Launch Pad 39-A early next week.

662.91Shuttle Status for 03/26/91 PRAGMA::GRIFFINDave GriffinThu Mar 28 1991 17:2630
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


           KSC SHUTTLE STATUS  -  TUESDAY, MARCH 26, 1991  ---  10:00 a.m.

          _________________________________________________________________


 
                STS-39/DoD  -  DISCOVERY (OV 103)  -  VAB High Bay 1
                          LAUNCH  --  LATE APRIL, EARLY MAY


          WORK IN PROGRESS:
          *  Orbiter lift and mate operations in high bay 1


          WORK COMPLETED:
          *  Orbiter rollover to VAB yesterday evening


          WORK SCHEDULED:
          *  Completion of mating operations to external tank
          *  Shuttle interface verification tests
          *  Power on testing Thursday
          *  Rollout to pad 39-A set for Monday 4:00 a.m.


 
662.92Shuttle Status for 03/28/91 PRAGMA::GRIFFINDave GriffinThu Mar 28 1991 17:3624
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


          KSC SHUTTLE STATUS  -  THURSDAY, MARCH 28, 1991  ---  10:00 a.m.
          _________________________________________________________________

 
                STS-39/DoD  -  DISCOVERY (OV 103)  -  VAB High Bay 1
                          LAUNCH  --  LATE APRIL, EARLY MAY

          WORK IN PROGRESS:
          *  Orbiter power up operations
          *  Shuttle interface verification tests

          WORK COMPLETED:
          *  Orbiter to external tank mate operations in high bay 1
          *  Liquid oxygen electrical closeouts
          *  Crew hatch functional tests

          WORK SCHEDULED:
          *  Rollout to pad 39-A set for Monday 4:00 a.m.

 
662.93Shuttle Status for 03/29/91 - 04/02/91PRAGMA::GRIFFINDave GriffinWed Apr 03 1991 01:1167
KSC SHUTTLE STATUS REPORT - FRIDAY, MAR. 29, 1991 - 11  a.m.


              STS-39/DoD - DISCOVERY (OV 103) - VAB
                       LAUNCH - LATE APRIL

WORK IN PROGRESS:
- Shuttle Interface Test to verify connections  between  the  or-
biter and launch platform and between the vehicle elements.
- Preparations to roll out to Launch Pad 39-A at 4 a.m.  EST Mon-
day, April 1.
- Thermal protection system operations.

WORK SCHEDULED:
- Retraction of work platforms away from the vehicle tomorrow.
- Rollout to Launch Pad 39-A Monday.



KSC SHUTTLE STATUS REPORT - MONDAY, APR. 1, 1991 - 10  a.m.


              STS-39/DoD - DISCOVERY (OV 103) - PAD A
                       LAUNCH - LATE APRIL

WORK IN PROGRESS:
- Hooking up ground systems to the vehicle.
- Rotating Service Structure moves around the vehicle at 1 p.m.

WORK COMPLETED:
- Rolled out to Launch Pad 39-A today. Left VAB at 3:16 a.m.  and
was harddown on the pad's pedestals at about 9 a.m.
-  Shuttle  Interface  Test to verify connections between the or-
biter and launch platform and between the vehicle elements.

WORK SCHEDULED:
- Verification of connections between the launch pad and  vehicle
tomorrow.
-  Installation  of the STS-39 payloads into the payload bay Wed-
nesday.





KSC SHUTTLE STATUS REPORT - TUESDAY, APR. 2, 1991 - 11:30  a.m.

           STS-39/DoD - DISCOVERY (OV 103) - PAD 39-A
                       LAUNCH - LATE APRIL

WORK IN PROGRESS:
- Hooking up ground systems to the vehicle.
- Verification of connections between the launch pad and vehicle.
- Opening of the payload bay doors later today.
- Preparations to install the STS-39 payloads.
- Preparations to load hypergolic propellants into the  orbiter's
onboard storage tanks.

WORK COMPLETED:
- STS-39 launch platform harddown on the pad's pedestals at about
9 a.m. yesterday.

WORK SCHEDULED:
-  Installation  of the STS-39 payloads into the payload bay Wed-
nesday.


662.94Shuttle Status for 04/03/91 PRAGMA::GRIFFINDave GriffinWed Apr 03 1991 18:3325
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


          KSC SHUTTLE STATUS REPORT - WEDNESDAY, APR. 3, 1991 - 10  a.m.

 
                     STS-39/DoD - DISCOVERY (OV 103) - PAD 39-A
                                 LAUNCH - LATE APRIL

          WORK IN PROGRESS:
          - Adjusting platforms for the installation of the payloads.

          WORK COMPLETED:
          - Hooking up ground systems to the vehicle.
          - Verification of connections between the launch pad and vehicle.
          - Opening of the payload bay doors.
          -  Preparations to load hypergolic propellants into the orbiter's
          onboard storage tanks.
          - Purges of the 17-inch disconnect cavity between the orbiter and
          external tank.



 
662.95Shuttle Status for 04/04/91 PRAGMA::GRIFFINDave GriffinThu Apr 04 1991 19:2423
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


          KSC SHUTTLE STATUS REPORT - THURSDAY, APR. 4, 1991 - 10  a.m.

 
                     STS-39/DoD - DISCOVERY (OV 103) - PAD 39-A
                                 LAUNCH - LATE APRIL

          WORK IN PROGRESS:
          - Installation of the STS-39 payloads.
          -  Preparations to load hypergolic propellants into the orbiter's
          onboard storage tanks.
          - Crew compartment hatch functional test today.

          WORK COMPLETED:
          - High pressure leak checks  of  the  external  tank  to  orbiter
          2-inch quick disconnects.

          WORK SCHEDULED:
          -  Pad  39-A  will be cleared at 10 p.m.  tonight until after the
 
662.96information needed58378::R_YURKIWMon Apr 08 1991 12:0616
    help...
    
    	I will down in florida between april 23 to May 4 and would like	to 
    try to see a launch. I know the launch is tentatively scheduled for 
    april 25. Is there an information phone number I can call when I am
    down there to get updates on the launch. The problem is that I will
    be out of touch with this notes conference for a week before the 
    current launch date and we all now how easy it is to get launch
    information from your local news sources!! Any help would be 
    appreciated..
    
    
    thanks in advance
    
    
    Roger
662.97DECWIN::FISHERPursuing an untamed ornothoidMon Apr 08 1991 12:519
I believe there is a Florida-only 800 number for info.  Maybe 800-555-1212 would
tell you.

Also, the National Space Society has a tape in DC which has space happenings
in general.  They generally update the tape frequently near a launch time.
That number should be here in this conference.  If not send mail and I'll look
on my stuff at home.

Burns
662.98Shuttle Status Report - 04/08/91PRAGMA::GRIFFINDave GriffinMon Apr 08 1991 18:3026
From: NASA Spacelink
Organization: NASA

KSC SHUTTLE STATUS REPORT - MONDAY, APR. 8, 1991 - 1:30  p.m.

 
           STS-39/DoD - DISCOVERY (OV 103) - PAD 39-A
                         LAUNCH - APRIL

WORK IN PROGRESS:
-  Loading  of  hypergolic propellants into the orbiter's onboard
storage tanks.
- Reopening of the launch pad for normal work at about noon.

WORK COMPLETED:
- Installation of the STS-39 payloads  into  Discovery's  payload
bay.
- Payload to orbiter interface verification tests.

WORK SCHEDULED:
- Main engine flight readiness test Wednesday.  Engine valves are
cycled and sensors are calibrated.
- Start aft closeouts later this week.
- Flight Readiness Review April 15-16.

 
662.99KSC Shuttle Status - 04/09/91PRAGMA::GRIFFINDave GriffinWed Apr 10 1991 09:3129
From: NASA Spacelink
Organization: NASA

KSC SHUTTLE STATUS REPORT - TUESDAY, APR. 9, 1991 - 10  a.m.

 
                  STS-39/DoD - DISCOVERY (OV 103) - PAD 39-A
                            LAUNCH - APRIL

WORK IN PROGRESS:
-  Circulation  and  sampling  of  the  hydraulic  fluid  in  the
orbiter's hydraulic system.
- Servicing payloads.
- Installation of booster thermal curtains.
- Closeouts of the avionics bays.

WORK COMPLETED:
- Loading of hypergolic propellants into  the  orbiter's  onboard
storage tanks.
- Pad reopened for normal work.
- Payload bay doors opened.

WORK SCHEDULED:
- Main engine flight readiness test Wednesday.  Engine valves are
cycled and sensors are calibrated.
- Start aft closeouts later this week.
- Flight Readiness Review April 15-16.

 
662.100Shuttle Status for 04/10/91 PRAGMA::GRIFFINDave GriffinThu Apr 11 1991 09:3529
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


          KSC SHUTTLE STATUS REPORT - WEDNESDAY, APR. 10, 1991 - 10  a.m.

 
                     STS-39/DoD - DISCOVERY (OV 103) - PAD 39-A
                                   LAUNCH - APRIL

          WORK IN PROGRESS:
          - Main engine flight readiness test to cycle valves and calibrate
          sensors.

          WORK COMPLETED:
          -  Circulation  and  sampling  of  the  hydraulic  fluid  in  the
          orbiter's hydraulic system.
          - Servicing payloads.
          - Installation of booster thermal curtains.
          - Pad was cleared for several hours last  night  due  to  adverse
          weather.  A tornado was spotted near Playalinda Beach, just north
          of the launch pad.

          WORK SCHEDULED:
          - Start aft closeouts later this week.
          - First part of ordnance installation Friday.
          - Flight Readiness Review April 15-16.

 
662.101KSC Shuttle Status - 04/15/91PRAGMA::GRIFFINDave GriffinMon Apr 15 1991 20:2522
From: NASA Spacelink
Organization: NASA

KSC SHUTTLE STATUS REPORT - MONDAY, APRIL 15, 1991 - 11 a.m.

 
                STS-39/DoD - DISCOVERY (OV-103) - Pad 39-A
                          LAUNCH-APRIL

      The STS-39 Flight Readiness Review began this  morning  and
may extend into Tuesday.   An official launch date for the STS-39
mission will be announced at its conclusion.

      At the pad,  Discovery was powered up this morning for pre-
launch  testing.    Aft  compartment closeout work and loading of
Mass  Memory  Units  with  mission  software  are  in   progress.
Replenishment of cryogenic propellants for the pad's main storage
dewars is in work and two waves of tankers with liquid oxygen are
being  offloaded  today.    Payload  work  in  progress  includes
cryogenic servicing of  AFP-675 and IBSS payloads.

 
662.102STS-39 DISCOVERY LAUNCH DATE SET (again) PRAGMA::GRIFFINDave GriffinMon Apr 15 1991 20:2722
STS-39 DISCOVERY LAUNCH DATE SET

Release:  91-54


        At the conclusion of today's Flight Readiness Review of mission
STS-39 aboard the Space Shuttle Discovery, Shuttle and payload managers
targeted April 23 for launch of this Department of Defense- dedicated
mission.

        The launch window for STS-39 on April 23 opens at 7:05 a.m. and
extends to 9:35 a.m.  EDT, on Pad 39A at NASA's Kennedy Space Center,
Fla.

        Commanding the seven-man Discovery crew will be Navy Capt.
Michael L. Coats. Air Force Major L. Blaine Hammond will serve as pilot.
Mission Specialists include Gregory J. Harbaugh; USAF Lt. Col. Don
McMonagle; USAF Col. Guion Bluford; C. Lacy Veach; and Richard J. Hieb.

        Two primary payloads will be carried aboard Discovery: Air Force
Program 675 (AFP-675) and the Strategic Defense Initiative Organization's
(SDIO) Infrared Background Signature Survey (IBSS).
662.103Shuttle Status for 04/16/91 PRAGMA::GRIFFINDave GriffinWed Apr 17 1991 14:0332
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


          KSC SHUTTLE STATUS REPORT - MONDAY, APR. 16, 1991 - 11:30 a.m.


 
                     STS-39/DoD - DISCOVERY (OV 103) - PAD 39-A
                                   LAUNCH - APRIL

          WORK IN PROGRESS:
          - Preparations for the last ordnance operation.
          -  Preparations for pressurizing the hypergolic propellant system
          for flight.
          - Closing out the aft compartment for flight.
          - Payload closeouts.
          - Launch countdown preparations.

          WORK COMPLETED:
          - Installation of two contingency space suits in Discovery's air-
          lock.
          - Installation of payload bay cameras.

          WORK SCHEDULED:
          - Final ordnance operations and pressurization of the  hypergolic
          system for flight tomorrow.
          - Launch countdown begins at 8:45 a.m. EDT Saturday, April 20.
          - STS-39 flight crew arrival at 6:30 p.m. EDT Saturday.
          - Launch at 7:05 a.m. EDT Tuesday, April 23.

 
662.104Shuttle Status for 04/17/91 PRAGMA::GRIFFINDave GriffinWed Apr 17 1991 18:2835
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


          KSC SHUTTLE STATUS REPORT - WEDNESDAY, APR. 17, 1991 - 10 a.m.


 
                     STS-39/DoD - DISCOVERY (OV 103) - PAD 39-A
                                   LAUNCH - APRIL


          WORK IN PROGRESS:
          - Final ordnance operations.  The pad is  cleared  for  this  ac-
          tivity.
          -  Preparations for pressurizing the hypergolic propellant system
          for flight.

          WORK COMPLETED:
          - Aft compartment was closed out for flight.  One of  the  flight
          doors  was installed and the other will be installed once the pad
          reopens.

