[Search for users] [Overall Top Noters] [List of all Conferences] [Download this site]

Conference 7.286::space

Title:Space Exploration
Notice:Shuttle launch schedules, see Note 6
Moderator:PRAGMA::GRIFFIN
Created:Mon Feb 17 1986
Last Modified:Thu Jun 05 1997
Last Successful Update:Fri Jun 06 1997
Number of topics:974
Total number of notes:18843

633.0. "STS-38 ATLANTIS (DOD)" by 4347::GRIFFIN (Dave Griffin) Mon Jun 11 1990 12:07

From: [email protected] (WILLIAM HARWOOD, UPI Science Writer)
Newsgroups: clari.tw.space,clari.news.aviation,clari.news.military,clari.news.urgent
Subject: Shuttle Atlantis moved
Date: 8 Jun 90 21:50:14 GMT

	CAPE CANAVERAL, Fla. (UPI) -- The shuttle Atlantis was hauled from
its hangar to NASA's rocket assembly building Friday in preparation for
movement next week to launch pad 39A and blastoff in July on a secret
military mission.

T.RTitleUserPersonal
Name
DateLines
633.1Shuttle Status for 06/11/904347::GRIFFINDave GriffinTue Jun 12 1990 14:0216
From: [email protected] (Peter E. Yee)
Newsgroups: sci.space.shuttle
Date: 11 Jun 90 18:57:53 GMT
Organization: NASA Ames Research Center, Moffett Field, CA

 
                KSC SHUTTLE STATUS - MONDAY JUNE 11, 1990  11:30 A.M.

                         STS-38 - ATLANTIS (OV 104) - VAB

               Atlantis  was  transferred  to the Vehicle Assembly Building
          Friday and hard mated to the  external  tank  by  about  10  p.m.
          Saturday.  There  were  no  problems reported with the connection
          process.  Atlantis is scheduled to be powered  up  after  carrier
          panels are mated to the tail service masts. Rollout to Launch Pad
          39-A is scheduled for 12:01 a.m. Saturday, June 16.
633.2Status reports - 6/13, 6/144347::GRIFFINDave GriffinFri Jun 15 1990 10:5742

                    Wednesday June 13, 1990           10:00 a.m.

                     KSC Space Shuttle Processing Status Report


                  STS-38  --  Atlantis (OV 104)  -  VAB High Bay 1


               Mating and closeout operations are continuing on the Shuttle
          Atlantis today in VAB high bay 1. The liquid hydrogen and liquid
          oxygen carrier plates have been mated and electrical mates are
          complete. The orbiter was powered up at 9:00 a.m. this morning
          followed directly by electrical interface and verification tests.
          Testing is currently in work. Rollout to pad A is tentatively
          scheduled for early Saturday morning. However, rollout is
          currently being assessed and may be set for early Monday morning.
          Word is expected later today on any changes. Atlantis' next
          flight is a DOD dedicated mission slated for mid-July 1990.




               KSC SHUTTLE STATUS - THURSDAY JUNE 14, 1990  9:30  A.M

                          STS-38 - ATLANTIS (OV 104) - VAB

               Atlantis was powered up yesterday for the Shuttle  Interface
          Test  of  the  critical connections between the vehicle elements.
          The test is scheduled to be completed  by  tomorrow  and  rollout
          preparations  will  begin.  Rollout  to  Launch  Pad  39-A is now
          scheduled for 12:01 a.m. Monday, June 18.

               The Countdown Demonstration Test with the STS-38 flight crew
          is planned for June 20-21.


From: [email protected] (Peter E. Yee)
Newsgroups: sci.space.shuttle
Date: 14 Jun 90 20:28:38 GMT
Organization: NASA Ames Research Center, Moffett Field, CA
633.3Atlantis hauled to launch pad4347::GRIFFINDave GriffinTue Jun 19 1990 12:5358
From: [email protected] (WILLIAM HARWOOD, UPI Science Writer)
Newsgroups: clari.tw.space,clari.news.aviation
Date: 18 Jun 90 15:59:16 GMT

	CAPE CANAVERAL, Fla. (UPI) - The shuttle Atlantis was slowly hauled
to the launch pad Monday for blastoff around July 13 on a secret
military mission, replacing the crippled shuttle Columbia in NASA's
revised flight schedule.
	Atlantis, mounted atop a squat mobile launch platform and carried
by a powerful crawler-transporter, began the 3.5-mile trip from the
Vehicle Assembly Building to launch pad 39A at 11:16 p.m. EDT Sunday,
about 45 minutes ahead of schedule.
	``It's been a smooth activity. It's run ahead of schedule all
night,'' said NASA spokesman George Diller. ``First motion was 11:16
p.m. and we were atop pad A at 5:30 a.m., a good hour and a half earlier
than (had been expected).''
	He said engineers planned to test fire the shuttle's hydraulic
power units late Monday after hooking up fuel lines and completing a
variety of electrical and mechanical connections between the spaceship
and the launch pad.
	Air Force Col. Richard Covey, Atlantis's commander, Navy Cmdr.
Frank Culbertson, the co-pilot, Marine Col. Robert Springer, Air Force
Lt. Col. Carl Meade and Army Capt. Charles Gemar planned to fly to the
Kennedy Space Center Monday night to participate in a practice countdown
Wednesday and Thursday.
	Details about the flight are classified, but sources have said
launch is planned for around 8 a.m. July 13 and that the mission is
scheduled to last about four days. The shuttle's typical altitude will
be 190 miles in an orbit tipped 28.5 degrees to the equator.
	The launch schedule flip flop between Atlantis and Columbia was
ordered by NASA managers to minimize the impact of the fuel leak that
grounded Columbia the night before its planned takeoff May 30 on a
10-day astronomy mission.
	NASA managers decided Monday to order a special test in which
supercold liquid hydrogen will be pumped aboard Atlantis's external tank
to make sure the ship does not have a similar problem to the one that
grounded Columbia. The test likely will be scheduled early next week,
officials said.
	Engineers traced Columbia's leak to a 17-inch-wide fuel line
fitting where the ship's main liquid hydrogen line enters the belly of
the orbiter. But technicians were unable to isolate the problem area and
NASA managers had little choice but to order Columbia back to its hangar
for a detailed inspection.
	The part of the ``17-inch disconnect'' fitting on the external tank
side of the big umbilical will be shipped back to the manufacturer
Tuesday.
	If tests fail to find a leak, the corresponding valves and plumbing
on the shuttle side of the fitting will be removed and replaced with
hardware currently installed in NASA's newest shuttle, the Endeavour.
	In either case, NASA officials say Columbia will be ready for
another launch attempt around Aug. 12.
	As for Atlantis, Covey and company planned to participate in the
practice countdown this week and to review emergency launch pad escape
procedures, a traditional milestone before any shuttle flight.
	If all goes well, the astronauts, dressed in bulky spacesuits, will
strap in aboard Atlantis Thursday for the final hours of the mock
countdown, scheduled to end with the simulated ignition and shutdown of
the shuttle's three main engines.
633.4Shuttle status 6/18/90, 6/19/904347::GRIFFINDave GriffinWed Jun 20 1990 11:0962
                KSC SHUTTLE STATUS - MONDAY JUNE 18, 1990  11:30  A.M

                    STS-38 - ATLANTIS (OV 104) - LAUNCH PAD 39-A

               Atlantis was rolled out to Launch  Pad  39-A  this  morning.
          First  motion  occurred last night at 11:16 p.m.  and the vehicle
          was harddown on the pad's pedestals at about  5:23  a.m.    Tech-
          nicians  are  making  connections between the pad and vehicle are
          underway.  Preparations are in work to perform a  "hot  fire"  of
          auxiliary  power units 1 and 2 early tomorrow morning.  The units
          will be run for 7 minutes each.

               The Countdown Demonstration Test with the STS-38 flight crew
          is planned for June 20-21. The flight crew is scheduled to arrive
          at KSC's Shuttle Landing Facility tonight at 8:30  p.m.  to  par-
          ticipate in the launch countdown dress rehearsal.

               Space  Shuttle  Director Robert Crippen has directed the KSC
          launch team to begin preparations for a mini tanking test on  Pad
          A.  The  test which will be similar to the one performed on Space
          Shuttle Columbia earlier this month,  will involve a small amount
          of  hydrogen  being  pumped  into the external tank and Atlantis'
          main propulsion system.  The test is currently planned  for  mid-
          next week.

               Shuttle  managers  are conducting this test to confirm their
          belief that the leak problem experienced with STS-35 and Columbia
          is unique to that mission.  The test will also give engineers ad-
          ditional  information  to compare as they study the data from the
          STS-35 tanking test.

               The addition of a tanking test in the processing of  Shuttle
          mission  STS-38  is  expected to have little impact to the launch
          schedule.  The official launch date for STS-38 will be set at the
          Flight Readiness Review.



                 KSC SHUTTLE STATUS - TUESDAY JUNE 19, 1990  10  A.M

                    STS-38 - ATLANTIS (OV 104) - LAUNCH PAD 39-A

               Auxiliary power units 1 and 2 were successfully "hot  fired"
          early this morning. The units were run for 7 minutes each at nor-
          mal speed and for 10 seconds at high speed.

               The Countdown Demonstration Test with the STS-38 flight crew
          is  planned for June 20-21.  A simulated engine firing and cutoff
          is scheduled for 11 a.m.  Thursday.  The flight crew  arrived  at
          KSC's  Shuttle  Landing Facility last night at 8:10 p.m.  to par-
          ticipate in the launch countdown dress rehearsal.

               The official launch date for  STS-38  will  be  set  at  the
          Flight Readiness Review next week.