          WORK SCHEDULED:
          - Pressurization,  later today,  of  the  hypergolic  system  for
          flight.
          - Purges of the fuel cell storage tanks tomorrow.
          - Final payload preparations.
          - Launch countdown begins at 8:45 a.m. EDT Saturday, April 20.
          - Closing the payload bay doors for flight Sunday.
          - STS-39 flight crew arrival at 6:30 p.m. EDT Saturday.
          - Launch at 7:05 a.m. EDT Tuesday, April 23.


 
662.105KSC Shuttle Status - 04/18/91PRAGMA::GRIFFINDave GriffinThu Apr 18 1991 19:1731
From: NASA Spacelink
Organization: NASA

KSC SHUTTLE STATUS REPORT - THURSDAY, APR. 18, 1991 - 10 a.m.


 
                STS-39/DoD - DISCOVERY (OV 103) - PAD 39-A
                             LAUNCH - APRIL 23


WORK IN PROGRESS:
- Pressurizing the hypergolic propellant system for flight.
- Final payload operations.
-  Purging the power reactant storage and distribution system for
flight.
- Launch countdown preparations.

WORK COMPLETED:
- Final ordnance operations.
- Aft compartment doors installed for flight.

WORK SCHEDULED:
- Final payload preparations.
- Launch countdown begins at 8:45 a.m. EDT Saturday, April 20.
- Closing the payload bay doors for flight Sunday.
- STS-39 flight crew arrival at 6:30 p.m. EDT Saturday.
- Launch at 7:05 a.m. EDT Tuesday, April 23.


 
662.106PREDICTED STS-39 ORBITAL ELEMENTSPRAGMA::GRIFFINDave GriffinThu Apr 18 1991 19:3324
The planned launch date for STS-39 is now 23 April, 1991, at 11:05 UTC.
The following elements may be used for pre-launch tracking predictions for
approximately the first 4 days after launch.  Predictions beyond this time
will be significantly in error because of the several maneuvers planned.
Updates will be provided here during the flight.  Landing is planned for
May 1 at 18:30 UTC.

STS-39
1 00039U          91113.52156250  .00280000  00000-0  44539-3 0    15
2 00039  57.0030 277.1989 0009407 267.9459  92.1059 16.05426977    29

Satellite: STS-39
Catalog number: 00039
Epoch time:      91113.52156250       (23 APR 91    12:31:03.000 UTC)
Element set:       1
Inclination:       57.0030 deg
RA of node:       277.1989 deg          Space Shuttle Flight STS-39
Eccentricity:     .0009407                  Keplerian Elements
Arg of perigee:   267.9459 deg          Launch:  23 APR 91  11:05 UTC
Mean anomaly:      92.1059 deg
Mean motion:   16.05426977 rev/day
Decay rate:       2.80E-03 rev/day^2
Epoch rev:               2
 
662.107DECWIN::FISHERPursuing an untamed ornothoidFri Apr 19 1991 12:354
57 degrees, eh?  It ought to be visible here in the northeast if the time works
out right.  Has anyone run the element set through a visibility predictor pgm?

Burns
662.108A telescopic view of launch from N.E.?6056::GAUDETNothing unreal existsFri Apr 19 1991 13:1017
Here's a question with a lot of "if's":

   If I have a "good" idea in what direction in the sky to look, and
   if I have a telescope with "reasonable" resolution, and
   if the sky is clear, and
   if I happen to be in a nice level field with a clear view of the
     south-southeast horizon, 
   could I see the shuttle through my scope once it comes above the horizon
     after launch?

   Is it a correct assumption that by the time the shuttle rises above the
horizon as viewed from New England, the SRB's have already burned out?  Has MECO
been reached by then?

   Am I reaching here?  :-)

...Roger...
662.109PRAGMA::GRIFFINDave GriffinFri Apr 19 1991 13:248
If by "seeing the shuttle" you mean a bright dot in the sky - not likely.

If you mean making out the outline of the orbiter/ET - no way.

You'd need a polar launch just to see the dot.


- dave
662.110Now I'll have to come to work!6056::GAUDETNothing unreal existsFri Apr 19 1991 13:348
RE: .109

Oh well, thanks Dave.  The thought just drifted into my head while reading the
notes about launch parameters (the 57 degree inclination sounded "promising"),
so I thought I'd ask.  Maybe I was just looking for an excuse to take the day
off!  :-)

...Roger...
662.111KSC Shuttle Status Report - 04/19/91PRAGMA::GRIFFINDave GriffinMon Apr 22 1991 08:3037
From: NASA Spacelink
Organization: NASA

   KSC SHUTTLE STATUS REPORT - FRIDAY, APR. 19, 1991 - 10 a.m.
   
 
                STS-39/DoD - DISCOVERY (OV 103) - PAD 39-A
                          LAUNCH - APRIL 23


WORK IN PROGRESS:
- Launch countdown preparations.
- Removal of service  platforms  from  the  deck  of  the  mobile
  launcher platform (MLP).
- Removing handrails from the launch platform.
- Preparing the MLP hazardous gas detection system for launch.
- Removal  of protective covers from the orbiter's reaction con-
  trol system thrusters.
- Removing platforms from the crew cabin.
- Payload servicing operations.

WORK COMPLETED:
- Pressurization of the hypergolic propellant system for flight.
- Purging of the power reactant storage and  distribution  system
  for flight.
-  Check  of  a  purge duct clamp in the aft compartment.  Aft is
  closed out for flight

WORK SCHEDULED:
- Final payload preparations.
- Launch countdown begins at 8:45 a.m. EDT Saturday, April 20.
- Closing the payload bay doors for flight Sunday.
- STS-39 flight crew arrival at 6:30 p.m. EDT Saturday.
- Launch at 7:05 a.m. EDT Tuesday, April 23.


 
662.112No launch this a.m., drat! :(6297::PHILLIPSMusic of the spheres.Tue Apr 23 1991 08:314
    I caught the tail end of a CNN brief this morning and heard the 
    launch was scrubbed.  Does anyone have the details?
    
    					--Eric--
662.113Recollection from the radio on my commute30086::REITHJim Reith DTN 226-6102 - LTN2-1/F02Tue Apr 23 1991 09:004
    NPR had it as a thermal transducer in one of the main engines that
    needs replacing. The payload will need to be reserviced so they are
    looking at a minimum 5 day standdown. They were hopeful for this
    weekend...
662.114Shuttle Status for 04/20/91 PRAGMA::GRIFFINDave GriffinTue Apr 23 1991 09:4550
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


          KSC SHUTTLE STATUS REPORT - SATURDAY, APR. 20, 1991 - 10 a.m.

 
                     STS-39/DoD - DISCOVERY (OV 103) - PAD 39-A
                                  LAUNCH - APRIL 23

                                 LAUNCH MINUS 3 DAYS


          WORK IN PROGRESS:
          - Launch countdown began on time today at 8:45 a.m  at  the  T-43
          hour mark.
          -  Verification that the data processing system and backup flight
          control system are operating.
          - Review of flight software.
          - Shuttle main engine controllers checked out for flight tonight.
          - Final payload servicing operations.


          WORK COMPLETED:
          - Removal of service  platforms  from  the  deck  of  the  mobile
          launcher platform (MLP).
          - Removing handrails from the launch platform.
          - Preparing the MLP hazardous gas detection system for launch.
          -  Removal  of protective covers from the orbiter's reaction con-
          trol system thrusters.
          - Removing platforms from the crew cabin.
          - Payload servicing operations.


          WORK SCHEDULED:
          - STS-39 flight crew arrival at 6:30  p.m.  EDT  tonight  at  the
          Shuttle Landing Facility.
          - First built-in hold at 12:45 a.m. Sunday at the T-27 hour mark.
          Hold will last for 8 hours.
          - Closing the payload bay doors for flight Sunday at 5 a.m.
          - Launch at 7:05 a.m. EDT Tuesday, April 23.


          WEATHER FORECAST:
               Probability  of  launch  weather  criteria  violation at the
          beginning of the launch period is 70  percent.  For  the  overall
          launch period  there is a 50 percent chance for violating weather
          criteria.


662.115Launch prep reports (sort of a letdown considering the scrub)PRAGMA::GRIFFINDave GriffinTue Apr 23 1991 10:12118
From: [email protected] (Peter E. Yee)
Subject: Shuttle Status for 04/21/91 (Forwarded)
Date: 22 Apr 91 23:48:05 GMT
Organization: NASA Ames Research Center, Moffett Field, CA


          SPACE SHUTTLE MISSION STS-39 COUNTDOWN STATUS --- April 21, 1991

                                LAUNCH MINUS TWO DAYS


               Everything at pad 39-A is continuing on schedule today as
          launch team members work toward the launch of the Space Shuttle
          Discovery at 7:05 a.m. Tuesday, April 23. The launch window
          extends through 10:31 a.m.

               The countdown clock came out of the T-27 hour planned eight-
          hour built-in hold on time this morning at 8:45. The clock will
          continue to count down until 4:45 p.m. today at which time it
          will enter another planned built in hold.

               Last night, final servicing of the STS-39 payloads was
          completed and the payload bay doors were closed today at 8:30
          a.m.

               At the pad today, the Power Reactant and Storage
          Distribution System on-board storage tanks are being serviced
          with liquid hydrogen and liquid oxygen reactants. The pad clear
          for this hazardous operation was given shortly after 9:00 a.m.
          today.

               Following PRSD loading operations, the orbiter midbody
          umbilical unit is scheduled to be retracted at about 4:45 p.m.
          today. Communication activation checks are then targeted to
          commence at about 9:00 p.m. this evening. The Rotating Service
          Structure is scheduled to be moved away from the vehicle at 11:45
          a.m. Monday.

               The STS-39 flight crew arrived at Kennedy Space Center at
          about 6:30 p.m. Saturday. Today, the seven member crew, already
          split into two teams to accommodate a 24-hour in-flight work
          schedule, had their final medical exams and flew training
          missions in the Shuttle Training Aircraft and T-38 trainer
          aircraft.

               Weather for Tuesday's liftoff is forecast to be less than
          favorable with 70 percent chance of violating launch constraints
          at the opening of the windown. There is a 60 percent chance of
          violating constraints throughout the entire three-hour, 26-minute
          window. A front located through western Florida and into the Gulf
          will probably produce low clouds and favorable conditions for
          showers.

               Wednesday's forecast calls for a 60 percent chance of
          violating launch constraints; Thursday's forecast calls for a 40
          percent chance of violation.



From: [email protected] (Peter E. Yee)
Subject: Shuttle Status for 04/22/91 (Forwarded)
Date: 22 Apr 91 23:49:07 GMT
Organization: NASA Ames Research Center, Moffett Field, CA


          SPACE SHUTTLE MISSION STS-39 COUNTDOWN STATUS --- April 22, 1991

                                LAUNCH MINUS ONE DAY

               Work at pad 39-A continues to go smoothly today as launch
          team members press toward launch of the Space Shuttle Discovery
          on Mission STS-39 at 7:05 a.m. Tuesday, April 23. The launch
          window extends through 10:31 a.m.

               Mission STS-39 is an unclassified Department of Defense
          mission featuring two primary payloads: Air Force Program 675 and
          the Strategic Defense Initiative's Infrared Background Signature
          Survey. There are also two secondary payloads; Space Test Payload
          and a Multi-Purpose Experiment Canister.

               The countdown clock entered the T-11 hour planned built-in
          hold this morning at 4:45. The clock will continue to hold until
          resuming the count at 4:45 p.m. today.

               Yesterday, the Power Reactant and Storage Distribution
          System on-board storage tanks were serviced with liquid hydrogen
          and liquid oxygen reactants. Following PRSD loading, the orbiter
          midbody umbilical unit was retracted. Communication activation
          checks then commenced at about 9:00 p.m. last night.

               The Rotating Service Structure is scheduled to be moved away
          from the vehicle at 11:45 a.m. today. Also today, final crew
          equipment and time critical items will be stowed on the orbiter.

               At 7:45 tonight the pad will be cleared of all personnel.
          Then at 10:45 p.m., operations will begin to load the external
          tank with liquid hydrogen and liquid oxygen propellants. Tanking
          operations should be completed by 1:45 a.m. Tuesday.

               The seven member STS-39 flight crew, already split into two
          teams to accommodate a 24-hour in-flight work schedule, are today
          undergoing weather and systems briefings. Tomorrow for launch,
          the crew will be awakened at 2:10 a.m. for breakfast. They will
          have a final weather briefing, suit up and at 3:50 a.m. depart
          their crew quarters for pad 39-A.

               The forecast weather for Tuesday's liftoff shows a 60
          percent chance of violating launch constraints at the opening of
          the window. There is a 50 percent chance of violating constraints
          throughout the entire three-hour, 26-minute window. A front
          located through western Florida and into the Gulf could produce
          low clouds and favorable conditions for thundershowers.

               Wednesday's forecast calls for a 40 percent chance of
          violating launch constraints; Thursday's forecast calls for a 30
          percent chance of violation.


662.116DECWIN::FISHERPursuing an untamed ornothoidTue Apr 23 1991 11:3310
I believe the claim was that if replacing the sensor fixed the problem, they
could launch Sunday.  If they had to replace the SSME controller (computer)
it would be longer.

They also said this particular problem was a first, and that it was in the fuel
pump (cryo temp sensor?).  That implies that it is not the same sensors that
failed several years back causing the ATO abort.  I think those were in the
engine on the "output" side.