From: [email protected] (Peter E. Yee)
Newsgroups: sci.space.shuttle
Date: 19 Jun 90 18:37:51 GMT
Organization: NASA Ames Research Center, Moffett Field, CA

633.5Shuttle Status for 06/21/904347::GRIFFINDave GriffinThu Jun 21 1990 22:3430

                KSC SHUTTLE STATUS - THURSDAY JUNE 21, 1990  12 NOON

                    STS-38 - ATLANTIS (OV 104) - LAUNCH PAD 39-A

               The Countdown Demonstration Test ended today at 11  a.m.  at
          the  T-5  second  mark.  A simulated engine firing and cutoff oc-
          curred at the conclusion of the countdown as planned.  The STS-38
          flight crew will be returning to their home base in Houston later
          today.

               A  helium  signature leak test of the main propulsion system
          and three main engines is scheduled to begin early tomorrow morn-
          ing and will continue through Friday.  Preparations are  underway
          for  loading  hypergolic  propellants  on  board the orbiter this
          weekend.

               A special tanking test is scheduled for Wednesday morning to
          determine if there are any leaks in the hydrogen  system  similar
          to the one detected on the shuttle Columbia last month.

               The  official  launch  date  for  STS-38  will be set at the
          Flight Readiness Review next Thursday and Friday.  The KSC Launch
          Readiness Review is scheduled for tomorrow afternoon.

From: [email protected] (Peter E. Yee)
Newsgroups: sci.space.shuttle
Date: 21 Jun 90 21:21:23 GMT
Organization: NASA Ames Research Center, Moffett Field, CA
633.6Shuttle Status for 06/25/904347::GRIFFINDave GriffinMon Jun 25 1990 18:3536
                KSC SHUTTLE STATUS - MONDAY JUNE 25, 1990  11:30 a.m.


                    STS-38 - ATLANTIS (OV 104) - LAUNCH PAD 39-A

               Saturday,  workers successfully conducted a helium signature
          leak  test  of the main propulsion system and three main engines.
          The test did not identify any leaks in the system.

               Hypergolic operations were held up about one shift yesterday
          because a transformer shorted out which brought down  the  system
          that supplies cooled air to the Launch Control Center. The cooled
          air  keeps  the  computers  at  the proper temperature for normal
          operations.  Atlantis was powered down while  technicians  recon-
          figured the system supplying cooled air to the LCC.

               Nitrogen  tetroxide  is  being loaded into the orbiter's on-
          board storage tanks  today.  Loading  of  monomethylhydrazine  is
          scheduled to start tomorrow morning. This operation also includes
          loading hydrazine into the orbiter's auxiliary power units and in
          the boosters' hydraulic power units.

               The  special  tanking  test  remains  scheduled for Thursday
          morning.  The Rotating Service Structure will be moved away  from
          the vehicle at midnight Wednesday. Liquid hydrogen will be loaded
          into  the external tank while engineers monitor sensors to deter-
          mine if there are any leaks.

               The official launch date for STS-38 will be set at the  con-
          clusion of the Flight Readiness Review on Friday.


From: [email protected] (Peter E. Yee)
Newsgroups: sci.space.shuttle
Date: 25 Jun 90 17:35:01 GMT
Organization: NASA Ames Research Center, Moffett Field, CA
633.7Shuttle Status for 06/26/904347::GRIFFINDave GriffinWed Jun 27 1990 11:1431
                 KSC SHUTTLE STATUS - TUESDAY JUNE 26, 1990  11 a.m.


                    STS-38 - ATLANTIS (OV 104) - LAUNCH PAD 39-A


               Hypergolic  operations  are  continuing  today.   Yesterday,
          nitrogen  tetroxide was loaded into the orbiter's onboard storage
          tanks.  Today,  monomethylhydrazine is being loaded into  orbiter
          storage  tanks.  These  propellants  will  be used by the orbital
          maneuvering system engines and the reaction control system.  This
          operation  also  includes  loading  hydrazine  into the orbiter's
          auxiliary power units and in the boosters' hydraulic power units.

               The special tanking test call-to-stations is set for 4  p.m.
          Wednesday  and  the test is scheduled to begin Thursday at 4 p.m.
          The Rotating Service  Structure  will  be  moved  away  from  the
          vehicle  at  about  9:30 a.m.  Thursday.  The tank will be filled
          about half full,  or about 200,000 gallons,  of  liquid  hydrogen
          while engineers monitor sensors from the Firing Room to determine
          if there are any leaks.

               The  official launch date for STS-38 will be set at the con-
          clusion of the Flight Readiness Review on Friday.


From: [email protected] (Peter E. Yee)
Newsgroups: sci.space.shuttle
Date: 26 Jun 90 17:59:43 GMT
Organization: NASA Ames Research Center, Moffett Field, CA
633.8a bad week for the space programSTAR::HUGHESYou knew the job was dangerous when you took it Fred.Fri Jun 29 1990 15:416
    I heard a news item that the fast fill part of the tanking test failed
    in the same manner as the Columbia, suggesting a design flaw.
    
    Anyone hear more details?
    
    gary
633.9Shuttle Fleet Grounded!15372::LEPAGEServing the servants of manFri Jun 29 1990 15:459
    	Yes, I heard that the Atlantis is suffering from a fuel leak in the
    engine compartment. As with the Columbia, the exact location of the
    leak is not known but engineers strongly suspect that the two are
    indeed related. As a result THE SHUTTLE FLEET HAS BEEN GROUNDED until
    further notice. The Atlantis will be rolled back to the VAB and the
    problem will be studied.
    
    				Drew
    
633.10A bit more19458::FISHERPrune Juice: A Warrior's Drink!Fri Jun 29 1990 18:2111
I got this today from a mailing list.  No attribution, but it sounds like a
news article.

NASA announced today that it found another fuel leak, this one on the 
space shuttle Atlantis.  They said that leaks of this nature, on both
Atlantis and Columbia, could have resulted in a Challenger-like accident.
The result is that, pending investigation, all of the shuttles are grounded,
and all missions are scrapped until an investigation is completed.  NASA says
it has to assume this is a design flaw, since it occured on two different
orbiters.

633.11Shuttle Status for 06/29/904347::GRIFFINDave GriffinFri Jun 29 1990 21:2528
From: [email protected] (Peter E. Yee)
Newsgroups: sci.space.shuttle
Date: 29 Jun 90 22:00:20 GMT
Organization: NASA Ames Research Center, Moffett Field, CA

                  KSC SHUTTLE STATUS - FRIDAY JUNE 29, 1990  4 p.m.

                    STS-38 - ATLANTIS (OV 104) - LAUNCH PAD 39-A

               A  special  tanking  test  today  verified  a  leak  in  the
          orbiter-to-external  tank 17-inch umbilical area.  Leak detectors
          exterior  to  the  umbilical  indicated  high  concentrations  of
          hydrogen  during  the  loading activity.  Several tests were per-
          formed this morning to try and isolate the leak.  Data  from  the
          tests are being reviewed.

               The  external  tank  has been drained of the liquid hydrogen
          used in the test.  Boil off of the residual hydrogen is estimated
          to be completed by tomorrow morning.  The Rotating Service Struc-
          ture  will  be moved back in place around the vehicle tomorrow so
          that access to the aft compartment can be obtained.  Thorough in-
          spections will be performed in the orbiter's aft compartment.  No
          tests will be performed this weekend and no new data is expected.

               The STS-38 Flight Readiness Review was cancelled today after
          the leak occurred this morning. Officials will continue to assess
          the  data  obtained  from today's tests and determine any further
          troubleshooting.
633.127672::COOKTo the sea! Too cold! To the bar!!Mon Jul 02 1990 10:525
    
    This is getting really pathetic. NASA needs a good kick in the head to
    get their act straight. There's no excuse for such shoddy workmanship.
    
    /prc
633.13judge not....2319::SAUTERJohn SauterMon Jul 02 1990 13:526
    re: .12
    
    You should not be so quick to criticize.  Let's wait until we know more
    about the nature of the problem.  Remember that this problem didn't
    show up on any earlier flight.
        John Sauter
633.14Who's workmanship? 2169::KOZIKOWSKIHubble: The Window on the UniverseMon Jul 02 1990 13:572
In addition, Who's workmanship should come into question?  NASA contracts
out for almost everything...
633.15Intermittent Design Flaw?58278::LEEWook... Like 'Book' with a 'W'Mon Jul 02 1990 15:538
If it is a design flaw, then the same problem should show up in the disconnect
assembly swapped out of Endeavour.  If it isn't a design flaw, what could cause
the exact same leak (if it is really the same) in Columbia and Atlantis at the
same time?  It seems like a mishandling problem could be the cause.  Someone did
something that caused the leak. (You mean I wasn't supposed to pry it out with
a screwdriver?)  How do they check for those kinds of errors?

Wook
633.16Why "all of a sudden" ?6056::GAUDETNothing unreal existsMon Jul 02 1990 16:299
Yes Wook, I was thinking the same thing.  Since the "leak" developed, they have
installed a myriad of new sensors, cameras, etc. to check for the presence of
hydrogen in the engine compartment during tanking.  Is it possible that the new
monitoring system is too sensitive?  I'm all for safety, and they certainly
shouldn't fly if there's a danger to the crew or the vehicle, but are they
looking too close?  What about the tanking procedure?  Could it be something at
39A?

...Roger...
633.17no H2 monitoring changes5393::PAULHUSChris @ MLO6B-2/T13 dtn 223-6871Tue Jul 03 1990 13:495
    	During yesterday's news conference, Craig Couvault (sp?) of AW&ST
    specificly asked about increased sensitivity and amount of monitoring.
    Dr. Linior (sp?) answered Craig's overall question and did not indicate
    any recent changes/increases in sensitivity.
    	- Chris, who just got cable TV and wishes he could get NASA Select
633.18Shuttle Status - 7/2/90, 7/3/904347::GRIFFINDave GriffinThu Jul 05 1990 12:2249
From: [email protected] (Peter E. Yee)
Newsgroups: sci.space.shuttle
Date: 2 Jul 90 18:07:48 GMT
Organization: NASA Ames Research Center, Moffett Field, CA

                  KSC SHUTTLE STATUS - MONDAY JULY 2, 1990  10 a.m.

                    STS-38 - ATLANTIS (OV 104) - LAUNCH PAD 39-A

               Today, a pressurization test of the external tank is planned
          to gather additional data about leakage at the 17-inch disconnect
          area. The tank will be pressurized to flight level, or  30 pounds
          per square inch, with helium while leakage at the 17-inch discon-
          nect is  monitored.  In  addition,  the  tank  pressure  will  be
          decreased by increments of 5 psi to collect baseline leakage con-
          ditions at ambient temperatures.

               A  special  tanking  test last Friday verified a leak in the
          orbiter-to-external tank 17-inch umbilical area.  Leak  detectors
          exterior  to  the  umbilical  indicated  high  concentrations  of
          hydrogen during the loading activity.  Data from  the  tests  are
          being reviewed.

               This  weekend,  workers moved the Rotating Service Structure
          in place around the vehicle and  established  access  to  various
          parts  of the orbiter.   Thorough inspections of the aft compart-
          ment have been performed and the special instrumentation  devices
          were  calibrated.  Nothing  unusual  was noted from those inspec-
          tions. No leakage was detected in the aft compartment during last
          Friday's test.  The configuration of the vehicle  will  be  main-
          tained  until  further  direction from the team investigating the
          leak.


                 KSC SHUTTLE STATUS - TUESDAY JULY 3, 1990  10 a.m.

                    STS-38 - ATLANTIS (OV 104) - LAUNCH PAD 39-A

               Yesterday,  a  pressurization  test  of  the  external  tank
          revealed  no  leaks at the 17-inch disconnect area.  The tank was
          pressurized to flight level with helium while engineers monitored
          for leakage at the 17-inch disconnect.  As part of the test,  the
          tank  pressure  was  decreased  incrementally to collect baseline
          leakage conditions at ambient temperatures.

               Today,  engineers will review data and get  signatures  from
          the  two  leak  detectors and sensors located on various parts of
          Atlantis. The configuration of the vehicle will be maintained un-
          til further direction from the team investigating the leak.
633.19Let them get back to work2853::BUEHLERSeat of the pants programmingThu Jul 05 1990 14:0514
  It really is kinda strange for anyone to assume a design flaw.  Sounds like
media nonsense to me.  It could just as easily be a process failure.  If the
manufacturing process is flawed, then it will show up in much the same way that
a design flaw would appear.  Only a real examination of the problem will point
out which is correct (design or manufacturing process).

  RE: Criticisms of NASA

  They're pretty much pointless unless they have some constructive purpose.
Consider the fact that they did, in fact, pick up on this problem, and that this
is one of the few (if not the only) groundings of the shuttle fleet apart from
the SRB problems so devastatingly encountered by Challenger.

John
633.20Shuttle Status for 07/05/904347::GRIFFINDave GriffinThu Jul 05 1990 19:1920
From: [email protected] (Peter E. Yee)
Newsgroups: sci.space.shuttle
Organization: NASA Ames Research Center, Moffett Field, CA

                 KSC SHUTTLE STATUS - THURSDAY JULY 5, 1990  11 a.m.

                    STS-38 - ATLANTIS (OV 104) - LAUNCH PAD 39-A


               Today,  a liquid leak check of auxiliary power units 1 and 2
          are planned to verify there are no internal seal leaks. Engineers
          are putting requirements together for another tanking test at the
          pad  as troubleshooting of the hydrogen leak continues.  The test
          will likely occur mid-next week. Meanwhile,  tests are planned to
          obtain  additional signatures from the two leak detectors mounted
          exterior of the orbiter-to-external  tank  disconnect.  The  con-
          figuration of the vehicle will be maintained until further direc-
          tion from the team investigating the leak.

 
633.21Shuttle Status for 07/06/904347::GRIFFINDave GriffinFri Jul 06 1990 19:1019
From: [email protected] (Peter E. Yee)
Newsgroups: sci.space.shuttle
Date: 6 Jul 90 16:26:16 GMT
Organization: NASA Ames Research Center, Moffett Field, CA

                  KSC SHUTTLE STATUS - FRIDAY JULY 6, 1990  11 a.m.

                    STS-38 - ATLANTIS (OV 104) - LAUNCH PAD 39-A


               Yesterday, liquid leak checks of auxiliary power units 1 and
          2 were performed and the test verified  there  were  no  internal
          seal leaks. Engineers are continuing to identify requirements for
          another  tanking  test  at  the  pad  as  troubleshooting  of the
          hydrogen leak continues.  The test will likely be  conducted  the
          end of next week. More instrumentation around the 17-inch discon-
          nect  will be installed for this next test.  The configuration of
          the vehicle will be maintained until further direction  from  the
          team investigating the leak.
633.22Shuttle Status Reports (7/9 -> 7/12)4347::GRIFFINDave GriffinMon Jul 16 1990 19:0139
From: [email protected] (Peter E. Yee)
Newsgroups: sci.space.shuttle
Organization: NASA Ames Research Center, Moffett Field, CA

                 KSC SHUTTLE STATUS - TUESDAY JULY 10, 1990  10 a.m.

                    STS-38 - ATLANTIS (OV 104) - LAUNCH PAD 39-A

               Technicians are continuing to set up special instrumentation
          for the liquid hydrogen tanking test now planned on Friday.  This
          test  will  be another attempt to isolate the source of the leak.
          Today,  special baggies are being installed around the 17  and  4
          inch disconnects in an effort to contain leaks during the test.

               The  call-to-stations  for  the  test is scheduled at 7 a.m.
          Thursday and the Rotating Service Structure will  be  moved  away
          from the vehicle at 11 p.m.  that night.  Chilldown of the liquid
          hydrogen lines is set for 7 a.m.  Friday with slow fill occurring
          shortly afterwards.


                KSC SHUTTLE STATUS - THURSDAY JULY 12, 1990  11 a.m.

                    STS-38 - ATLANTIS (OV 104) - LAUNCH PAD 39-A

               The call-to-stations for the liquid  hydrogen  tanking  test
          occurred  this  morning  at 7 a.m.  Today,  work will be centered
          around preparing the vehicle and pad systems to  support  loading
          liquid hydrogen into Atlantis' external tank tomorrow. Chill down
          of the plumbing system is scheduled for 7 a.m. tomorrow with slow
          fill of liquid hydrogen following 10 minutes later.

               Technicians are continuing to set up special instrumentation
          for the test.  The aft compartment was closed out for the test at
          about 3 a.m. this morning.

               At  about  11 p.m.  tonight,  the Rotating Service Structure
          will be moved away from the vehicle and weather protection panels
          will be retracted.
633.23Shuttle Status Reports (7/16, 7/17)4347::GRIFFINDave GriffinWed Jul 18 1990 15:1845
From: [email protected] (Peter E. Yee)
Newsgroups: sci.space.shuttle

                KSC SHUTTLE STATUS - MONDAY JULY 16, 1990  11:30 a.m.

                    STS-38 - ATLANTIS (OV 104) - LAUNCH PAD 39-A

               A second liquid hydrogen tanking  test  was  conducted  last
          Friday.  A  leak was found at the external tank flange that mates
          to its 17-inch disconnect. Today, photographs of the aft compart-
          ment will be taken and thorough inspections of the  aft  will  be
          made.  The hazardous gas detection system is being calibrated and
          the flow rates of purges in the baggies are being measured.

               Preparations  to  remove  auxiliary power unit number 3 will
          begin today.  Since Atlantis has been at the pad,  the vendor has
          identified a time-life issue of this unit. The other two APUs are
          refurbished units.

               The  Rotating  Service  Structure  was  moved  back in place
          around the vehicle on Saturday.

                 KSC SHUTTLE STATUS - TUESDAY JULY 17, 1990  11 a.m.

                    STS-38 - ATLANTIS (OV 104) - LAUNCH PAD 39-A

               Troubleshooting plans are being identified to  gain  further
          understanding  into the leakage detected during the second liquid
          hydrogen tanking test conducted last  Friday. A leak was found at
          the external tank flange that mates to  its  17-inch  disconnect.
          Managers  want  to  determine  if any leakage between baggies oc-
          curred during the test and if repairs can be  made  at  the  pad.
          Workers at KSC are preparing for another tanking test as early as
          next weekend.

               Yesterday, photographs of the aft compartment were taken and
          thorough inspections were made. Calibrations of the hazardous gas
          detection  system  are continuing and the flow rates of purges in
          the baggies are being measured.

               Preparations to remove auxiliary power  unit  number  3  are
          continuing today.  Since Atlantis has been at the pad, the vendor
          has identified a time-life issue with this unit.  The  other  two
          APUs are refurbished units.

633.24Shuttle Status for 07/18/90, 7/19/904347::GRIFFINDave GriffinFri Jul 20 1990 13:4846
From: [email protected] (Peter E. Yee)
Newsgroups: sci.space.shuttle
Organization: NASA Ames Research Center, Moffett Field, CA

                KSC SHUTTLE STATUS - WEDNESDAY JULY 18, 1990  11 a.m.

                    STS-38 - ATLANTIS (OV 104) - LAUNCH PAD 39-A

               Today,  helium will be injected into the baggies around  the
          flange  and 17-inch disconnect area in an effort to gain a better
          understanding about the leakage that occurred during the  tanking
          test last Friday.  Later today,  the baggies and sense lines will
          be removed and dye will be injected  into  the  foam  around  the
          flange.  The foam will be cut to determine if the dye reveals any
          leak paths through the foam.  Managers want to determine if   any
          leakage between baggies occurred during the test.

               The  bags  will  be  reinstalled  and the tank will be pres-
          surized early tomorrow morning to check for leaks in the baggies.
          Workers at KSC are preparing for another tanking test  next  Wed-
          nesday, July 25.