Burns
662.117KSC Shuttle Status Report - 04/24/91PRAGMA::GRIFFINDave GriffinWed Apr 24 1991 18:0132
From: NASA SpaceLink
Organization: NASA

KSC SHUTTLE STATUS REPORT - WEDNESDAY, APRil 24, 1991 - 11:30 AM

 
                      STS-39/DoD - DISCOVERY (OV 103) - PAD 39-A
                            LAUNCH - NO EARLIER THAN APRIL 28


WORK IN PROGRESS:
- Replacement of a failed high pressure oxidizer turbopump  pres-
  sure transducer and its electrical harness for the no. 3 main en-
  gine.
- Preparations for payload servicing operations.
- Opening payload bay doors.
- Establishing access to the aft compartment.

WORK COMPLETED:
- Boiloff of liquid hydrogen propellant.
- Draining onboard propellants from the fuel cell storage tanks.

WORK SCHEDULED:
-  Closing the aft compartment for flight,  targeted for tomorrow
   afternoon.
- Start of launch countdown tentatively  scheduled  for  tomorrow
   morning at 8:45 a.m at the T-43 hour mark.
- Launch no earlier than Sunday,  April, 28 pending completion of
   planned work.


 
662.118UPI: Shuttle Discovery's countdown resumesPRAGMA::GRIFFINDave GriffinThu Apr 25 1991 16:3279
From: [email protected] (WILLIAM HARWOOD, UPI Science Writer)
Date: 25 Apr 91 16:50:23 GMT

	CAPE CANAVERAL, Fla. (UPI) -- Engineers replaced a faulty fuel pump
sensor, plugged a helium leak and restarted the shuttle Discovery's
countdown Thursday for blastoff Sunday on a ``Star Wars'' flight
grounded Tuesday by an electrical glitch.
	``I only have good news this morning,'' NASA test director Albert
Sofge told reporters shortly after countdown clocks began ticking at
8:45 a.m. EDT.
	If all goes well, Discovery and its seven-man crew will thunder away
on an unclassified eight-day military mission at 7:01 a.m. Sunday. Air
Force meteorologists called for a 70 percent chance of good weather at
launch time.
	Commander Michael Coats, 45, and five of his six crewmates -- co-pilot
Blaine Hammond, 39, Gregory Harbaugh, 35, Charles Lacy Veach, 46,
Richard Hieb, 35, and Donald McMonagle, 38 -- took advantage of the five-
day delay and flew back to Houston for additional training in a shuttle
simulator.
	``We going to go back and practice up a little bit more and then come
back,'' Hammond said before departing for the Johnson Space Center.
	All six shuttle fliers planned to rejoin crewmate Guion Bluford at
the Kennedy Space Center by Friday afternoon to await liftoff on the
40th shuttle flight, the second of six planned for 1991.
	During the course of the flight, Coats and company plan to work in
two shifts, around the clock, to operate a complex battery of
experiments and to launch four small satellites to learn more about how
to detect enemy missiles in flight.
	Data from the mission will be used by engineers with the Strategic
Defense Initiative -- ``Star Wars'' -- missile defense project to develop
sensors that can detect incoming missiles so space-based interceptors or
other weapons systems can blast them out of space.
	If all goes well, Discovery will glide to an afternoon landing May 6
at Edwards Air Force Base, about 50 miles north of Palmdale, Calif.,
where the new shuttle Endeavour, built to replace Challenger, is being
readied for delivery to NASA.
	Running nearly two months behind schedule because of cracks in
critical hinges, NASA attempted to launch Discovery Tuesday at 7:05 a.m.
	But six hours before the ship's planned takeoff, the countdown was
stopped when one of two sensors on main engine No. 3's high-pressure
oxygen fuel pump showed higher-than-allowable pressure inside a cavity
that should have reflected sea level readings.
	The suspect sensor showed more than 300 pounds per square inch, while
an identical ``transducer'' showed a normal sea level reading of about
15.7 pounds per square inch.
	The sensors are in place to detect potentially catastrophic leaks
that would require a quick engine shutdown in flight. All such sensors
on each engine must be operational before a shuttle can be cleared for
takeoff.
	After Discovery's external tank was drained of fuel, the suspect
sensor began behaving properly again, leading engineers to conclude the
transducer or its associated electrical cables were at fault, and not
the pump itself or the engine's computer controller.
	``We replaced the transducer and the wiring harness that goes to the
transducer and completed that at mid afternoon Wednesday,'' Sofge said.
``We retested that and it retests good.''
	The faulty sensor and its cable harness were flown to the Marshall
Space Flight Center in Huntsville, Ala., for tests to pin down exactly
what went wrong.
	Sofge said engineers used supercold liquid nitrogen to chill the
sensor to temperatures approaching those of liquid oxygen and once
again, the transducer produced faulty readings.
	``They were able to successfully reproduce the failure,'' Sofge said.
``They got the same basic indication we got during launch countdown.
They also installed the transducer on a different wiring harness,
chilled it down and got the same failure. So we're fairly certain it was
the transducer that was the problem.''
	Engineers also noticed a small helium leak in the engine room Tuesday
and took advantage of the sensor repair work to fix that problem as
well.
	``We're very comfortable with both repairs and things are looking
good,'' Sofge said.
	Liftoff originally was scheduled for Feb. 26, but the launch date
slipped to March 9 because of leaking rocket thrusters. The flight then
slipped to April 23 because of cracks in the hinges of doors in the
belly of the shuttle that must close propely in flight to allow a safe
re-entry.
	The delay Tuesday marked the crew's third postponement in as many
months.
662.119NASA Select for STS-39PRAGMA::GRIFFINDave GriffinSat Apr 27 1991 19:004
    Rev C of the NASA Select television schedule for STS-39 can be
    found at pragma::public:[nasa]sts-39.nasa_select
    
    - dave
662.120KSC Shuttle Status Report - 04/26/91PRAGMA::GRIFFINDave GriffinSat Apr 27 1991 19:0451
From: NASA Select
Organization: NASA

KSC SHUTTLE STATUS REPORT - FRIDAY, APRIL 26, 1991 - 10 AM

 
                STS-39/DoD - DISCOVERY (OV 103) - PAD 39-A
                            LAUNCH - APRIL 28

                           LAUNCH MINUS 2 DAYS


WORK IN PROGRESS:
- Launch countdown continuing with no problems.
- Pad is closed to all non-essential personnel for loading liquid
  oxygen and liquid hydrogen reactants in the orbiter's  fuel  cell
  storage tanks.
- Countdown will enter second built-in hold at the T-19 hour mark
  at 4:45 p.m. tonight for a duration of 4 hours.
- Orbiter communications will be activated tonight.
-  Tail  service  masts  on  the mobile launcher platform will be
  prepared for launch early tomorrow morning.

WORK COMPLETED:
- Serviced payloads.
- Closed payload bay doors for flight at 2:35 a.m. this morning.
- Closed out the aft compartment for flight  at  2:50  a.m.  this
  morning.

WORK SCHEDULED:
- Move Rotating Service Structure away from the orbiter at 11:45
  a.m. Saturday.
- Start loading liquid oxygen  and  liquid  hydrogen  propellants
  into the external tank at about 10:40 p.m. EDT Saturday.
- Launch at 7:01 a.m. EDT Sunday, April 28.

FLIGHT CREW:
-  STS-39  Commander  Michael  Coats  and Mission Specialist Lacy
  Veach are scheduled to arrive at KSC today at 1 p.m. Pilot Blaine
  Hammond and  Mission Specialists Rick Hieb, Greg Harbaugh and Don
  McMonagle  returned this morning to KSC.  Mission Specialist  Guy
  Bluford  practiced  approaches to the Shuttle Landing Facility in
  the T-38 jet this morning.

WEATHER FORECAST:
- There is a 30 percent chance of violating weather  criteria  at
  launch  time  on  Sunday  and  a  20 percent chance for violating
  criteria for the duration of the window.


 
662.121Launched at approx 7:35 am58453::SKLEINNulli SecundusSun Apr 28 1991 08:2210
Well they finally launched this morning. They were late by about 35 minutes
because they had a minor problem onboard, I think with a computer. The launch
was good and always a pretty site to see. Interesting that the launch broke
right through clouds about 7 seconds after launch. I wonder what they weather
issue is about. Obviously the clouds cannot cover the landing site, but the 
launch and landing site are about 3 miles apart, and the clouds seemed to be 
fairly extensive. 

Susan
662.122Launch time3149::BIROMon Apr 29 1991 08:546
    lauch took place on Sunday the 28th of April at 11:33:15 UTC
    I monitored radio comunications on the normal UHF frequencies
    between the Shuttle and Ground Control
    
    jb
    
662.123additional details on recorder woes2319::SAUTERJohn SauterMon Apr 29 1991 09:1210
    re: .121
    
    They were worried that the problem might be due to a computer
    malfunction, but they decided that it must be the tape recorder itself
    that glitched, so they launched.
    
    Once in orbit they discovered that two tape recorders weren't working.
    I don't think either of these is the one that started by itself before
    launch, but I could be mistaken.
        John Sauter
662.124Mission Control Center Status Reports #1-4 (Sunday, Monday AM)PRAGMA::GRIFFINDave GriffinMon Apr 29 1991 09:59205
        MISSION CONTROL CENTER
        Status Report #1


Sunday, April 28, 1991, 10:30 a.m. CDT

The Space Shuttle Discovery lifted off this morning at 7:33
a.m. eastern daylight time with its crew of seven to begin eight
full days of operations in low earth orbit.  After flying to an
initial altitude of 133 nautical miles, Discovery's big
maneuvering engines were fired to circularize the orbit at
about 140 nautical miles, where Discovery and crew will carry
out their mission to test and verify sensor and tracking
technologies for the Department of Defense.

The launch was delayed for about half an hour to allow flight
controllers to assess any potential effects of a data
recorder which had inadvertently begun to record.  It was
quickly determined that the recorder anomaly would have no
effect on a safe launch and, in fact, that it was functioning
normally.

All major systems aboard Discovery are working well, and the
flight crew, including 5 first-time flyers, are working ahead
of the timeline.





        MISSION CONTROL CENTER
        Status Report #2


Sunday, April 28, 1991, 1:30 p.m. CDT


Discovery's seven-member crew, getting started on a packed
timeline, settled in on-orbit and started work with the
STS-39 payloads.

The seven astronauts on board Discovery will be split into
two teams for the nine-day flight. The Red Team consists of
Pilot Blaine Hammond and mission specialists Lacy Veach and
Richard Hieb while the Blue team is mission specialists Greg
Harbaugh, Don McMonagle and Guion Bluford. Commander Mike
Coats is free to adjust his schedule as the mission merits,
but is expected to closely align it with the Red Team.

During the Red Team's first shift, crewmembers successfully
completed checkout of Discovery's remote manipulator system
arm. The arm will be used later in the flight to deploy and
retrieve the Shuttle Pallet Satellite with the Infrared
Background Signature Survey payload. The Blue Team's first
activity was to start their eight-hour sleep shift.

Activities also began with the Air Force Program-675. Veach
performed a short troubleshooting procedure to open the cover
of the Quadrupole Ion and Neutral Spectrometer which failed
to open on the first attempt. That effort was sucessful.
The payload community also reported that activities are
moving along with the Space Test Program-1 checkout and
activiation.

Sending messages to Discovery via the Text and Graphics
System was temporarily delayed due to a jam indication on the
system. Hammond, however, was able to clear the jam.

All other systems on Discovery are performing well with no
major system anomalies. The orbiter is currently in a 57
degree orbit at an altitude of 140 by 138 nautical miles.


Mission Control Status Report #3
9 p.m. CDT April 28, 1991

Members of the blue team aboard Discovery -- mission specialists
Greg Harbaugh, Don McMonagle and Guy Bluford -- are well into
their first work shift in space, continuing to tune up the
ultraviolet, infrared and X-ray sensors in Discovery's
payload bay.

Activation and alignment of all scientific instruments has
gone well so far, however, the crew has had no success in
activating two tape recorders designed to record observations
by three secondary instruments on Air Force Payload-675.
Three attempts to power on the recorders have been
unsuccessful, and payload controllers are considering further
troubleshooting procedures and alternatives to the onboard
recorders that may be available.

The two recorders are designed to store information obtained
by the Uniformly Redundant Array, an X-ray instrument
designed to study various X-ray sources in the universe; the
Quadrupole Ion-Neutral Mass Spectrometer, an instrument
designed to measure the amount and nature of contamination in
Discovery's payload bay; and the Horizon Ultraviolet Program,
an instrument planned to study the Earth's horizon in
ultraviolet light.

The first planned science observation for the URA, a look at X-
rays from the crab nebula, was replaced with the third
unsuccessful attempt to turn on the recorders. In all other
activities, the crew has been either ahead of or on an ambitious
schedule.

The crew reported an exciting view of the aurora in the
southern hemisphere as Discovery passed below the Cape of
Africa. Auroral activity, a prime target of several of
Discovery's planned scientific observations, has been at a
peak throughout the day and is predicted to be high tomorrow
as well.

Also, the crew reported taking good still photography
of Lake Baikal with both color and infrared film. Lake
Baikal, in the USSR, is of interest due to its geologic area,
the northernmost area of collision of the Indian continental
plate with the Eurasian plate. In addition, the crew was
asked by ground scientists to photograph smoke from Central
American fires that had drifted as far north as Texas and as
far east as Florida, as well as a Class 3 typhoon in the
Indian Ocean's Bay of Bengal with winds gusting to 130 knots.

Discovery's systems are performing very well and flight
controllers are tracking no significant spacecraft problems.



Mission Control Center Status Report #4

Monday, April 29, 1991, 7 a.m. CDT


Discovery crew members were successful in obtaining auroral
emission data with the CIRRIS (Cryogenic Infrared Radiance
Instrumentation for Shuttle) instrument mounted on the Air
Force Program-675 payload in the orbiter's payload bay.