               Preparations  to  remove  auxiliary  power unit number 3 are
          continuing today.  The unit is scheduled to be  removed  Thursday
          and Friday.


               KSC SHUTTLE STATUS - THURSDAY JULY 19, 1990  11:30 a.m.

                    STS-38 - ATLANTIS (OV 104) - LAUNCH PAD 39-A

               The external tank is being pressurized this morning to check
          for leakage at the flange and around  each  bolt.  This  evening,
          each of the 48 bolts around the flange will be over torqued by 10
          percent.  Tomorrow, the integrity of the flange welds will be in-
          spected with a dye penetrant test to reveal any imperfections  in
          the welds.  Workers at KSC are preparing for another tanking test
          next Wednesday, July 25.

               Two leak paths in the foam were detected around  the  flange
          yesterday  by  a  dye  injection  test.  These  paths  are  being
          evaluated to determine if any leakage could  have  migrated  into
          the larger baggie.

               Preparations  to  remove  auxiliary  power unit number 3 are
          continuing today. Replacement of the unit is scheduled tomorrow.
633.25Shuttle Status for 07/20/904347::GRIFFINDave GriffinSun Jul 22 1990 19:2038
From: [email protected] (Peter E. Yee)
Newsgroups: sci.space.shuttle
Date: 21 Jul 90 01:24:14 GMT
Organization: NASA Ames Research Center, Moffett Field, CA

                 KSC SHUTTLE STATUS - FRIDAY JULY 20, 1990  10 a.m.


                    STS-38 - ATLANTIS (OV 104) - LAUNCH PAD 39-A

               Today, the 48 bolts around the external tank liquid hydrogen
          flange will be over torqued by 10 percent in an  effort  to  stop
          the  leak  discovered  during last week's tanking test.  The bolt
          torquing activities were not worked last night as planned because
          of measurements taken yesterday.  Measurements taken of the  bolt
          flatness  and  gap distance did not give the expected results and
          mold impressions were made of each bolt.  It has been  determined
          that all bolts are within specifications.

               Yesterday,  no  leakage was detected while the external tank
          was pressurized to check for leaks at the flange and around  each
          bolt.

               Later  today,  the  primer  around  the flange welds will be
          removed and a check of the  integrity  of  the  flange  welds  is
          planned using a dye penetrant test that will reveal imperfections
          in  the  welds.  Workers at KSC are preparing for another tanking
          test next Wednesday, July 25.

               In parallel with the tank operation,  the number 3 auxiliary
          power unit was disconnected this morning. Replacement of the unit
          is underway today.  Tomorrow, the pad will be cleared for about 2
          shifts of all non-essential personnel while the new APU  is  con-
          nected.  On Sunday, work will center on preparing the vehicle for
          Wednesday's  test,  including  installation  of baggies and sense
          lines and foaming various areas.

 
633.26Shuttle Status for 07/25/904347::GRIFFINDave GriffinWed Jul 25 1990 20:2326
From: [email protected] (Peter E. Yee)
Newsgroups: sci.space.shuttle
Date: 25 Jul 90 19:56:28 GMT
Organization: NASA Ames Research Center, Moffett Field, CA

               Wednesday July 25, 1990                      12:30 p.m.

                     KSC Space Shuttle Processing Status Report

          -----------------------------------------------------------------

                  STS-38  --  Atlantis (OV 104)  -  Launch Pad 39-A

               A liquid hydrogen special tanking test was conducted this
          morning on Atlantis at pad 39-A. Chill down of the liquid
          hydrogen lines began at 7:30 followed by slow and fast fills.
          During the fast fill portion of the test, a liquid hydrogen leak
          was detected in the area of the flange joint on the external tank
          side of the 17-inch umbilical lines. This leak then reappeared
          during subsequent slow fill operations. The leak appears to be
          similar to the one previously detected during earlier tests.
          Engineers will be digesting the data gathered during today's test
          and presenting the information to program management.

               Following the test this morning, engineers prepared to
          perform an Auxiliary Power Unit hot fire test on APU number 3.
633.27Shuttle Status for 07/26/904347::GRIFFINDave GriffinMon Jul 30 1990 14:0438
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA

               Thursday July 26, 1990                      10:00 p.m.

                     KSC Space Shuttle Processing Status Report

          -----------------------------------------------------------------

                  STS-38  --  Atlantis (OV 104)  -  Launch Pad 39-A

               Following yesterday's liquid hydrogen tanking test on the
          shuttle Atlantis, shuttle project managers have decided to remove
          Atlantis from the pad and roll it back to the VAB for repairs.
          Results of yesterday's test confirmed the existence of a leak in
          the 17-inch umbilical flange joint on the external tank. Managers
          have said the space shuttle Columbia will fly next on mission
          STS-35.

               Two rollback scenarios are currently being discussed for
          Atlantis. The preferred involves not moving Atlantis until the
          day before Columbia is ready to roll out to pad A, probably near
          the end of the first week in August. The second scenario involves
          the possible effects of tropical storm Arthur, currently working
          its way northwest from the Caribbean. If Arthur is predicted to
          affect weather conditions at KSC, Atlantis may be moved as early
          as the first of next week.

               Boil off of the liquid hydrogen remnants in the external
          tank from yesterday's test was completed at 5:00 a.m. this
          morning. Post tanking test operations are in work and the
          rotating service structure is scheduled to be moved back around
          the orbiter by 11:00 a.m. Access to the orbiter's aft compartment
          is scheduled for 8:00 p.m. tonight.

               Engineers decided yesterday not to perform the APU hot fire
          as scheduled. Preparations are underway today to remove APU
          number three on Saturday.
633.28Shuttle Status for 08/03/904347::GRIFFINDave GriffinMon Aug 06 1990 19:4624
[It looks like vistors to the KSC may get a bit of a treat: a space shuttle
 traffic jam...  dg]

From: [email protected] (Peter E. Yee)
Newsgroups: sci.space.shuttle
Organization: NASA Ames Research Center, Moffett Field, CA

                Friday August 3, 1990                      9:30 a.m.

                     KSC Space Shuttle Processing Status Report

          -----------------------------------------------------------------

                  STS-38  --  Atlantis (OV 104)  -  Launch Pad 39-A

               APU number three was removed from Atlantis last night and it
          has been transported to the OPF for installation into Discovery.
          Yesterday, the payload bay torque tube was installed. Helium
          mapping has been completed to date and helium injection tests are
          scheduled for Saturday. Atlantis is scheduled to be rolled back
          to the VAB at 12:01 a.m. Wednesday, August 8. It will wait
          outside the VAB until Columbia is moved out to pad A the
          following day. Atlantis will then be moved into the VAB,
          destacked, and returned to the OPF.
633.29Shuttle Status for 08/09/904347::GRIFFINDave GriffinFri Aug 10 1990 10:4223
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA

              Thursday August 9, 1990                   10:00 a.m. EDT



                     KSC SPACE SHUTTLE PROCESSING STATUS REPORT

          -----------------------------------------------------------------

              STS-38  --  Atlantis (OV 104)  -  Outside VAB high bay 3


               Atlantis was rolled off pad A last night with first motion
          occurring at 10:14 p.m. It arrived at the VAB this morning
          shortly after 4:00 a.m. and will remain outside high bay 1 until
          Columbia is hard down on the pad. This afternoon between 2:00 and
          3:00, Atlantis will be moved into high bay 3 of the VAB for
          destack operations. Demate of the orbiter from the ET/SRB stack
          will occur this weekend and transfer to the OPF is targeted for
          Monday morning. The external tank flange joint is scheduled to be
          removed and shipped to the vendor for analysis on Friday.
633.30Shuttle Status for 08/13/904347::GRIFFINDave GriffinMon Aug 13 1990 20:0522
From: [email protected] (Peter E. Yee)
Subject: Shuttle Status for 08/13/90 (Forwarded)
Organization: NASA Ames Research Center, Moffett Field, CA

            KSC SHUTTLE STATUS REPORT - MONDAY, AUGUST 13, 1990  11 A.M.

                      STS-38 - ATLANTIS (OV 104) - VAB HIGH BAY 3

               Operations to demate the shuttle Atlantis from the  external
          tank  began this weekend but were temporarily halted this morning
          when a valve in the VAB firex system failed causing water to drip
          onto power transformers.  The power in VAB high bay  3  has  been
          cut  off  to avoid electrical shorts.  The water has been cleaned
          up. Officials are determining if that part of the firex system is
          necessary to continue with demate operations.  There was no water
          on flight hardware.

               Atlantis will be towed to the OPF after demate where work to
          ready it for the STS-38 mission will commence including replacing
          seals  in  the  17-inch  disconnect  assembly  and for repairs to
          tiles.

633.31Shuttle Status for 08/15/904347::GRIFFINDave GriffinThu Aug 16 1990 14:2913
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA

           KSC SHUTTLE STATUS REPORT - WEDNESDAY, AUGUST 15 1990  11 A.M.

                        STS-38 - ATLANTIS (OV 104) - VAB HIGH BAY 3

               Atlantis was demated from the external tank last  night  and
          rolled  into the OPF at about 3:10 a.m.  Access to the vehicle is
          being established.   Work to ready it for the STS-38 mission will
          commence  including replacing seals in the 17-inch disconnect as-
          sembly and for repairs to tiles.

633.32Shuttle Status for 09/26/904347::GRIFFINDave GriffinWed Sep 26 1990 18:5618
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA

          KSC SHUTTLE STATUS REPORT - WEDNESDAY, SEPT. 26, 1990 11:30 AM

                       STS-38 - ATLANTIS (OV 104) - OPF BAY 2


               The  auxiliary  power  unit  was installed yesterday.  Tech-
          nicians are adjusting the amount of freon in cooling loop 2.  In-
          spections  of the radiator are continuing.  Seals for the 17 inch
          disconnect  assembly  are  scheduled  to  be  installed   Friday.
          Closeouts  are underway on all areas of the vehicle.  Atlantis is
          being prepared for rollover to the VAB at midnight Tuesday,  Oct.
          2.