Two attempts were made to run the procedure to collect
auroral data with two successes.  The first attempt was ahead
of the timeline with the second as an added bonus.

The payload community was very pleased with the data obtained
by Mission Specialists Guy Bluford and Lacy Veach during the
two "initial airglow" data takes with the CIRRIS because it
is the highest priority experiment on the AFP-675.

The crew is preparing to activate the Far Ultraviolet (FAR
UV) cameras to photograph thruster firings of the orbiter
during a night pass around the Earth.

Mission Specialist Rick Hieb unstowed Discovery's robot arm
to get a closer look at the Arizona Imager Spectrograph in an
attempt to better visualize the postion of the instrument on
its gimbal mechanism.  Once that is completed, payload
investigators will center the device in preparation for
tonights start of the IBSS operations.

AIS is used to observe the orbiter's payload environment
during the deployment, retrieval and stow of the IBSS

Activation and alignment of all scientific instruments is
continuing to go well with the exception of activating two
tape recorders designed to record observations by three
secondary instruments on AFP-675.

Attempts to power on the recorders have been unsuccessful,
and payload controllers are investigating what further
troubleshooting procedures could be tried or what alternatives to
the onboard recorders may be available.

The two recorders are designed to store information obtained
by the Uniformly Redundant Array, an X-ray instrument
designed to study various X-ray sources in the universe; and
the Horizon Ultraviolet Program, an instrument planned to
study the Earth's horizon in ultraviolet light.

The two instruments' major activity is planned to take place
after the Infrared Background Signature Survey (IBSS)
operations are complete on flight day 4 which gives the
payload community time to continue troubleshooting the
recorder anomaly.

In all other activities, the crew has been either ahead of
or right on the timeline planned prior to launch.

Auroral activity, a prime target of several of Discovery's
planned scientific observations, was very active throughout
the evening and is predicted to be high tomorrow as well.

In addition, the crew was asked by ground scientists to
photograph smoke from Central American fires that had drifted
as far north as Texas and as far east as Florida, as well as
a typhoon in the Indian Ocean's Bay of Bengal with winds
gusting to 130 knots.

The crew also was asked to photograph the North-Central
Mediterranean, the coastal range of Southern California, and oil
well fires in Kuwait.

All systems aboard Discovery are performing well with no
significant spacecraft problems being tracked by the Mission
Control flight team.
 
662.125UPI: Shuttle crew like 'kids in a candy store'PRAGMA::GRIFFINDave GriffinMon Apr 29 1991 18:5563
From: [email protected] (WILLIAM HARWOOD, UPI Science Writer)
Date: 29 Apr 91 04:47:54 GMT

	CAPE CANAVERAL, Fla. (UPI) -- Working around the clock, the shuttle
Discovery's crew struggled to fix two balky data recorders Monday amid a
full slate of ``Star Wars'' experiments to learn how to detect enemy
missiles in space.
	Using a heat-sensitive infrared telescope and other instruments in
Discovery's cargo bay, the seven astronauts planned to spend most of the
day studying the appearance of Earth's atmosphere as well as recording
high-energy emissions from astronomical bodies in deep space.
	Such data is crucial to planners with the Strategic Defense
Initiative, or ``Star Wars,'' project, who are trying to develop sensors
capable of detecting elusive enemy missiles against a variety of
backdrops.
	But some of the data could be lost, depending on the outcome of work
to get two apparently balky tape recorders running that are needed by
three of the shuttle's instruments to record scientific data.
	If troubleshooting efforts fail, data from at least two of the
experiments could be lost. But officials said instruments making up the
shuttle's major payloads were working properly and that they were
pleased with the progress of the mission.
	``As far as the orbiter goes, we're in good shape, there are no
significant problems to report,'' flight director Ron Dittemore said
late Sunday. ``Everything is working fine and we're just looking forward
to the next several days when we have a lot of activities planned.''
	On board Discovery are Navy Capt. Michael Coats, 45, he commander;
Air Force Lt. Col. Blaine Hammond, 39, the co-pilot; Gregory Harbaugh,
35; Charles Lacy Veach, 46; Air Force Col. Guion Bluford, 48; Richard
Hieb, 35; and Air Force Lt. Col. Donald McMonagle, 38.
	The primary goal of the 40th shuttle mission is to learn how to
distinguish fast-moving missiles in different lighting conditions and
against a variety of space backdrops ranging from the black of space to
the flickering polar auroras.
	``We just were fascinated by some aurorae in the Southern Hemisphere
here,'' one of the astronauts radioed as the shuttle sailed over
Australia late Sunday. ``We're seeing some white aurorae that goes well
up above the atmosphere and it's spectacular.''
	Running two months late because of technical problems, Discovery took
off on the second shuttle mission this month at 7:33 a.m. EDT Sunday,
five days after the ship was grounded Tuesday by a faulty engine sensor.
	Circling the globe every 90 minutes at an altitude of 160 miles, the
astronauts spent the day checking out their $260 million payload, a
battery of experiments primarily devoted to Strategic Defense Initiative
anti-missile research.
	The goal of the flight, the first unclassified military mission in
shuttle history, is to gather data about how to locate and track enemy
missiles in flight, a key element of the SDI program.
	While critics claim the controversial system could not stop an all-
out Soviet attack, supporters say it could, in fact, protect the nation
from attacks by smaller nations, citing the success of Patriot missiles
in shooting down Iraqi Scuds during the Persian Gulf War.
	``What this mission tells us is what do our targets look like in the
realistic space environment where we will have to fight,'' said Michael
Griffin, deputy for technology with the Strategic Defense Initiative
Organization.
	``The task of acquiring, tracking, identifying and setting up fire
control, setting up the engagement of our targets, is one of the most
difficult things we in SDI have to do. This mission plays a major part
in understanding how to do that.''
	If all goes well, Coats and Hammond will close out the eight-day
voyage with a Mojave Desert landing at 11:57 a.m. PDT on May 6 at
Edwards Air Force Base, Calif.
662.126UPI: Shuttle crew marvels at southern lights; Colorful auroras thrill astronautsPRAGMA::GRIFFINDave GriffinMon Apr 29 1991 18:57129
From: [email protected] (WILLIAM HARWOOD, UPI Science Writer)
Newsgroups: clari.tw.space,clari.news.aviation,clari.news.bulletin
Date: 29 Apr 91 19:41:43 GMT

	CAPE CANAVERAL, Fla. (UPI) -- The Discovery astronauts beamed down
spectacular television views of Earth's colorful auroras Monday in
unprecedented ``Star Wars'' research to find out how the gossamer
curtains of light might mask enemy missiles.
	``We're looking at a long, long curtain of aurora here,'' shuttle
skipper Michael Coats radioed mission control as Discovery approached
the southern edge of Australia. ``It's just like flying through a
curtain of light. This is spectacular!''
	Amid work to fix two balky tape recorders needed by three secondary
experiments, the shuttle's hard-charging seven-man crew used an infrared
telescope known as CIRRIS to also study the hard-to-see glow produced by
atomic oxygen smashing into the shuttle as it raced through space.
	The eight-day mission, off to a remarkably trouble-free start, moves
into high gear Tuesday with the launch of a small satellite that will
photograph some 60 firings of the shuttle's maneuvering rockets from up
to 6 miles away.
	The research from these and a host of other experiments aboard
Discovery is expected to help engineers with the Strategic Defense
Initiative determine how to detect incoming missiles against a variety
of backdrops ranging from the black of space to the brighter hues of the
aurora and planet Earth itself.
	Taking a handful of minor problems in stride, including an overheated
instrument and the balky recorders, Discovery's astronauts managed to
stay on or ahead of schedule throughout their second day in space,
photographing a shuttle rocket firing and carrying out a full slate of
experiments.
	Television images beamed down from the CIRRIS instrument Monday
showed the aurora australis, or southern lights, snaking like a curtain
across Earth's horizon. The rippling bands of light are generated by
atomic particles from the sun that spiral down magnetic field lines and
smash into the atmosphere.
	``Discovery ... that's a landmark measurement, you're right on target
and congratulations,'' payload communicator Roscoe Miller radioed the
shuttle from Houston as data flowed down from CIRRIS.
	``There's so much out here, I don't know what to point at,'' said
astronaut Charles Lacy Veach. ``Congratulations to all you guys who
built this thing.''
	``You're doing a fine job,'' Miller replied. ``We're elated.''
	Joining Veach, 46, and Navy Capt. Coats, 45, aboard Discovery are Air
Force Lt. Col. Blaine Hammond, 39, the co-pilot; Gregory Harbaugh, 35;
Air Force Col. Guion Bluford, 48; Richard Hieb, 35; and Air Force Lt.
Col. Donald McMonagle, 38.
	Discovery's two major payloads are the satellite scheduled for launch
Tuesday and a suite of five experiments, including the CIRRIS telescope,
known collectively as Air Force Project 675. The balky tape recorders
are needed by three of those experiments.
	Air Force Capt. Lindley Johnson, AFP-675 project manager, said if the
tape recorders cannot be fixed, scientists with the affected experiments
would lose about 15 percent to 20 percent of the data they had hoped to
collect.
	But he dismissed news reports about the significance of the problem,
saying CIRRIS was the most important member of the AFP-675 suite of
instruments, the only one gathering data for the Strategic Defense
Initiative.
	``That's really fairly minor,'' he said of the tape recorders. ``The
big news that we've got is that CIRRIS is operating quite well. The
aurora was active ... and we've gotten some good aurora data. We expect
to get a lot more.''
	Johnson said the tape recorders ``only record data from our secondary
experiments. Yeah, it is a little disappointing to our secondary
experimenters, but as far as overall success of 675, we're still quite
happy with the data that we're getting.''
	Castle said the shuttle itself was sailing along in excellent
condition and that work was on schedule for the overnight launch of the
SPAS-2 satellite carrying a battery of sensitive cameras and other
instruments known by the acronym IBSS (pronounced eye'-biss).
	The satellite was scheduled to be released from Discovery's 50-foot-
long robot arm about 4:30 a.m. Tuesday to begin a 38-hour space ballet
requiring some of the most complicated shuttle piloting ever attempted.
If all goes well, the satellite will be hauled back aboard Wednesday.
	The astronauts also plan to launch three smaller satellites during
the mission -- the first was scheduled for Tuesday night -- to release
various rocket fuels into space that will be studied by instruments
aboard the SPAS-2 satellite, the shuttle and on the ground.
	Discovery was launched Sunday into an orbit carrying it 57 degrees to
either side of the equator, giving the crew a bird's eye view of the
auroras at both poles.
	If all goes well, Coats and Hammond will close out the eight-day
voyage with a Mojave Desert landing at 11:57 a.m. PDT on May 6 at
Edwards Air Force Base, Calif.




From: [email protected] (WILLIAM HARWOOD, UPI Science Writer)
Newsgroups: clari.tw.space,clari.news.aviation,clari.news.military
Subject: Colorful auroras thrill astronauts
Date: 29 Apr 91 19:49:08 GMT

	CAPE CANAVERAL, Fla. (UPI) -- From the ground, Earth's colorful
auroras appear as flickering walls of light that dance across the night
sky.
	But from the shuttle Discovery, the northern and southern lights look
like snaking rivers of color that can stretch from horizon to horizon in
a spectacular display of nature's artistry, the ship's crew said Monday.
	During repeated passes over Australia and the southern Indian Ocean,
the astronauts studied the aurora australis, or southern lights, with a
sophisticated ``Star Wars'' camera, marvelling at the view from 160
miles up. Commander Michael Coats was especially impressed.
	``It goes from just below us -- in fact we're kind of flying through
it -- all the way up to the horizon, kind of a long, snaking bright line
of aurora,'' he radioed mission controllers.
	``We'll be interested to see that on playback,'' replied astronaut
Kathryn Thornton from the Johnson Space Center in Houston.
	``I hope so, Kathy,'' Coats said. ``It's just like flying through a
curtain of light up here. This is spectacular. (Astronaut) Rick (Hieb)
says you're going to need your dark glasses to look at this one.''
	``We're down here eating it up, probably not as much as you are, but
we're enjoying it too,'' Thornton replied.
	A few minutes later, Coats said he could see faint colors in the
display that changed with altitude.
	``At the bottom of that curtain, nearest the Earth, you can see some
reds and purples,'' he said. ``All we need is a low-light-level color
TV. This is amazing! From the right wing out to the horizon, all the way
around to the left wing on the horizon is just 180 degrees of a curtain
right now.
	``It looks kind of like green in the brightest part ... and then
colorful toward the bottom. As it goes up toward space it kind of
shallows out and disappears.
	``But it just snakes around the horizon. It looks like somebody drew
a curtain all the way around the horizon.''
	Scientists with the Strategic Defense Initiative -- ``Star Wars'' --
program hope to use data from Discovery's flight to learn more about how
to detect enemy missiles that might otherwise be hard to find in the
glow of an aurora.
662.127MCC Status Reports #5-7 (Monday-Tuesday AM)PRAGMA::GRIFFINDave GriffinTue Apr 30 1991 09:35136
        MISSION CONTROL CENTER
        Status Report #5


Monday, April 29, 1991, 1:30 p.m. CDT

Treating their Earth-bound flight controllers to an occasional
look at the spectacular atmospheric phenomenon, crew members on
board Discovery are continuing to gather auroral data for the
Cryogenic Infrared Radiance Instrumentation for Shuttle.

"It's just like flying through a curtain of light," said STS-39
Commander Mike Coats as Discovery floated through an aurora off
the southwestern coast of Australia.

CIRRIS is the highest priority payload on the AFP-675 package.
The instrument gathers infrared characteristics of atmospheric
emissions. Members of the CIRRIS team are enthusiastic about the
results thus far.