               Closeouts of the  external tank are continuing in the VAB in
          preparation for orbiter mating operations scheduled next week.
633.33Shuttle Status for 09/28/90 4347::GRIFFINDave GriffinTue Oct 02 1990 09:5820
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


          KSC SHUTTLE STATUS REPORT - FRIDAY, SEPT. 28, 1990 11:30 AM

 
                       STS-38 - ATLANTIS (OV 104) - OPF BAY 2

               Checks  of  the  auxiliary power unit controller are planned
          today. Seals for the 17 inch disconnect assembly are scheduled to
          be installed today.   Closeouts are underway on all areas of  the
          vehicle.  Cleaning operations of the payload bay are scheduled to
          begin tonight.  The payload bay doors are scheduled to be  closed
          tomorrow  night.  Atlantis  is being prepared for rollover to the
          VAB at midnight Tuesday, Oct. 2.  Closeouts of the  external tank
          are  continuing  in  the  VAB  in  preparation for orbiter mating
          operations scheduled next week.


633.34Shuttle Status for 10/03/90 4347::GRIFFINDave GriffinThu Oct 04 1990 11:1522
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


          KSC SHUTTLE STATUS REPORT - WEDNESDAY, OCT. 3, 1990  11 AM


 
                          STS-38 - ATLANTIS (OV 104) - VAB

               Atlantis was towed to the Vehicle Assembly Building  shortly
          before midnight last night.  The orbiter is being lifted over the
          transom this morning and will be carefully lowered into  position
          next  to  the  external tank.  The vehicle is expected to be hard
          mated by tomorrow morning. While in the VAB, the vehicle elements
          will be mechanically and electrically  connected.  Those  connec-
          tions will then be tested.

               Rollout to Launch Pad 39-A is scheduled for Tuesday, Oct. 9,
          with first motion at 4 a.m. EDT.


633.35Equipment Accident may have damaged Atlantis8713::J_BUTLERUSAR...and ready...Thu Oct 04 1990 16:279
    I heard a report on ABC news that a 70-pound retaining bar was
    left unsecured in Atlantis. When Atlantis was moved to the vertical
    position, 3 thumps were heard in the aft section. An investigation
    is underway to determine the extent of damage and the effect any
    damage might have on the launch schedule.
    
    This has not been the best of years for NASA...
    
    John B. 
633.36Shuttle Status for 10/04/90 4347::GRIFFINDave GriffinThu Oct 04 1990 19:1128
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


          KSC SHUTTLE STATUS REPORT - THURSDAY, OCT. 4, 1990  12 noon

 
                          STS-38 - ATLANTIS (OV 104) - VAB


               A 9-foot-long I-beam was found in Atlantis's aft compartment
          this morning. The support beam is part of the horizontal platform
          kit  used  for  access  in  the aft compartment.  The beam is not
          flight hardware and should have been removed prior  to  the  rol-
          lover to the VAB. The incident is under investigation.

               While  Atlantis  was  being  hoisted to the vertical positon
          yesterday several  employees  involved  in  the  operation  heard
          several sounds which appeared to be coming from the orbiter.  Of-
          ficials were concerned and decided to proceed   with  the  mating
          operation without detaching the sling upon its conclusion.

               Atlantis was hardmated at about 6 a.m.  this morning and the
          aft was opened about a half hour later for inspections.  The rest
          of  the  mating  operation  is on hold until an assessment of the
          situation can be made.


633.37Shuttle Status for 10/05/90 4347::GRIFFINDave GriffinTue Oct 09 1990 14:0527
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


          KSC SHUTTLE STATUS REPORT - FRIDAY, OCT. 5, 1990  10 A.M.

 
                          STS-38 - ATLANTIS (OV 104) - VAB

               An investigation is continuing to assess damage cause by a 9
          ft.  long support beam that was  left  in  the  aft  compartment.
          Preliminary  inspections  indicate  that  the damage is minor.  A
          broken purge duct and a small portion of a manifold  relief  line
          in the  main propulsion system  will be replaced. Minor abrasions
          to  the surface coating of a strut and scuff marks on freon lines
          were noted.  Technicians are installing access platforms for fur-
          ther inspections.

               While the inspections are underway, mate operations are con-
          tinuing.  Overnight, the tail service masts were connected to At-
          lantis.  Today,  electrical connections between the vehicle  ele-
          ments are planned.

               Atlantis is scheduled to be powered up Sunday for testing of
          connections and rolled to Launch Pad 39-A on Tuesday.


633.38Shuttle Status for 10/10/90 4347::GRIFFINDave GriffinThu Oct 11 1990 10:1526
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


          KSC SHUTTLE STATUS REPORT - WEDNESDAY, OCT. 10, 1990  10:30 A.M.


 
                          STS-38 - ATLANTIS (OV 104) - VAB

               The  Shuttle  Interface  test  has  been  completed.  Today,
          workers  will  power  down  the vehicle and begin closing out all
          areas for the move to the launch pad. Tomorrow, platforms will be
          retracted away from the vehicle and the crawler transporter  will
          be positioned under the launch platform.

               Weather   permitting,   the   STS-38  vehicle  is  currently
          scheduled to be rolled to Launch Pad 39-A sometime tomorrow  eve-
          ning. First motion could come as early as 8 p.m. tomorrow.

               While  at the launch pad,  a liquid hydrogen tanking test is
          planned to verify there are no leaks. Atlantis is scheduled to be
          launched in early November on Mission  STS-38,  a  Department  of
          Defense flight.


633.39Shuttle Status for 10/11/90 4347::GRIFFINDave GriffinSat Oct 13 1990 12:1725
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA
 
 
          KSC SHUTTLE STATUS REPORT - THURSDAY, OCT. 11, 1990  10:30 A.M.
 
 
                          STS-38 - ATLANTIS (OV 104) - VAB
 
               Atlantis was powered down early this morning  and  closeouts
          of  the vehicle are continuing in preparation for roll out to the
          launch pad. Platforms will be retracted away from the vehicle and
          the crawler transporter will be positioned under the launch plat-
          form later today.
 
               Weather  permitting,   the  STS-38  vehicle   is   currently
          scheduled  to  be  rolled  to  Launch Pad 39-A at 12:01 a.m.  EDT
          tomorrow.
 
               While at the launch pad, a tanking test is planned to verify
          there are no leaks in the main  propulsion  system.  Atlantis  is
          scheduled  to be launched in early November on Mission STS-38,  a
          Department of Defense flight.
 
 
633.40Shuttle Status for 10/12/90 4347::GRIFFINDave GriffinSat Oct 13 1990 12:1826
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA
 
 
          KSC SHUTTLE STATUS REPORT - FRIDAY, OCT. 12, 1990  11:30 A.M.
 
 
                          STS-38 - ATLANTIS (OV 104) - VAB
 
               Rollout of Atlantis was postponed early this morning because
          of inclement weather.  The vehicle was closed out and  all  plat-
          forms  were  retracted  away  from  the  vehicle  by about 3 a.m.
          However, at that time,  rainshowers with a potential of lightning
          moved into the area.
 
               Weather   permitting,   the   STS-38  vehicle  is  currently
          scheduled to be rolled to Launch Pad 39-A at 9 p.m. EDT this eve-
          ning.
 
               While at the launch pad, a tanking test is planned to verify
          there are no leaks in the main  propulsion  system.  Atlantis  is
          scheduled  to be launched in early November on Mission STS-38,  a
          Department of Defense flight.
 
 
 
633.41Shuttle Status for 10/23/90 4347::GRIFFINDave GriffinThu Oct 25 1990 10:0031
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


          KSC SHUTTLE STATUS REPORT - TUESDAY, OCT. 23, 1990  11:30 A.M.

 
                        STS-38 - ATLANTIS (OV 104) - PAD 39-A

               The call-to-stations for the tanking test came on time at  7
          a.m.  this morning.  The Rotating Service Structure will be moved
          away from the vehicle at about 10 p.m. tonight.

               The vehicle will be in a normal launch countdown  configura-
          tion  for  tomorrow's test and the hazardous gas detection system
          will be active.  Chilldown of the  system  used  in  loading  the
          propellants  is scheduled for 7 a.m.  tomorrow.  During the test,
          liquid hydrogen will be loaded aboard the external  tank.  Liquid
          oxygen  will  be  loaded  into the main propulsion system but not
          into the tank to make sure there are no problems with  that  sys-
          tem.    After the test,  the propellants will be drained from the
          orbiter and tank.

               Yesterday,  purges of the external tank were completed    to
          ready it for the tanking test.

               Atlantis  is  scheduled  to be launched in early November on
          Mission STS-38, a classified Department of Defense flight.


 
633.42Leak is fixed!19458::FISHERI like my species the way it is" "A narrow view...Thu Oct 25 1990 14:214
News this morning said that the tanking test was successful, i.e. no more than
normal leakage.

Burns
633.43Shuttle Status for 10/24/90 4347::GRIFFINDave GriffinMon Oct 29 1990 10:1631
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


          KSC SHUTTLE STATUS REPORT - WEDNESDAY, OCT. 24, 1990  10 A.M.

 
                        STS-38 - ATLANTIS (OV 104) - PAD 39-A

               The tanking test has been delayed from 7  a.m.  today  to  1
          p.m.  this  afternoon.  Extra time was needed to evaluate a small
          ding in the liquid hydrogen feedline for engine 1  and  a  broken
          transducer  for  the  engine 3 liquid oxygen feedline.  Officials
          determined late last night  that  these  items  would  not  be  a
          problem for today's test.  The aft compartment was closed out for
          the test at 2 a.m.  this morning and the Rotating Service  Struc-
          ture was moved away from the vehicle at 6 a.m. this morning.