Efforts to power on two recorders on AFP-675 were not successful,
but analysis by team members continues. The two recorders, which
operate with the secondary AFP-675 experiments, quit working
after about four hours of operation on Flight Day 1. The anomaly
affects only the recording of data from the Quadropole Ion-
Neutral Mass Spectrometer, the Horizon Ultraviolet Program and
the Uniformly Redundant Array. Some realtime data from those
experiments will be available, but several data takes with URA
have been deleted.

Earlier today, Mission Specialist Rick Hieb used Discovery's
robot arm to look at the Arizona Imager Spectrograph and its
position on the gimbal mechanism. After viewing the downlink of
the AIS, controllers are developing plans to correct the
instrument's position.

The arm will next be used to deploy the Shuttle Pallet Satellite
holding the Infrared Background Signature Survey for its deployed
operations. During that time, the orbiter will perform a manuever
that will take Discovery out of plane of the SPAS groundtrack
while flipping the orbiter's nose 180 degrees before returning to
the original position.  The "Malarkey Milkshake," named after
Orbit Two Rendezvous Office John Malarkey, will be performed five
times while the SPAS is away from Discovery.

All orbiter systems are performing well with no significant
spacecraft problems being tracked by the Mission Control
flight team.




              MISSION CONTROL STATUS REPORT #6

                 5:30 p.m. CDT April 29, 1991


Crew members on board Discovery will continue to work with
the AFP-675 payload Tuesday, delaying the planned orbital ballet
with the Infrared Background Signature Survey for 24 hours.

The change in plans was made because the CIRRIS instrument,
collecting data on the Earth's aurora, is using about twice as
much of its liquid helium coolant as expected.

Under the new plan, Discovery's manipulator arm will grapple
and unberth the Shuttle Pallet Satellite carrying the IBSS
during the Red Team's shift on Flight Day 4. After a series of
deployed operations, the Discovery will rendezvous with and
grapple the SPAS. IBSS will begin RMS operations immediately
thereafter.

In the interim, activities with AFP-675 will continue, maximizing
CIRRIS data collection. AFP-675 officials said the instrument has
collected more than 3 hours worth of exciting data, more than has
ever been collected. They expect to collect 85 to 90 percent of
the data hoped for before the SPAS/IBSS deployment, and possibly
more afterward if enough coolant remains.

AFP-675 scientists have established that fuses on the two data
recorders that refused to activate have not been blown, and they
are continuing to troubleshoot the problem.

Also, payload controllers are developing a software patch for the
Arizona Imager/Spectrometer. The patch will compensate for
previous difficulties in gimballing the instrument on SPAS.




             MISSION CONTROL STATUS REPORT #7
                 5:30 a.m. CDT April 30, 1991


Discovery's crew continued getting good auroral and airglow
data using the CIRRIS instrument mounted on the AFP-675
payload during the last eight hours after planners delayed
for 24 hours the start of mission activities related to the
Infrared Background Signature Survey.

The change in plans was a result of higher than expected
usage of cryogenic fuel used by the CIRRIS.

Under the new plan, Discovery's manipulator arm will grapple
and unberth the Shuttle Pallet Satellite carrying the IBSS
during the Red Team's shift on Flight Day Four.  Actual
release of the IBSS will occur at approximately 3:24 a.m. CDT
Wednesday -- 2 days 20 hours and 51 minutes into the mission.

The 36-hour deployed operations will conclude with Discovery
closing in and retrieving the SPAS.  IBSS will begin RMS
operations immediately threafter.

In the interim, activities with AFP-675 will continue,
maximizing CIRRIS data colletion.

Flight controllers currently are in the process of finalizing
the plan.

Also, payload controllers developed a software patch for the
Arizona Imager/Spectrometer to compensate for previous
difficulities in gimballing the instrument on SPAS.  The
success of that software patch has not yet been determined.


An additional troubleshooting procedure for the ESS recorders
mounted on the AFP-675 secondary experiments was performed
with no success in recovering the use of those recorders.
Mission Specialist Guy Bluford did, however, report that the
light on the Command Monitor Panel did flicker several times
giving the payload community a data point to go off and work
with.

The major activities associated with the ESS recorders do not
occur until after the IBSS operations are completed.
 
662.128Shuttle Status for 04/29/91 PRAGMA::GRIFFINDave GriffinTue Apr 30 1991 11:5432
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


          KSC SHUTTLE STATUS REPORT - MONDAY, APRIL 29, 1991 - 10:30 AM

 
                     STS-39/DoD - DISCOVERY (OV 103) - ON ORBIT


               Discovery was launched at  7:33:14.07812  a.m.  EDT  Sunday,
          April  28  after  a brief delay to analyze the sudden start of an
          onboard orbiter and payload recorder.  After a discussion,  offi-
          cials  determined  that  there  was no problem with the orbiter's
          computers and the  countdown was resumed.

               Landing is planned on Monday, May 6 at 2:57 p.m.  EDT at Ed-
          wards Air Force Base, Calif.

               Damage  to  the launch pad was reported as very minimal this
          morning.

               The solid rocket boosters are being towed  by  the  recovery
          ships to Hangar AF. They are scheduled to arrive at the Hangar at
          about  5  p.m.  today.  Safing the boosters is the first order of
          business.  Afterwards,  they will be inspected and  washed  down.
          Thermal foam and exterior cork will be removed with high pressure
          water.  Disassembly  operations  are  scheduled  to take about 10
          days.


 
662.129Shuttle Status for 04/30/91 PRAGMA::GRIFFINDave GriffinTue Apr 30 1991 18:4221
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


          KSC SHUTTLE STATUS REPORT - TUESDAY, APRIL 30, 1991 - 10:30 AM

 
                     STS-39/DoD - DISCOVERY (OV 103) - ON ORBIT

               The solid rocket boosters arrived at Hangar AF about 5  p.m.
          yesterday  and  have been hoisted out of the water and secured in
          stands. The two boosters have been washed down and rinsed.  Ther-
          mal  foam  and  exterior  cork will be removed with high pressure
          water.  Disassembly operations are scheduled  to  take  about  10
          days.

               Discovery  is  scheduled  to  land  on Monday,  May 6 at ap-
          proximately 2:57 p.m. EDT at Edwards Air Force Base, Calif.


 
662.130Mission Control Center Status Report #8 - 1 p.m. CDT April 30, 1991PRAGMA::GRIFFINDave GriffinTue Apr 30 1991 18:4634
Mission Control Center Status Report #8

1 p.m. CDT April 30, 1991



Data collection continues with the CIRRIS experiment aboard
Discovery as flight controllers prepare for Wednesday's
operations with the Infrared Background Signature Survey (IBSS).

Efforts to build a software patch to correct the Arizona
Imager/Spectrograph gimbal anomaly have been successful.
Controllers are now in the process of implementing the final
steps of their troubleshooting plan to co-align AIS for IBSS
operations.

The detached operations will begin at about 3:20 a.m. CDT
Wednesday when Discovery moves away from the Shuttle Pallet
Satellite. Five orbital manuevering system engine firings
will take place during the next 38 hours to provide plume
data for the IBSS experiment. Following the retrieval of the
SPAS, IBSS operations with the remote manipulator arm will
commence.

Today, work continues with the Cryogenic Infrared Radiance
Instrumentation for Shuttle. Thus far, 11 of the 17 CIRRIS
catagory-one experiments have been completed sucessfully.
Members of the payload community have expressed enthusiasm
for the quality of data collected during the first three days
of the flight.

All systems on Discovery are performing very well.
No orbiter issues are being worked by flight controllers at
this time.
662.131MCC Status Reports #9, #10 (Tue. P.M, Wed. A.M.)PRAGMA::GRIFFINDave GriffinWed May 01 1991 10:1685
        MISSION CONTROL STATUS REPORT #9
        9:00 p.m. CDT April 30, 1991

The blue team aboard Discovery -- mission specialists Greg
Harbaugh, Don McMonagle and Guy Bluford -- are in the midst
of another shift of highly productive observations of the
Earth's limb at dawn and dusk using the CIRRIS-1A infrared
sensor.

Observations with the CIRRIS are expected to wrap up later
this evening with a final observation of Discovery's
mechanical arm and a phenomenon known as "shuttle glow," a
well-documented effect caused by the interaction of atomic
oxygen with the spacecraft as it orbits the Earth.  Following
that observation, CIRRIS will be calibrated once before being put
aside.

As their work day comes to a close tonight, the blue team members
will be joined by the red team, which will be awakened at 1:23
a.m. CDT Wednesday, to deploy the Infrared Background
Signature Survey experiment mounted on the Shuttle Pallet
Satellite-II. The satellite is scheduled to be released from
Discovery at 3:17 a.m. CDT Wednesday to begin about 38 hours
of rendezvous operations. IBSS will observe Discovery's
engine firings from distances of about eight miles and again
from about one and a half miles to obtain information for the
Strategic Defense Initiative Organization.

Payload controllers were successful today in recovering full
use of the Arizona Imaging Spectrograph (AIS) after one
of several switches used to tell where the instrument is
pointing failed to operate early in the flight. A computer
software patch and remote commands from the ground worked
around the problem, aligning the pointing of the AIS with
that of the IBSS.

The shuttle Discovery is continuing to perform well, and flight
controllers are watching no significant problems.




               MISSION CONTROL STATUS REPORT #10
                   7:30 a.m. CDT May 1, 1991


Discovery's crew checked out and released the Infrared
Background Signature Survey experiment mounted on the Shuttle
Pallet Satellite and maneuvered to a position 6 1/2 miles
behind the satellite in preparation for the plume
observations in support of the Strategic Defense Initiative
Organization.

The satellite was released at 3:17 a.m. CDT

The first plume observation was delayed at least one orbit
when the sun sensor on the IBSS recognized a bright object
and changed the SPAS attitude in order to protect the IBSS
instruments.

Flight and payload controllers are continuing to work
procedures to correct the attitude of the SPAS.

Up until the point of the sun sensor bright object detection,
all activities related to the IBSS operations were going
exactly as predicted.  All checkouts of the instruments went
well and Discovery's maneuvering jet burns occurred on time
putting the orbiter in the proper position to support the far
field operations using the IBSS.

Observations with the CIRRIS payload wrapped up last night
with a final observation of Discovery's mechanical arm and a
phenomenon known as "shuttle glow," a well-documented effect
caused by the interaction of atomic oxygen with the
spacecraft as it orbits the Earth that has been seen since
early shuttle flights. Following that observation, CIRRIS
was calibrated before being powered off for the IBSS
operations.

The blue team aboard Discovery was joined by the remaining
crew members during the pre-deploy checkout of the IBSS/SPAS
to prepare for the release and subsequent observation burns.

Discovery continues to perform well.
662.132SpaceVAX Successfully Flys!37090::KILGOREDan @ WashingtonWed May 01 1991 13:0541
    NASA and Digital Successfully tested the FASTEST VAX ever!!!
    
    At 17,000 Miles per hour as it orbited around the earth, the prototype
    Raytheon SpaceVAX qualifies as the fastest VAX ever run.  It executed
    standard VMS 5.1 and standard VAX ADA.
    
    Because of a reshuffle of experiment communication time, due to CIRRIS
    coolant problems, our SpaceVAX experiment was allocated 1 hour time the
    night of Apr 29 and then a 20 minute window on Tuesday Apr 30.  For the
    Tuesday experiment (and it will be the last for this mission) we had
    both NASA and DEC folks to observe the experiment and had it vidio
    taped for a press release at the end of the mission.  NASA folks there
    included:
    Dr. James Trainor, Deputy Dir., Goddard Space Flight Center,
    Dr. Don Krueger, Chief, Applied Engineering Division.
    Dr. Danny Dalton, Chief, Flight Data Systems Branch.
    
    The experiment tested standard VMS running on the SpaceVAX, in the total
    vaccum environment of the open shuttle bay.  It was booted and operated
    in a wide temperture range.  Exact data is not available until the post
    mission debrief.  It generated commands based on a Artificial
    Intellignece Program that solved a 3 dimensional space Robot Arm
    Movement problem.  The arm was successfully moved across it's working
    space while avoiding obstacles in the arms path.  The robot arm for the
    experiment was located in the Robotics Lab at Goddard not on the
    shuttle.
    
    The system is configured with 1 VAX cpu, 16 MB memory, 300 MB erasable
    optic disk, SCSI disk controller, 1553A Communication buss, and
    ethernet.  The 1553 and ethernet were not used in the experiment but
    went along for the ride in space.  They will be tested when returned to
    earth.
    
    A very interesting side note is that the system was launched with the Ada
    compiler on the disk.  A variation in the experiment required some
    "tuning".  A source code change developed, compiled, relinked and
    executed on the on orbit VAX!.  This is a true testimony to the fact
    that the SpaceVAX is just as compatible as any other VAX.
    
    The space qualification experiment has been deemed a success!
    
662.133MCC Status Reports #11-#13 (Wed PM - Thursday)PRAGMA::GRIFFINDave GriffinThu May 02 1991 14:43123
          MISSION CONTROL STATUS REPORT #11

               2 p.m. CDT May 1, 1991


Work with the Infrared Background Signature Survey continues
to progress as astronauts and ground controllers prepare for
the orbital manuevering system plume observations later this
afternoon.

Controllers on the ground have successfully ajusted the
attitude of the Shuttle Pallet Satellite carrying IBSS to the
proper reference attitude. Those activities were necessary
when the sun sensor on SPAS recognized a bright object and
altered its attitude to protect the instruments.

With the attitude refinements completed, crewmembers on
Discovery will pick up the flight plan to perform two
alignment procedures and a Earthlimb data take before
entering the plumes observation sequences. At that time,
current plans call for crewmembers picking up this morning's
OP1 sequence in addition to OP2, OP3 and PRCS.