               The  vehicle will be in a normal launch countdown configura-
          tion for the test and the hazardous gas detection system will  be
          active.  Chilldown  of the system used in loading the propellants
          is scheduled for 1 p.m. today.  During the test,  liquid hydrogen
          will  be  loaded aboard the external tank.  Liquid oxygen will be
          loaded into the main propulsion system but not into the  tank  to
          make  sure  there  are  no problems with that system.   After the
          test, the propellants will be drained from the orbiter and tank.

               Atlantis is scheduled to be launched in  early  November  on
          Mission STS-38, a classified Department of Defense flight.

 
633.44Shuttle Status for 10/26/90 4347::GRIFFINDave GriffinMon Oct 29 1990 10:1838
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


               Friday October 26, 1990                 11:00 a.m. EDT

                     KSC SPACE SHUTTLE PROCESSING STATUS REPORT

          -----------------------------------------------------------------

 
                      STS-38 -- Atlantis (OV-104)  -  Pad 39-A

               Operations were briefly halted at the pad this morning as
          SCAPE operations were instituted to repair minor leaks at the
          hypergolic oxidizer and fuel farms. The pad was re-opened for
          operations at 10:30 a.m. The leaks were thought to be as a result
          of cooler weather experienced overnight. No impact in the
          schedule is expected.

               Purge operations of the external tank have been completed
          following the successful tanking test Wednesday. Access was
          gained to the aft compartment and work continues to ready the
          vehicle for flight. At the pad today, fuel cell voltage
          adjustments will be made.

               This weekend, the mass memory unit on the orbiter will be
          changed out and the Shuttle main engine flight readiness test
          will be conducted. Monday, liquid oxygen tankers will arrive at
          the pad to replenish the on-site storage tanks.

               The Flight Readiness Review is scheduled for next Monday and
          Tuesday, following which an announcement is expected setting the
          launch date and launch period for Atlantis' Department of Defense
          mission.


 
633.45STS-38 launch set, STS-35 tanking briefing scheduled4347::GRIFFINDave GriffinWed Oct 31 1990 10:2944
From: [email protected] (Peter E. Yee)
Date: 30 Oct 90 23:36:45 GMT
Organization: NASA Ames Research Center, Moffett Field, CA

Jim Cast
Headquarters, Washington, D.C.                   October 30, 1990
(Phone:  202/453-8536)

Dick Young
Kennedy Space Center, Fla.
(Phone:  407/867-2468)


N90-86:  STS-38 LAUNCH SET, STS-35 TANKING BRIEFING SCHEDULED


     NASA and DoD managers today established Nov. 9th as the 
target date for the launch of STS-38 Space Shuttle Atlantis.  The 
4-hour launch period for this classified DoD flight begins at 
6:30 p.m. EST.

     Additionally, a press briefing will be held today following 
completion of the STS-35 Columbia tanking test at Kennedy Space 
Center, Fla.  The briefing, time to be determined, will be 
carried live on NASA Select television with 2-way question and 
answer capability.

     The decision to launch Atlantis on the 9th was made 
following the STS-38 Flight Readiness Review at NASA's Kennedy 
Space Center.  On October 24, Atlantis successfully passed a 
special tanking test designed to assure the absence of 
significant liquid propellant leaks, both hydrogen and oxygen.  
No major obstacles have surfaced since that time which would 
preclude launch on the targeted date.

     The five-man crew for this 37th Space Shuttle mission is 
commanded by 41-year-old Richard O. Covey, an Air Force 
Colonel.  Sitting in the right seat will be Pilot Frank L. 
Culbertson, Jr., 41, a Navy Commander.  Three STS-38 Mission 
Specialists will be flying aboard Atlantis:  Air Force Lt. 
Colonel Carl J. Meade, 39; Marine Corps Colonel Robert C. 
Springer,48; and 35-year-old Army Captain Charles D. (Sam) 
Gemar.  Both Covey (twice) and Springer (once) have flown in 
space before aboard the Shuttle.
633.4625474::MAIEWSKIWed Oct 31 1990 18:369
  They keep saying that this mission is to launch a spy satillite that
will be used to watch the Persian Gulf but as I understand it, this
payload was originaly suppose to be launched in June and I believe that
the invasion of Kuwait was in July.

  What do you bet it's the long awaited KH-12 which spys on everything
including, but not limited to, the Persian Gulf.

  George
633.47Another (non-NASA) delay30086::REITHJim Reith DTN 226-6102 - LTN2-1/F02Thu Nov 01 1990 08:024
    I heard last night that there were unspecified problems in the "cargo
    checkout" and that the mission would be delayed. At least it's a
    "cargo" problem this time. Could they move Columbia in front of it now 
    that it passed the tanking test also?
633.48a 28 deg KH-12??? CSS::BIROThu Nov 01 1990 08:4612
    re:46

    A KH-12 in a 28 deg orbit, what a waste, so I don't think so.
    
    I have not heard an updates on the DoD launch, but with
    a 28 deg launch maybe it is a Rhyolite, and most likely
    the Shuttle Radar image of the gulf.
    
    The only other possibility is a geo orbit.
    john

    
633.49No KH-12, but there's lots more58205::ALLEGREZZAGeorge Allegrezza @VROThu Nov 01 1990 09:2911
    Well, there is no KH-12.  It was canceled a couple of years ago.
    
    There is the Indigo Lacrosse radar imaging sat, the new class of
    infrared satellite, and the new generation visible wavelength imaging
    sat, which is smaller and less capable than KH-12 (call it KH-13 if you
    like).  There are also at last two classes of high-orbit (not
    necessarily geosync) satellites which may have both singals
    intelligence and imaging capabilities.  
    
    Sources: Av. Week, "Deep Black" by William Burrows, follow-on article
    by Burrows in Popular Science.
633.50Probably 57 degrees15372::LEPAGELife sucks then the bill comes inThu Nov 01 1990 10:0112
    Re:.48
    
    John,
    	Where did .46 say anything about the DoD payload going into a 28
    degree orbit? If the payload is indeed a KH-12 or similar satellite, it
    is likely that it will be launched into a highest inclination orbit
    possible with a launch from Cape Canaveral (i.e. about 57 degrees).
    That would give coverage of about 85% of the planet's surface including
    the Middle East.
    
    				Drew
    
633.51from a good sourceCSS::BIROThu Nov 01 1990 10:343
    the launch will be 28 deg...
    jb
    
633.52Maybe it isn't a photo recon satellite?15372::LEPAGELife sucks then the bill comes inThu Nov 01 1990 11:4513
    Re:.51
    
    	If it is launched into an orbit that has an inclination of only 28
    degrees than I would have to question whether it is a photo recon
    satellite. At that inclination it would be just able to see Kuwait and
    would be far to south to be able to see most of Iraq including Baghdad
    except at extreme look angles (if even then). It would be in a fairly
    good position to serve as an elnit dedicated to observing that region.
    Or it may be destined to be some sort of satellite destined for
    geosynchronous orbit.
    
    				Drew
    
633.53PAXVAX::MAIEWSKIThu Nov 01 1990 16:226
  Still, the question is, why are they describing it as a satillite who's job
is to spy on the Persian Gulf? Did the mission or payload change after the July
invasion or did they know the invasion was comming a year or more ago when the
payload was 1st scheduled for launch? 

  George
633.54Seems wrong but time will tell30086::REITHJim Reith DTN 226-6102 - LTN2-1/F02Thu Nov 01 1990 16:407
    Could be a flexible enough IntelSat that they can now use to figure out
    the situation in the Gulf closer. The 28 degree inclination seems wrong
    from that but we'll know more as it gets launched. I thought the quick
    response/ short notice support sats used expendables to avoid these long 
    lead times anyway. Maybe its all propoganda to give Saddam some short
    term pressure and doesn't involve the situation there in any significant 
    way?
633.55Atlantis mission on hold4347::GRIFFINDave GriffinFri Nov 02 1990 09:1274
From: [email protected] (WILLIAM HARWOOD, UPI Science Writer)
Date: 1 Nov 90 22:18:49 GMT

	CAPE CANAVERAL, Fla. (UPI) -- Problems with a military satellite
aboard the shuttle Atlantis do not appear as serious as first believed
and the ship may be ready for launch by Nov. 15, only six days or so
behind schedule, sources said Thursday.
	Atlantis and its five-man all-military crew were formally cleared
Tuesday for blastoff Nov. 9 to carry a top-secret Pentagon spy satellite
into orbit. But the Air Force announced an indefinite delay Wednesday,
citing problems with the classified payload.
	Sources initially said the flight faced a delay of at least a week to
10 days and possibly more than two weeks. Officials who asked not to be
named said Thursday, however, the problem did not appear to be as
serious as they first believed and that Atlantis may be ready for flight
as early as Nov. 15.
	In the meantime, engineers are pressing on with preparations to
launch both Atlantis and the recently repaired shuttle Columbia as soon
as possible. Shuttle program director Robert Crippen said in a statement
Thursday that Atlantis -- mission STS-38 -- still has priority over
Columbia.
	``At this time, we are continuing to proceed with the schedule to fly
STS-38 before (Columbia),'' he said. ``I am optimistic about flying
(Columbia) sometime in December.''
	Before Atlantis was delayed, Columbia was on track for takeoff around
Dec. 1 to kick off a 10-day astronomy mission that has been grounded
since May by a series of elusive hydrogen fuel leaks. The repaired
shuttle finally passed a fueling test Tuesday without any problems,
clearing the way for launch.
	Sources who requested anonymity said NASA managers are discussing the
possibility of waiving a rule requiring three weeks between shuttle
missions so data from one flight can be analyzed before launching the
next.
	Waiving the rule would raise the possibility of two shuttle launches
in less than three weeks, but Crippen said Columbia would not be
launched on mission STS-35 until data from Atlantis's flight can be
studied.
	``A specific target launch date for (Columbia) will not be determined
until after the flight readiness review has been conducted and
performance data from the STS-38 mission has been analyzed,'' he said.
	NASA managers currently are in the final stages of developing a 1991
launch schedule and while the flight sequence appears to be solid, the
dates may yet change. Here is a preliminary schedule of major 1991
events:
	--March 7: Shuttle Discovery; Payload: Four unclassified Air Force
experiments.
	--April 11: Shuttle Atlantis; Payload: Gamma Ray Observatory.
	--May 7: The new shuttle Endeavour is delivered to the Kennedy Space
Center.
	--May 16: Shuttle Columbia; Payload: Spacelab science module.
	--July 11: Shuttle Discovery; Payload: A NASA Tracking and Data Relay
comunications satellite.
	--Aug. 4: Columbia is ferried to a Rockwell International facility in
Palmdale, Calif., for five months of major modifications.
	--Aug. 15: Shuttle Atlantis; Payload: An Air Force Defense Support
Program early warning satellite.
	--Nov. 14: Shuttle Discovery; Payload: An atmospheric research
satellite.
	--Dec. 12: Shuttle Atlantis; Payload: A materials processing Spacelab
mission.
	A final manifest is expected to be announced after new launch dates
are set for the upcoming flights of Atlantis and Columbia.
	In a two-sentence statement released Wednesday, the Air Force said
Atlantis's flight would be delayed ``to resolve anomalies discovered
during cargo testing. Details are classified and it's too early to
predict a new launch date.''
	Because the payload and all other details about the 37th shuttle
mission are classified, it was not immediately possible to determine the
nature of the problem or whether it involved the satellite or on-board
support equipment.
	Atlantis originally was scheduled for launch in mid July, but the
flight was grounded after a hydrogen leak showed up during a June 29
fueling test. The problem was fixed and NASA managers Tuesday formally
cleared the ship for takeoff Nov. 9.
633.56It's all propaganda15372::LEPAGELife sucks then the bill comes inFri Nov 02 1990 11:2112
    Re:.53
    
    	The reason the DoD is now connecting the launch of this satellite
    with the current Gulf crisis can be summed up in one word: Propaganda.
    They want to show the American public, our allies, and Saddam that we
    are using all of our military assests to watch Iraq's every move. To a
    lesser extent the DoD could also be showing the taxpayers that the
    highly secretive, multi-billion dollar recon satellite program has
    value even in the post Cold War era.
    
    				Drew
    
633.5719548::YANKESFri Nov 02 1990 16:2510
	What is the latitude of KSC?  If it is around 28 degrees north, then
NASA is trying to launch the shuttle along the path that is the most equitorial
for the shuttle.  (ie. launching it "due east" puts the northern-most position
of the orbit over KSC's latitude.)  In that case, I'd bet the satellite is
going to be put into an equitorial -- and possibly geosynchronous -- orbit.
My guess would be it isn't a signal-gathering or photo-recon satellite, but
rather a missile launch detection satellite.

								-craig
633.58KCS Location on Earth2631::DAHLTom Dahl, CDMSFri Nov 02 1990 16:437
RE:                      <<< Note 633.57 by 19548::YANKES >>>

>	What is the latitude of KSC?

I can't resist.  The location of Launch Complex 39A (the southern-most of the
two LC39 pads) is 28� 36' 29.66" North, 80� 36' 10.81" West.
						-- Tom
633.5919548::YANKESFri Nov 02 1990 19:536
    
    	Re: .58
    
    	Too bad I'm not always this good at guessing at numbers... :-)
    
    								-craig
633.60Shuttle Status for 11/05/90 4347::GRIFFINDave GriffinTue Nov 06 1990 18:2827
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


          KSC SHUTTLE STATUS REPORT - MONDAY, NOV. 5, 1990  11 A.M.


 
                        STS-38 - ATLANTIS (OV 104) - PAD 39-A

               Work to ready the vehicle for the STS-38 launch is  proceed-
          ing.  Closeouts of the aft compartment are in work. Dye penetrant
          tests of the main engine high pressure fuel ducts  were  success-
          ful.  A  functional check of the crew hatch was successfully com-
          pleted this weekend.

               The two space suits are scheduled to be installed in the air
          lock tomorrow. Two suits are routinely flown on board the orbiter
          in case of an unplanned space walk during the mission.  Purges of
          the external tank are planned tomorrow.

               Atlantis  is  scheduled to be launched on Mission STS-38,  a
          classified Department of Defense flight. Last week, Air Force of-
          ficials identified a problem with the payload which  delayed  the
          launch. A new launch date has not yet been set.

 
633.61Shuttle Status for 11/06/90 4347::GRIFFINDave GriffinTue Nov 06 1990 18:3025
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


          KSC SHUTTLE STATUS REPORT - TUESDAY, NOV. 6, 1990  10 A.M.


 
                        STS-38 - ATLANTIS (OV 104) - PAD 39-A

               Work to ready the vehicle for the STS-38 launch is  proceed-
          ing.  Closeouts  of the aft compartment are in work.   Yesterday,
          the flash evaporator system was topped off.

               The two space suits are scheduled to be installed in the air
          lock tomorrow. Two suits are routinely flown on board the orbiter
          in case of an unplanned space walk during the mission.  Purges of
          the external tank also are planned tomorrow.

               Atlantis  is  scheduled to be launched on Mission STS-38,  a
          classified Department of Defense flight. Last week, Air Force of-
          ficials identified a problem with the payload which  delayed  the
          launch. A new launch date has not yet been set.

 
633.62Shuttle Status for 11/09/90 4347::GRIFFINDave GriffinSat Nov 10 1990 12:5429
From: [email protected] (Peter E. Yee)
Organization: NASA Ames Research Center, Moffett Field, CA


          KSC SHUTTLE STATUS REPORT - FRIDAY, NOV. 9, 1990  10 A.M.


 
                        STS-38 - ATLANTIS (OV 104) - PAD 39-A

               Work to ready the vehicle for the STS-38 launch is  proceed-
          ing.  Closeouts  of  the  aft  compartment are continuing and are
          scheduled to be complete Sunday evening.

               Purges of the fuel cells were completed yesterday.  Ordnance
          activities are scheduled to begin early tomorrow morning. The pad
          will be closed tomorrow to all non-essential personnel.  Tomorrow
          evening,  Atlantis' hypergolic propellant  tanks  will  be  pres-
          surized for flight.

               Launch  of  Atlantis  and  Mission  STS-38  on  a classified
          Department of Defense flight remains set for Nov. 15.  The launch
          countdown is set to begin at 10:30 p.m.  EST Sunday, Nov. 11. The
          four-hour launch period begins at 6:30 p.m.  EST  Thursday,  Nov.
          15.  The  crew  is scheduled to arrive at KSC at 5 p.m.  Tuesday,
          Nov. 13.


 
633.63Shuttle Atlantis, crew, ready for launch4347::GRIFFINDave GriffinWed Nov 14 1990 17:4859
From: [email protected] (WILLIAM HARWOOD, UPI Science Writer)
Date: 14 Nov 90 14:40:25 GMT

	CAPE CANAVERAL, Fla. (UPI) -- The shuttle Atlantis's countdown to
launch Thursday night on a secret military flight ticked into its final
stages Wednesday with a revised forecast calling for a 60 percent chance
of acceptable weather.
	Engineers planned to move a giant rotating gantry away from the $2
billion shuttle at 1 p.m. Wednesday, exposing the ship to view and
setting the stage for fuel loading Thursday morning.
	With work at the launch pad on or ahead of schedule, Atlantis's five-
man all-military crew flew to the Kennedy Space Center from Houston
Tuesday to prepare for blastoff.
	The only question mark was the weather. Air Force meteorologists
Tuesday predicted a 70 percent chance of high crosswinds and offshore
rain that would prevent an on-time liftoff. But the outlook improved
dramatically overnight and the revised forecast called for a 60 percent
chance of acceptable weather Thursday, 70 percent for Friday and
Saturday.
	While Atlantis's launch time will not be revealed until nine minutes
before liftoff, sources who requested anonymity said the shuttle and its
five-man all-military crew are scheduled for takeoff at 6:46 p.m.
Thursday to kick off a four-day mission, the last fully classified
shuttle flight on NASA's books.
	At the controls will be commander Richard Covey, 44, an Air Force
colonel, and Navy Cmdr. Frank Culbertson, 41, the co-pilot. Their
crewmates are Army Maj. Charles Gemar, 35, Air Force Lt. Col. Carl
Meade, 39, and Marine Corps Col. Robert Springer, 48.
	The goal of the mission is classified, but Aviation Week & Space
Technology magazine reported last month that Atlantis's payload is
photo-reconnaissance satellite that may be used to monitor conditions in
the Persian Gulf in support of the Desert Shield operation.
	The duration of the 37th shuttle mission also is classified, but
sources who requested anonymity said the flight is scheduled to last
three days, 23 hours and 55 minutes, resulting in a touchdown at Edwards
Air Force Base, Calif., at 3:41 p.m. PST next Monday.
	Launch originally was scheduled for mid July, but Atlantis was
grounded by an elusive hydrogen fuel leak. At least two such leaks
grounded the shuttle Columbia in May and September, but both spaceplanes
have since been repaired and cleared for flight.
	Atlantis's flight is the last fully classified Air Force shuttle
mission left on NASA's launch manifest, a move that reflects a Pentagon
shift away from the shuttle in favor of unmanned rockets like the Titan
4 that was successfully launched Monday night from the Cape Canaveral
Air Force Station.
	The move also will save some $80 million a year that was being spent
on shuttle security operations.
	While two more military shuttle flights are scheduled in 1991, the
payloads of both have been declassified.
	The shuttle Discovery will carry four payload bay experiment packages
into space in February to learn more about infrared sensor technology
that may prove useful for detecting enemy missile launches or aircraft
in flight.
	An Air Force spokesman said the payload of a military shuttle flight
planned for next summer is an early warning Defense Support Program
satellite equipped with a large infrared telescope capable of detecting
enemy missile launches.
	The Titan 4 launched Monday night was widely reported to have carried
a ``DSP'' satellite into orbit.
633.6458457::SKLEINNulli SecundusThu Nov 15 1990 17:116
I heard that they did complete the fueling, however, the weather has gotten
slightly worse. So don't know if they are going to launch, I hope so, my mom
is down there right now and I want her to see it.