In those sequences, Discovery will be positioned behind SPAS
with its nose pointing north of the groundtrack and its
payload bay pointing toward SPAS. Discovery will then fire
its right OMS engine to begin the sequence. Shortly after
that burn, crewmembers will input the attitude for the
braking burn. That action will yaw the orbiter 180 degees
performing a fast flip. Following the braking burn, Discovery
will perform a slower flip to return the orbiter to its
original position. This manuever has been nicknamed the
Malarkey Milkshake for its designer Orbit Two Rendezvous
Officer John Malarkey.

The satellite began its 38-hour deployed operations at 3:17
a.m. CDT when the SPAS/IBSS payload was released from
Discovery's remote manipulator arm.

Today's activities focused primarily on IBSS operations.
Observations with the CIRRIS payload closed Tuesday night.

Meanwhile, Discovery continues to perform with little or no
problems.





        MISSION CONTROL STATUS REPORT #12
        5 a.m. CDT May 2, 1991

The crew of Discovery successfully moved to within 1.5
statute miles of the Shuttle Pallet Satellite and Infrared
Background Signature Survey to remotely command that
satellite to observe two engine firing sequences by the
orbiter. All operations at the near-position were performed
smoothly and on schedule.

Discovery is now more than two miles from the SPAS/IBSS and
continuing to separate at a little over one mile per hour.
Discovery will separate from the SPAS for five orbits before
initiating rendezvous operations to retrieve the satellite at
3:33 p.m. CDT today.  As that rendezvous operation commences,
Discovery will be at a distance of about 48,000 feet from the
SPAS/IBSS.

Also yesterday, the crew deployed the CRO C subsatellite at
8:28 p.m. CDT. Currently, the CRO C, a satellite filled with
the rocket propellant nitrogen tetroxide, is about 63
nautical miles behind the SPAS/IBSS. The chemical will be
released from the CRO C at about 9:18 a.m. for attempted
simultaneous observations by the SPAS/IBSS, instruments at
Vandenburg Air Force Base, airborne instruments, and
Discovery. The release is to occur over Vandenburg, when
the CRO C is about 93 nautical miles from Discovery.

Discovery's crew noted about a 15 degree-per-second roll on
the CRO C as it was deployed. Payload controllers
are now checking any problems this may imply for subsequent
observations.

The space shuttle's systems contiue to perform without any
significant problems.



             MISSION CONTROL STATUS REPORT #13

                11:30 a.m. CDT May 2, 1991


Release of nitrogen tetroxide (N2O4) rocket fuel from a
cannister deployed early this morning was successfully
captured by sensors and cameras located on the Infrared
Background Signature Survey instruments.

The observation was also monitored at the Vandenberg Air
Force Base in California as Discovery, IBSS and the Chemical
Release Observation cannister containing the fuel passed
overhead.

At the time of the fuel release, the cannister was about 112
miles behind the IBSS mounted on the Shuttle Pallet
Satellite.

Before and after the first CRO fuel release, the IBSS
instruments were pointed at the Earth's limb to take
additional aurora data along with learning more about the
levels of carbon dioxide in the upper atmosphere.

All of this activity followed the successful data gathering
of orbiter plume data as Discovery performed many intricate
maneuvers in front of the IBSS so that engine firing data
could be collected.

Discovery is presently 48,000 feet, or nine miles behind the
satellite.  Rendezvous operations are scheduled to begin
about an hour prior to the grapple of SPAS using the
orbiter's robot arm.

Discovery and crew continue to perform flawlessly, now half-
way through their eight day mission.
662.134On-Orbit OMS Burns2631::DAHLTom Dahl, CDMSThu May 02 1991 17:2411
RE:             <<< Note 662.133 by PRAGMA::GRIFFIN "Dave Griffin" >>>

>Discovery will then fire its right OMS engine...

Does anyone know whether the OMS engines have been fired before to change the
shuttle's orbit (other than the OMS-1, OMS-2, and de-orbit burns of course)?
The OMS engines are relatively powerful; it's slightly surprising to me that
they're being used here. I can imagine the urgency to the "fast flip" maneuver
to re-allign the shuttle for a counter OMS burn to nullify the effect of the
first burn.
						-- Tom
662.135DECWIN::FISHER&quot;I am NOT a Merry Man&quot;--WorfThu May 02 1991 17:577
I'm reasonably sure they always use the OMS engines for any non-trivial manuvers.
For example during rendezvous with various things like wayward com satellites,
Solar Max, etc.  They are powerful, but not THAT powerful. The deorbit burn is
on the order of minutes long, so they are not in immediate danger of dropping
out of orbit.

Burns
662.136MCC Status Reports #14 & 15 (Thursday evening, Friday morning)PRAGMA::GRIFFINDave GriffinFri May 03 1991 13:0177
             MISSION CONTROL STATUS REPORT #14

                7 p.m. CDT May 2, 1991


The Shuttle Pallet Satellite (SPAS) is back in Discovery's payload
bay after the successful completion of the rendezvous
operations.

Discovery's remote manipulator arm grappled the SPAS
carrying the Infrared Bavckground Signature Survey at 5:25
p.m. CDT. Shortly after, the arm maneuvered the SPAS
and berthed the satellite after 38 hours of deployed
operations.

Prior to the SPAS capture, the Infrared Background Signature
Survey observed the release of unsymmetric dimethyl
hydrazine from the second Chemical Release Observation
canister. CRO B was deployed from Discovery at 1:03 p.m.
CDT. Earlier today CRO C was deployed and released its
nitrogen tetroxide. Both chemicals are commonly used as
rocket propellants.

Currently, the Blue Team members, Greg Harbaugh, Don McMonagle
and Guy Bluford, are in the midst of their flight day six
activities. Those activities will consist primarily
of work with AFP-675 and predeploy checkout for the
IBSS remote manipulator system operations.

After analysis of the orbits of the two empty CRO
canisters, flight controllers have opted to wait to
perform height adjust maneuvers with the orbiter. The orbit
adjustment could be performed later in the mission if flight
requirements dictate.

Meanwhile, the Space Shuttle Discovery continues to perform very well.



        MCC STATUS REPORT #15
        5 a.m. May 3, 1991

The blue team aboard Discovery spent their sixth work shift
in space working with the Far Ultraviolet experiment, making
observations of the Earth, celestial targets, and a
phenomenon known as "shuttle glow," caused by the interaction
of atomic oxygen with the spacecraft.

In Mission Control, flight controllers spent much of the
night assessing tracking data from ground radar sites on the two
CRO subsatellites deployed from Discovery during the past
day and a half. Following those assessments, Discovery will
perform a series of two engine firings to raise its orbit
above that of the subsatellites and avoid any possiblity of
reentering their vicinity during the remainder of the
mission.

To allow for the best possible tracking assessment,
Discovery's altitude-gaining maneuvers were delayed several
hours, and the deployment of a third CRO subsatellite was
postponed until after the engine firings are completed.
Better tracking information is important to determine the
most fuel-efficient method of avoiding the deployed CRO
subsatellites. Fuel economy is extremely important on this
flight due to the mission's large number of engine firings
and the overall length of the flight.

The delay in deployment of the third CRO subsatellite has not
affected plans to conduct a third gas release observation of
that satellite later in the flight. Flight controllers now
anticipate deploy of that third subsatellite at a mission elapsed
time of 5/00:36 or around 7:10 a.m. CDT Friday. Also today, the
crew of Discovery is scheduled to again unberth the Shuttle
Pallet Satellite and Infrared Backgrond Signature Survey for a
series of scientific observations to be conducted with the
instrument while it is held on the end of Discovery's mechanical
arm.
662.1372631::DAHLTom Dahl, CDMSFri May 03 1991 17:247
RE:      <<< Note 662.135 by DECWIN::FISHER ""I am NOT a Merry Man"--Worf" >>>

>They are powerful, but not THAT powerful. The deorbit burn is
>on the order of minutes long...

That's true, I had forgotten the long burn times.
						-- Tom
662.138MCC Status Report #16 (12:30 p.m. CDT May 3, 1991)PRAGMA::GRIFFINDave GriffinFri May 03 1991 20:1737
             MISSION CONTROL STATUS REPORT #16


                 12:30 p.m. CDT May 3, 1991



Discovery's crew lifted the Shuttle Pallet Satellite out of
the payload bay to support the next phase of the STS-39
mission -- observations using the Infrared Background
Signature Survey instruments while attached to the robot arm.

Once in the observation attitude on the end of the arm,
observations of the Earth's limb and aurora continued as was
done while the SPAS was deployed from the Shuttle during the
last couple of days.  Again good data was obtained using the
IBSS instruments with little or no problems encountered.

During the checkout of the IBSS equipment prior to the
unberth of the SPAS, the third and final Chemical Release
Observation (CRO-A) cannister was deployed from Discovery's
payload bay.

Later today, at about 5:00 p.m. CDT, 15 gallons of monomethyl
hydrazine rocket fuel will be released and observed by the
IBSS and the ground as the orbiter and cannister pass over
the Vandenberg AFB tracking site in California.

The deployment of the CRO was delayed while flight
controllers assessed the best possible tracking of the first
two empty CRO cannisters to ensure they were located a
sufficient from the orbiter prior to the two orbital
maneuvering system burns that raised Discovery's orbit to 139
nautical miles.

All systems aboard the orbiter continue to perform very well.
 
662.1398713::TAVARESStay low, keep movingMon May 06 1991 10:5711
Thanks to NASA select, I've really enjoyed this flight, even
though it has been relatively quiet.  Last evening they showed
how the galley worked and rather impressed me with the
difficutly of working in space -- I somehow thought things were
easier in zero G.

What is that pot-bellied stove looking thing with the lights and
a digital clock that they spent long minutes filling the screen
with?  Every time the announcer talked about it I was out of the
room or the kids were screaming. It must've been of great
significance to, I figure, about 12 people on this planet.
662.140DISCOVERY to land todayADVAX::KLAESAll the Universe, or nothing!Mon May 06 1991 11:3181
Article         1263
From: [email protected] (WILLIAM HARWOOD, UPI Science Writer)
Newsgroups: clari.tw.space,clari.news.aviation,clari.news.military
Subject: Discovery crew packs for landing
Date: 6 May 91 12:56:48 GMT
  
	CAPE CANAVERAL, Fla. (UPI) -- The Discovery astronauts were cleared
for a California landing Monday after launching a top-secret Pentagon
satellite to complete the final major objective of a successful ``Star
Wars'' research flight.
	Air Force Col. John Armstrong, deputy mission director for the
Strategic Defense Initiative Organization, said researchers were 
``absolutely elated with the overall success of this mission.''
	With near-perfect weather expected, commander Michael Coats and co-
pilot Blaine Hammond were scheduled to fire Discovery's twin braking
rockets at 1:54 p.m. EDT Monday to drop the ship out of orbit for an
hourlong glide to touchdown at Edwards Air Force Base, Calif., at 2:49
p.m. EDT, 11:49 a.m. local time.
	``We've accomplished just about everything that we came into space
the last eight days to do, so I think the flight control team and the
crew are all ready to come back home,'' said flight director Robert
Kelso. ``ALl the payloads are buttoned up in the shuttle and ready to
come back home.''
	Joining Navy Capt. Coats, 45, and Air Force Lt. Col. Hammond, 39,
aboard Discovery were Gregory Harbaugh, 35, Air Force Col. Guion
Bluford, 48, Richard Hieb, 35, Air Force Lt. Col. Donald McMonagle, 38,
and Charles Lacy Veach, 46.
	The astronauts completed the final primary goal of the flight at 4:17
a.m. Monday when they launched a small, top-secret Pentagon satellite.
While the 40th shuttle mission was conducted on an unclassified basis,
details about a satellite were not revealed.
	The shuttle crew took a moment Sunday to mark the 30th anniversary of
former astronaut Alan Shepard's pioneering launch aboard a one-man
Mercury capsule May 5, 1961, to become the first American in space.
	``Thirty years ago, we were flying one man at a time,'' Coats radioed
mission control in Houston. ``Now, we're flying seven or more. We're all
wondering what it's going to be like 30 years from now, how many people
will be up here and in what kind of vehicle. Happy anniversary from the
(Discovery) crew.''
	NASA Administrator Richard Truly said in a message, ``We should
remember that event and all the members of the NASA team that have
worked so hard to make 30 years of manned spaceflight possible. Your
flight is an extension of that great tradition.''
	The astronauts worked through the day Sunday and into the night
wrapping up their Pentagon experiments to close out a 3.5 million-mile,
134-orbit mission to help Strategic Defense Initiative researchers learn
more about detecting enemy missiles in space.
	One of three secondary experiments that were hot-wired Saturday in a
complex shuttle repair job shut itself off early Sunday because of an
unknown problem. Efforts to revive the instrument, an X-ray sensor built
to verify arms control treaties, were not successful.
	The other two instruments, however, were able to complete their
planned observations and given the success of Discovery's two primary
payloads -- a $94 million ``Star Wars'' satellite and an infrared
telescope called CIRRIS -- NASA officials said the flight had
accomplished virtually all of its goals.
	With Discovery's flight winding down, engineers at the Kennedy Space
Center are pressing on with work to ready the shuttle Columbia for
blastoff in just 17 days, on May 22. If the schedule holds up, NASA will
chalk up its third shuttle launch in just 47 days, beating a 1985 record
by a full week.
	Columbia's four-man, three-woman crew flew to the Kennedy Space
Center on Sunday to review emergency procedures and to participate in
the final hours of a dress-rehearsal countdown Tuesday that will set the
stage for launch on the year's third shuttle flight.
	But the Columbia crew will have a difficult time topping the
performance of Discovery's astronauts, who managed to accomplish
virtually all of the themission's major objectives despite one of the
most complex flight plans in shuttle history.
	Coats and his six crewmates used the CIRRIS telescope during the
first two days of the mission to make more space-based observations of
Earth's shimmering auroras than had been accomplished in the history of
space flight.
	The CIRRIS instrument also completed landmark observations of Earth's
atmosphere in research critical to SDI scientists who must design
sensors capble of spotting incoming missiles against a variety of
natural backdrops.
	As for the appearance of such missiles, the astronauts launched the 
``SPAS-2'' satellite Wednesday that was used to photograph a spectacular
series of shuttle rocket firings from up to 6 miles away.

662.141Status Report 19 - May 4ADVAX::KLAESAll the Universe, or nothing!Mon May 06 1991 11:3656
Article         8026
From: [email protected] (Peter E. Yee)
Newsgroups: sci.space.shuttle
Subject: Mission Control Status Report for 05/04/91 [#19, 1130 CDT] (Forwarded)
Date: 6 May 91 01:07:19 GMT
Sender: [email protected] (USENET Administration)
Organization: NASA Ames Research Center, Moffett Field, CA
 
 
	MISSION CONTROL STATUS REPORT #19
	11:30 a.m. CDT -- May 4, 1991
 
 
Crew members aboard Discovery successfully performed a two
hour operation to bypass the experiment support structure
tape recorders and send data directly to the White Sands, NM
ground station in support of three secondary experiments
mounted on the Air Force Program-675 payload in the payload bay.
 
The procedure began just before 8 a.m. CDT and data was beginning
to be received and recorded at White Sands at about 10:15.
 
The procedure involved routing wires through a data tranfer
cable under the command and monitor panel on the aft flight
deck of Discovery and attaching a splice wire to the Ku-band
antenna system for direct transmission of the data from
several secondary payload experiments on the AFP-675.
 
The experiment data recovered is from the Uniformly Redundant
Array (URA) which studies sources of X-ray radiation; the
Horizon Ultraviolet Program (HUP) which measures spatial and
spectral characteristics of the Earth's horizon in the
ultraviolet wavelength; and the Quadrupole Ion-Neutral Mass
Spectrometer (QINMS) which collects data on the orbiter
environment, specifically levels of hydrogen, oxygen, water
vapor and other gases that may be present.
 
Before, during and after the in-flight maintenance (IFM)
procedure, data collection continued using the Infrared
Background Signature Survey satellite by maneuvering it to
various positions for observations of the Earth's horizon at
night, dawn and during the daytime.
 
IBSS also continued collecting data after being restowed in
Discovery's payload bay.
 
The IBSS also was used to observe three gas releases of Neon,
Xenon, Carbon Dioxde and Nitrous Oxide from the Critcal
Ionizaton Velocity experiment in the payload bay.
 
After berthing the shuttle pallet satellite (SPAS), the robot
arm was placed in its cradle and powered down for the
remainder of the flight.
 
All systems aboard Discovery continue to peform well with no
significant problems being worked by flight controllers.
662.142I'm glad they had the manual...DECWIN::FISHER&quot;I am NOT a Merry Man&quot;--WorfMon May 06 1991 13:244
How would you like to reach behind the panels of this machine which is
keeping you alive and start clipping wires?

Burns
662.143DISCOVERY lands in FloridaADVAX::KLAESAll the Universe, or nothing!Mon May 06 1991 18:1388
Article         1268
From: [email protected] (WILLIAM HARWOOD, UPI Science Writer)
Newsgroups: clari.tw.space,clari.news.aviation,clari.news.military
Subject: Discovery glides to smooth touchdown
Date: 6 May 91 19:05:41 GMT 
 
	CAPE CANAVERAL, Fla. (UPI) -- The shuttle Discovery plunged
across the heartland of America and glided to a rare Florida landing
Monday to close out a successful ``Star Wars'' flight after high winds
blocked a California touchdown. 
	Heralded by two shotgun-like sonic booms, commander Michael
Coats and co-pilot Blaine Hammond piloted Discovery through a sweeping
left overhead turn, guiding the ship to a flawless touchdown on the
Kennedy Space Center's 3-mile-long shuttle runway at 2:56 p.m. EDT. 
	``Houston, Discovery; wheels stopped,'' Coats radioed mission control
after bringing the 100-ton spaceplane to a halt, winding up only the
second Florida landing in six years.
	``Roger, Discovery. Welcome back to sunny Florida and congratulations
on an outstanding mission,'' replied astronaut Kenneth Bowersox from
Houston.
	Just a few miles away, the crew of the shuttle Columbia reviewed
emergency procedures at launch pad 39B during a dress-rehearsal
countdown that sets the stage for liftoff in just 16 days, on May 22, to
kick off a nine-day Spacelab astronomy mission. But all eyes were on
Discovery Monday.
	Despite the last-minute change in landing sites, Air Force Col. John
Armstrong, deputy mission director for the Strategic Defense Initiative
Organization, said researchers were ``absolutely elated with the overall
success of this mission.''
	Coats, 45, Hammond, 39, and their crewmates -- Gregory Harbaugh, 35,
Guion Bluford, 48, Richard Hieb, 35, Donald McMonagle, 38, and Charles
Lacy Veach, 46 -- planned to fly back to their homes in Houston later in
the day after brief medical exams and routine de-briefing.
	The astronauts had planned to close out the 134-orbit, 3.5-million-
mile voyage with a landing at Edwards Air Force Base in California's
Mojave Desert. But unexpected high winds, and a forecast of more of the
same Tuesday, prompted flight director Lee Briscoe to divert the crew to
Florida instead.
	Discovery's re-entry carried it over parts of Alaska and western
Canada before a steep, high-speed plunge over middle America to only the
seventh Florida touchdown in 40 flights, the second since April 19,
1985, when one of Discovery's landing gear tires blew out.
	NASA currently is in the process of testing new carbon brakes
to make landings at the space center safer. The shuttle Atlantis made
a safe Florida landing last November after high winds blocked an
Edwards touchdown. 
	The goal of Discovery's eight-day flight was to learn how to detect
enemy missiles in space against a variety of natural backdrops including
Earth, it's atmosphere and the shimmering aurora, which can mask an
incoming rocket.
	The crew also launched a $94.2 million ``SPAS-2'' satellite to
observe the appearance of repeated shuttle rocket firings that sent
Discovery cartwheeling through space in one of the most complicated
orbital ballets ever attempted.
	The astronauts accomplished 32 of 33 planned primary
observations, 18 of 21 secondary observations and 41 of 44 category-3
experiments, a remarkable record for any shuttle flight but especially
so for Discovery's action-packed mission. 
	``It promises to be a giant step forward for tracking objects, for
our understanding of the aurural effects and how that might disguise any
observations,'' Armstrong said. ``It has tremendous potential.''
	Instruments aboard SPAS-2 observed 15 shuttle rocket firings
from up to 6 1/2 miles away. SPAS-2 and other instruments completed
eight unprecedented auroral measurements, 15 atmospheric and Earth
observations and studied the appearance of seven rocket-related
chemicals that were released in space. 
	Along with making pioneering ultraviolet observations, the astronauts
also hot-wired three experiments that were derailed by faulty tape
recorders. Finally, the crew launched four satellites in addition to
SPAS-2, which was brought back to Earth aboard Discovery.
	As Discovery's mission was winding up, engineers at nearby launch pad
39B at the Kennedy Space Center started a dress-rehearsal countdown Monday 
for the shuttle Columbia, setting the stage for the year's third mission.
	If the schedule holds up, Columbia's launch will mark NASA's
third in just 47 days, beating a record set in 1985 by a full week.
The ship's four-man, three-woman crew planned to strap in aboard the
shuttle early Tuesday for the final hours of the mock countdown. 
	Columbia's crew will be hard pressed to top the performance of
Discovery's seven astronauts, who accomplished virtually all of their
major objectives despite one of the most complicated flight plans in
shuttle history.
	``We're all excited about not only the tremendous data that we've
helped collect for our customers on this flight, but also excited by the
performance of this flight crew and the flight control team,'' said
flight director Robert Kelso. ``In my judgment, this flight has pushed
out new limits for NASA, for what we can achieve for our customers in
the use of the shuttle program.''

662.144DISCOVERY landed "hot" at KSC25626::KLAESAll the Universe, or nothing!Thu May 09 1991 10:4269
Article         1281
From: [email protected] (WILLIAM HARWOOD, UPI Science Writer)
Newsgroups: clari.tw.space,clari.news.aviation,clari.news.military
Subject: Discovery's landing 'hot'
Date: 9 May 91 11:50:45 GMT 
 
	CAPE CANAVERAL, Fla. (UPI) -- The shuttle Discovery touched
down at a blistering 242 mph Monday -- one of the fastest landings on
record -- a scant 168 feet past the threshold of the Kennedy Space
Center's 3-mile-long runway, officials say. 

	The shuttle Atlantis landed some 600 feet short of its
California runway last month and given Discovery's safe but somewhat
off-balance touchdown Monday, the debate about when shuttles might be
cleared for routine Florida landings likely will intensify. 

	With commander Michael Coats and co-pilot Blaine Hammond at
the controls, the 210,800-pound Discovery's right-side main landing
gear tires hit the runway first with the left-side gear touching down
215 feet farther along. The shuttle's nose gear touched down 4,723
feet down the landing strip. 

	Discovery, diverted from a planned California landing because
of high winds, was descending at a routine 2 feet per second when it
landed at 242 mph, one of the fastest shuttle touchdowns on record. 

	After rolling 6,316 feet along the 3-mile-long runway, Coats
applied 37 million foot pounds of energy to the shuttle's right-side
brakes and another 30 million foot pounds to the left-hand landing
gear, bringing Discovery to a stop 9,152 feet down the runway, one of
the longest ``rollouts'' in shuttle history. 

	The somewhat off-balance landing resulted in unusual tire
damage, officials said. But a NASA spokesman said Wednesday the crew
was never in any danger of a blowout. 

	``The landing gear tires contain 16 plies of material,'' said
NASA spokesman Kyle Herring. ``Normally, a blowout or flat could not
occur unless at least eight or more were lost from a tire. The
right-hand main landing gear outboard tire was the most worn, losing
up to three plies of material.'' 

	New , more durable tires made of synthetic rubber are
scheduled to debut later this year. 

	Discovery's landing marked only the seventh Florida shuttle
touchdown in 40 flights to date and only the second since April 1985
when the ship blew a tire during touchdown in a stiff crosswind. 

	Since then, Edwards Air Force Base, Calif., has been the
shuttle program's prime landing site pending tests of new, beefed up
brakes and other landing systems intended to make touchdowns on
Florida's single runway safer. 

	Coats conducted a braking test during landing Monday as part of 
that program, but whether it contributed to the tire damage was not known. 

	The shuttle Atlantis landed 600 feet short of a dry lakebed
runway threshold at Edwards April 11, primarily because of shifting
winds. The shuttle runway in Florida has 1,000 feet of load-bearing
``overrun'' at either end and had Coats landed as short as Atlantis,
the ship still would have been safe, officials said. 

	But landing problems are inherently easier to handle at
Edwards, where numerous dry lakebed runways are available. Given the
unusual nature of the last two shuttle touchdowns, debate about the
safety of using the Kennedy Space Center as the program's prime
landing site is sure to continue. 

662.145STS-39 Update - May 825626::KLAESAll the Universe, or nothing!Thu May 09 1991 10:4328
Article         8069
From: [email protected] (Peter E. Yee)
Newsgroups: sci.space.shuttle
Subject: Shuttle Status for 05/08/91 (Forwarded)
Date: 8 May 91 22:23:14 GMT
Sender: [email protected] (USENET Administration)
Organization: NASA Ames Research Center, Moffett Field, CA 
 
          KSC SHUTTLE STATUS REPORT - WEDNESDAY, MAY 8, 1991 - 11:30 AM
 
                     STS-39/DoD - DISCOVERY (OV 103) - OPF BAY 1
  
          WORK IN PROGRESS:
          - Offloading of residual propellant from the  fuel  cell  storage
          tanks. (Certain areas are cleared for this operation.)
          -  Installing access platforms in various areas including the aft
          compartment.
 
          WORK SCHEDULED:
          - Opening of the payload bay doors Friday.
          - Post flight inspections
          - Replacement of thermal barriers between tiles on the  orbiter's
          belly.  About  twice as many fillers as usual will have to be re-
          placed because of over-temperature conditions experienced  during
          this  particular re-entry.  Initial indications are that about 10
          tiles will  need  to  be  replaced  as  a  result  of  the  over-
          temperature conditions.

662.146VAX 6000 in space aboard Shuttle25626::KLAESAll the Universe, or nothing!Thu May 23 1991 18:2947
VNS COMPUTER NEWS:                            [Tracy Talcott, VNS Computer Desk]
==================                            [Nashua, NH, USA                 ]

 Digital - VAX in space aboard Discovery shuttle

	{Livewire, Worldwide News, 6-May-91}

   One of Digital's specially designed VAX computers was aboard the shuttle 
 Discovery as part of the NASA experiment to test the use of commercial
 computer software technology in space. Orbiting the globe in the shuttle's 
 cargo bay was a militarized version of the VAX 6000 series computer technology
 produced by Raytheon Co., a Digital licensee, to meet the rigors of space
 travel as part of NASA's Data Systems Experiment (DSE). The DSE project, a
 joint effort by Digital and NASA, supports a new initiative for the Space
 Shuttle system under the "Hitchhiker" program. The experiment involved a
 computer in space generating commands for a robotic system situated at the
 Goddard Space Flight Center in Greenbelt, Md.    

   The successful tests verified that standard VAX commercial architecture and
 standard commercial software, VMS and the ADA Language, can be used in the
 harsh environment of space. "This could mean a tremendous cost savings by
 eliminating the need for many custom written software programs," said Harvey
 Weiss, vice president Government Systems.

   The Mil-Spec computer was produced by Raytheon's Equipment Division and 
 delivered to NASA in October 1989. The computer is a Raytheon Model 860 VAX 
 computer presently being delivered to the military, but modified to resist the
 rigors of space travel, such as the extreme forces of a rocket launch, the
 vacuum of space and the temperature extremes of the intended application. 

   Future NASA projects such as the Space Station Freedom and the Mission to 
 Planet Earth Observation Satellites will use computer systems that can benefit
 from the availability of commercial standard parts and software. The Data
 Systems Experiment is one of the first steps to qualify the use of commercial
 computer architectures and software in space.
 ---
 Ada Language is a trademark of the Department of Defense. 

<><><><><><><><><><><><><><><><><><><><><><><><><><><><><><><><><><><><><><><><>
        Please send subscription and backissue requests to CASEE::VNS

    Permission to copy material from this VNS is granted (per DIGITAL PP&P)
    provided that the message header for the issue and credit lines for the
    VNS correspondent and original source are retained in the copy.

<><><><><><><><>   VNS Edition : 2322     Tuesday 14-May-1991   <><><><><><><><>

662.147Mission HighlightsPRAGMA::GRIFFINDave GriffinFri May 31 1991 09:54255
STS-39 Mission Highlights

Space Shuttle Discovery
 April 28 - May 6, 1991
Commander: Michael L. Coats, Capt., USN
Pilot: L. Blaine Hammond, Lt. Col., USAF
Mission Specialists:
 Gregory J. Harbaugh
 Donald R. McMonagle, Lt. Col., USAF
 Guion S. Bluford, Col., USAF
 C. Lacy Veach
 Richard J. Hieb


Major Mission Accomplishments

% Conducted a wide range of experiments supporting the U.S. Air Force's
studies of upper atmospheric phenomena and the Strategic Defense Initiative
Organization's work in characterizing rocket engine exhaust plumes.

% Made the first rocket engine plume observations ever outside Earth's
atmosphere. (Sponsored by the Strategic Defense Initiative Organization.)

% Executed a record 35 firings of the orbital maneuvering and reaction
control systems.

% Conducted extensive studies of upper atmospheric aurora and airglow limb
emissions. (Sponsored by the USAF Systems Command-Space Systems Division.)

% Deployed three Chemical Release Observation (CRO) subsatellites for
simultaneous space and ground observations of gas releases. (Sponsored by
the USAF Systems Command-Space Systems Division.)

% Deployed a classified Multipurpose Experiment Canister. (Sponsored by the
USAF Space Systems Division.)

% Collected infrared, ultraviolet, and visible light data on auroras, solar
spectra, Earth airglow limb, and stellar objects to learn how better to
distinguish natural from human-made phenomena. (Sponsored by the Strategic
Defense Initiative Organization.)

% Took advantage of the high inclination of Discovery's orbit to take color
and infrared pictures of important Earth surface features and phenomena,
including Lake Baikal in the USSR, oil field fires in Kuwait, and the
devastating typhoon in the Indian Ocean.

% First Space Shuttle crew consisting of seven NASA astronauts.




With its touchdown at the Kennedy Space Center on May 6, 1991, the Space
Shuttle Discovery completed one of the most complicated shuttle flights to
date.  STS-39 was an unclassified Department of Defense mission that sought
to enhance national security by gathering scientific data essential to the
development of advanced missile detection systems.  

The seven-member crew of Discovery conducted a variety of sophisticated
experiments that included the deployment of five spacecraft (SPAS II/IBSS,
Multipurpose Experiment Canister, and three CRO) from the payload bay and
the retrieval of one of these spacecraft later.  Because of their high
orbital inclination (57 degrees with respect to Earth's equator) they flew
directly over most major land masses on Earth and were able to take
extensive photos of Earth's resources.  One of the major payloads on STS-39
was a cluster of experiments sponsored by the Strategic Defense Initiative
Organization and the Air Force Systems Command's Space Systems Division. 

The Air Force Program-675 (AFP-675) payload consisted of five instruments
designed to observe targets--such as the atmosphere, aurora, and stars--in
infrared, far ultraviolet, and X-ray wavelengths.  One of the most
important experiments in this cluster was CIRRIS (Cryogenic Infrared
Radiance Instrumentation for Shuttle). Using an infrared detector, which
required chilling with supercold liquid helium to achieve maximum
sensitivity, the CIRRIS instrument studied airglow and auroral emissions in
Earth's upper atmosphere to determine their characteristics in the infrared
region of the electromagnetic spectrum.  

Due to a faster than anticipated consumption of liquid helium coolant,
early completion of the CIRRIS experiment became a priority and resulted in
delaying the deployment of the SPAS II/IBSS spacecraft by 24 hours.  During
the operation of CIRRIS, both STS-39 crew and scientists on the ground were
treated to spectacular and unusually intense auroral displays.  

As Discovery passed through the aurora australis (southern lights) over the
South Atlantic Ocean, STS-39 commander Mike Coats reported, "It's just like
flying through a curtain of light." Understanding auroras is important,
because the radiations they produce can interfere with early missile
detection. As a result of the rescheduling and the efforts of the STS-39
crew, CIRRIS scientists were rewarded with 50 percent greater return of
data than they had planned.  

Other experiments in the AFP-675 payload included the FAR Ultraviolet
Cameras (FAR UV), Uniformly Redundant Array (URA), Horizon Ultraviolet
Program (HUP), and the Quadrupole Ion-Neutral Mass Spectrometer (QINMS). 
URA, HUP, and QINMS were adversely affected after about four hours of
operation on flight day one when two tape recorders gathering data failed. 
In a convincing demonstration of the value of a human presence in orbit,
STS-39 crew members, through a complicated bypass repair operation,
successfully rerouted data from these instruments to an orbiter antenna. 
The data were then transmitted directly to two Tracking Data Relay
Satellites for relay to the ground, fulfilling the objectives of those four
experiments.  

On flight day four, Discovery's remote manipulator system arm was used by
the crew to grasp the SPAS II/IBSS spacecraft.  The SPAS II (Shuttle Pallet
Satellite carrier) is a free-flying satellite that can provide support for
a variety of instruments and permit them to be independently flown in space
from the Space Shuttle. When lifted out of the payload bay, it can be
released to operate in orbit at varying distances from the Shuttle. At the
completion of its tasks, it is captured by the arm and replaced in the
payload bay for return to Earth. 

On STS-39, the SPAS II spacecraft was a part of the IBSS (Infrared
Background Signature Survey) experiment sponsored by the Strategic Defense
Initiative Organization. Two scientific instruments were mounted on the
SPAS II; an infrared telescope and the Arizona Imaging Spectrometer (AIS). 
The infrared telescope contained detectors for creating infrared images and
for spectral analysis.  The AIS contained detectors capable of creating
images in the ultraviolet, infrared, and visible parts of the spectrum.  

After its deployment on the SPAS II carrier spacecraft, the IBSS experiment
instruments were used to image and measure the spectral nature of rocket
exhaust plumes.  Discovery was maneuvered away from IBSS to various
distances ranging from 2 to nearly 11 km. By firing Discovery's reaction
control engines and orbital maneuvering system engines while positioned in
a variety of different attitudes, these experiments permitted scientists to
compare known firing directions, burn durations, and chemical compositions
of Discovery's exhaust gases to the spectral data collected by the
instruments on the IBSS. Such data will aid future missile detection
systems to determine the trajectory of missiles more accurately.  

In additional studies with the IBSS, measurements of chemical releases were
made. In one experiment, four different gases were released from containers
in the payload bay and observed by the IBSS sensors looking back at the
orbiter. These gases included xenon, neon, carbon dioxide, and nitrous
oxide.  In addition, three small CRO subsatellite canisters carrying
various chemicals were ejected from Discovery's payload bay.  After the
canisters had drifted to distances ranging from 50 to 95 km away from
Discovery, they each released short-lived clouds of chemical rocket fuels
and oxidizers.  Simultaneous observations of these releases were made by
the IBSS in orbit and with Earth-based instruments at the Vandenburg Air
Force Base in California.

Observation of the third release was made following the SPAS II/IBSS
retrieval. SPASII/IBSS was raised above Discovery's payload bay at the end
of the remote manipulator system arm.  A great many other observations were
made with the IBSS instrument in the free-flying mode, attached to the end
of the arm, and from within the payload bay.  Included were studies of
Earth limb, aurora, orbiter environment, stars, and Shuttle glow.  

During the mission, STS-39 crew members took advantage of their high view
of Earth to take many pictures that can be used by researchers in the study
of environmental problem areas. Astronauts photographed black smoke palls
from the oil field fires in Kuwait and smoke palls from fires in Central
America that had drifted as far north as Texas and as far east as Florida.
They observed, from above, the typhoon in the Indian Ocean's Bay of Bengal
that devastated Bangladesh and left more than 100,000 people dead.  Over
the Soviet Union, crew members photographed Lake Baikal, which is of
interest to geologists because of its location in the northernmost part of
the area where the Indian continental plate is colliding with the Eurasian
plate.  

Although the STS-39 mission experienced occasional instrument problems
during the flight, teamwork between the crew and mission control permitted
a high rate of data return and the accomplishment of virtually all mission
objectives.  

The mission concluded with Discovery's landing at the Kennedy Space Center
in Florida when high crosswinds at the planned landing site in California
prohibited a safe landing there.

Crew Biographies

Commander: Michael L. Coats (Capt., USN). Michael Coats was born in
Sacramento, California but considers Riverside, California his hometown. 
He graduated from the U.S. Naval Academy and earned a master of science
degree in aeronautical engineering from the U.S. Naval Post Graduate
School. Coats was a combat pilot in Southeast Asia and a test pilot before
joining NASA. He served as the pilot of the STS-41D mission and commander
of STS-29. 

Pilot: L. Blaine Hammond, Jr. (Lt.  Col., USAF). Blaine Hammond was born in
Savannah, Georgia and received a bachelor of science degree from the U.S.
Air Force Academy and a master of science degree from the Georgia Institute
of Technology. Before joining NASA, he was an Air Force pilot and a test
pilot instructor.  This was his first flight on the Space Shuttle. 

Mission Specialist: Gregory J. Harbaugh. Gregory Harbaugh was born in
Cleveland, Ohio but considers Willoughby, Ohio his hometown.  He attended
Purdue University and received a bachelor of science degree in aeronautical
engineering.  He also earned a master of science degree in physical
sciences from the University of Houston-Clear Lake. Harbaugh served in
engineering and management positions at NASA before becoming an astronaut.
This was his first space flight.  

Mission Specialist: Donald R. McMonagle (Lt. Col., USAF). Donald McMonagle
comes from Flint, Michigan and received a bachelor of science degree in
aeronautical engineering from the Air Force Academy and a master of science
degree in mechanical engineering from California State University-Fresno.
He has been an Air Force pilot and test pilot.  This was his first space
flight.  

Mission Specialist: Guion S. Bluford (Col., USAF). Guion Bluford was born
in Philadelphia, Pennsylvania and received a bachelor of science degree in
aerospace engineering from Pennsylvania State University and a master of
science degree in the same subject from the Air Force Institute of
Technology. He earned a doctorate in aerospace engineering from the Air
Force Institute of Technology and a master of business administration
degree from the University of Houston-Clear Lake. Bluford has flown on the
STS-8 and STS 61-A missions.  

Mission Specialist: C. Lacy Veach. Lacy Veach was born in Chicago, Illinois
but considers Honolulu, Hawaii his hometown.  He earned a bachelor of
science degree in engineering management from the Air Force Academy. He has
been a fighter pilot and a member of the Thunderbirds Air Force
Demonstration Squadron. Veach joined NASA as an engineer and research pilot
before becoming an astronaut.  This was his first space flight.  

Mission Specialist: Richard J. Hieb. Richard Hieb was born in Jamestown,
North Dakota and earned a bachelor of arts degree in math and physics from
Northwest Nazarene College and a master of science degree in aerospace
engineering from the University of Colorado. Before becoming an astronaut,
he worked for NASA in mission control and specialized in rendezvous and
proximity operations.

                Mission Facts

Orbiter: Discovery 
Mission Dates: April 28-May 6, 1991 
Commander: Michael L. Coats, Capt., USN 
Pilot: L. Blaine Hammond, Lt. Col., USAF 
Mission Specialist: Gregory J. Harbaugh 
Mission Specialist: Donald R. McMonagle, Lt. Col., USAF
Mission Specialist: Guion S. Bluford, Col., USAF 
Mission Specialist: C. Lacy Veach 
Mission Specialist: Richard J. Hieb
Mission Duration: 8 days, 7 hours, 22 minutes 
Distance Traveled: 5,594,750 km 
Orbit Inclination: 57 degrees 
Orbits of Earth: 134
Orbital Altitude: 260 km 
Payload Weight Up: 5,102 kg 
Orbiter Landing Weight: 96,045 kg 
Landed: Kennedy Space Center 
Payloads and Experiments:
  AFP-675
  SPAS-II/IBSS
  Space Test Payload-1
  Multi-Purpose Experiment Canister
  Chemical Release Observation
  Critical Ionization Velocity
  Radiation Monitoring Experiment-III
  Cloud Logic to Optimize the Use of Defense Systems
  Educational Activities Educational videotaping