Susan
633.65in orbit2319::SAUTERJohn SauterFri Nov 16 1990 07:524
    They launched shortly before 7 PM Eastern Time last night.  I missed
    the live feed, but got to watch the playbacks.  The last I heard before
    mission control "signed off" they had achieved orbit.
        John Sauter
633.6658453::SKLEINNulli SecundusFri Nov 16 1990 10:4412
Re: -1

Launch was at 6:48 pm EST. The launch was in the dark and lit up the night sky
and could be seen for hundreds of miles. Those night launches are really
impressive. I was watching the evening news with Dan Rather, don't remember his
station, and they should it live. I flipped to the other two networks, but
didn't see anything. They did not show much of the launch for t-10 seconds to
shortly after the roll program. Then they picked it up again with the SRB 
separation.

Susan
633.67first ovsrevationsCSS::BIROFri Nov 16 1990 10:5212
    eye witness of the roll indicated that the inc
    was higher the 28 deg maybe 33 deg or so, that
    makes a lot more sense.
    
    also lift off was 18:48:16est
    thus for those doing their own element sets
    that would give a epoc of 90320.042546
    and a RAAN of about 243.4 
    Mean Motion of about 16.1
    
    john
    
633.6819548::YANKESFri Nov 16 1990 11:4417
	Re: .66

	ABC World News Tonight showed it as a re-run a few minutes before 7pm.
They gave it about 5 or 6 seconds of airtime...  I was really suprised that
they did it this way (I was expecting the live feed at 6:48), but then I
remembered that World News Tonight is taped for later rebroadcast.  (For
example, I was watching the 6:30 showing (live, I presume) on our channel 9
and channel 5 has the exact same show at 7:00.)  They probably didn't want to
run into the potential confusion of having to have two separate WNT's -- one
with the shuttle live and the other as a rerun-but-modified-for-the-shuttle.
This "two-WNT" idea probably isn't even possible to easily arraign -- I bet the
"7:00 stations" pull it off the satellite feed at 6:30.

	But it sure was pretty!  I love nighttime launches.

								-craig
633.69PAXVAX::MAIEWSKIFri Nov 16 1990 13:054
  Can someone translate the orbital stats into layman's terms? How far
north/south of the equator should it go? How high up, etc.

  George
633.7032238::FRIEDRICHSwinded in at ASHFri Nov 16 1990 14:3013
    rathole alert...
    
    re .68 rebroadcast...
    
    Actually, as I understand it from watching some show, the "7:00"
    rebroadcast originates from the news center, not the local stations.
    I believe it was Brokaw that was saying that if he didn't like how a
    piece goes, then he actually does it over live during the rebroadcast,
    and that feed replaces the tape for the broadcast..
    
    FWIW,
    jeff
    
633.71Shuttle Status Report 11/16/904347::GRIFFINDave GriffinSat Nov 17 1990 09:5424
From: NASA Spacelink
Date: 17-Nov-1990


KSC SHUTTLE STATUS REPORT - FRIDAY, NOV. 16, 1990  10 A.M.

 
              STS-38 - ATLANTIS (OV 104) - PAD 39-A

     Launch of  Atlantis  and  Mission  STS-38  on  a  classified
Department  of  Defense flight occurred at 6:48:15.0639 p.m.  EST
yesterday.  Post launch securing operations are underway  at  Pad
39-A today. The mobile launcher platform will be transferred back
to  the  VAB on Monday.  Launch damage to the pad was reported as
minimal.

     At sea,  the  booster  retrieval  operations  are  underway.
Recovery  teams  station-kept  the  boosters  overnight and began
retrieval activities at sunrise this morning.  The parachutes are
on board and work to secure the boosters for tow is underway. The
boosters are expected to be in port tomorrow.


 
633.72Atlantis is still up there19458::FISHERI like my species the way it is&quot; &quot;A narrow view...Tue Nov 20 1990 10:536
Atlantis did not land yesteday at EAFB as schedule because of high winds.  The
landing has been rescheduled for today, although the forcast looks bad.
Contingency plans are to land at Kennedy.  I don't know how long they can wait
in space for the weather to clear rather than chance a KSC landing.

Burns
633.734347::GRIFFINDave GriffinTue Nov 20 1990 12:063
I believe it has to come down tomorrow (wed.) - somewhere.

- dave
633.74First landing at KSC in many years!19458::FISHERI like my species the way it is&quot; &quot;A narrow view...Tue Nov 20 1990 17:495
    They landed this afternoon at KSC!  CNN just had pix.  No info about
    brakes or anything, though.  It was just claimed to be "flawless".
    
    Burns
    
633.75Rumors...58519::PIERCEawk!! I&#039;ve been greped!Wed Nov 21 1990 10:5615
    Headline news this morning had coverage of the landing.
    
    They said that observations of amateur astronomers (they saw 1 object,
    then 2 objects, then 1 object) have lead to speculation that
    
    	1) The bird was a sync. comm spy satellite (and went higher).
    
    	2) It was defective and brought back.
    
    Also got a kick out of how the press was making a big deal out of it
    being a mission to "spy on Iraq"..... 
    
    "Hey guys, lets whip together a satellite to help us in the Iraq thing,
    and give the shuttle guys a call, they deliver... on call!".
    
633.76STAR::HUGHESYou knew the job was dangerous when you took it Fred.Wed Nov 21 1990 11:037
    Or that the initial suggestion by AvLeak was correct and that it was
    boosted into an intermediate orbit of about 400 miles.
    
    And yeah, 'satellites built while you wait'. They seem to have
    forgotten that this was out on the pad once before :-)
    
    gary
633.77McNews watchers...58519::PIERCEawk!! I&#039;ve been greped!Wed Nov 21 1990 12:325
    Somehow I don't think that the average Headline News/CNN watcher reads
    Aviation Leak 
    
    	;-)
    
633.78STAR::HUGHESYou knew the job was dangerous when you took it Fred.Wed Nov 21 1990 13:435
    Ah, but on one version of the story that CNN ran this morning, they
    mentioned it. They will often have three or four different edits of a
    story, each one slightly different.
    
    gary
633.79Shuttle Status Report - 11/21/904347::GRIFFINDave GriffinSun Nov 25 1990 01:5845
From: NASA
Organization: NASA

           KSC SPACE SHUTTLE PROCESSING STATUS REPORT

   Wednesday November 21, 1990                 11:00 a.m. EST

-----------------------------------------------------------------

 
             STS-38 -- Atlantis (OV-104)  -  OPF Bay 2

     The orbiter Atlantis landed without incident on Kennedy
Space Center's runway 33 yesterday at 4:43 p.m. concluding a 4
day, 21 hour, 54 minute, 28 second Department of Defense
dedicated mission. Atlantis' main gear touched down at 4:42:43
p.m. Rollout distance was 8900 feet.

     Initial indications reveal minimal tile damage and the tires
and brakes were reported to look good. All systems functioned
properly during descent.

     The vehicle was safed at the runway and towing operations
began at about 8:45 p.m. The vehicle was in the Orbiter
Processing Facility bay by 10:27 last night. Purge operations of
the on-board propellant tanks is underway today with the
anticipation that all safing operations will be completed by mid-
day Thursday.

     Atlantis had been scheduled to land at Edwards Air Force
Base, Ca. However, due to adverse winds and standing water on the
dry lake bed, and a forecast for no improvement of weather
conditions on the following day, the decision was made at
approximately 1:30 p.m. to land at KSC. This was the sixth
shuttle landing at the space center -- the first for Atlantis.
This was also the first landing at the launch site in five and a
half years.

     Approximately four hours following the landing, the five-
member crew departed for Ellington Field in Houston, Texas. Crew
members for STS-38 include Commander Richard Covey, Pilot Frank
Culbertson, and Mission Specialists Sam Gemar, Robert Springer,
and Carl Meade.

 
633.80Do we save any money by landing in Florida?6056::GAUDETNothing unreal existsMon Nov 26 1990 13:2429
I realize that safety is the primary reason the shuttle lands at Edwards, but
what sort of savings (if any) are realized when the shuttle lands at KSC?  I'd
be interested in some informed opinions and/or hard statistics around some of
the things that seem like "obvious" savings to me.  The estimates I've included
are "gut feel" and are quite probably out in space.  :-)  I realize also that
some of these savings may be absorbed by additional costs at the KSC end.  If
that's so I'd like to know that too.  I'll even take a "See note XXX" response
if there's a better place for this.

	1) Time (at least a week?)
	   a) No need for prep at Edwards (engine cones, mate w/747, etc.)
	      for its trip back to KSC atop the 747 (3-5 days?)
	   b) No need for the trip to KSC (2 days)
	   c) No need for orbiter demate from the 747 at KSC (a few hours?)

	2) Fuel (who knows how many thousands of gallons?)
	   a) No need to fuel the 747 for the trip to KSC (as well as to Edwards
	      if KSC is where it starts from)

	3) Personnel (100 people?)
	   a) No need for prep crew at Edwards (this time at least)
	   b) No need for flight crew on 747
	   c) No need for 747-demate operations at KSC

Even if it's a small amount, what are we talking here?  Seems like it could
easily be in the tens of thousands of dollars or more.  No fair giving figures
as a percentage of launch cost!  :-)

...Roger...
633.8119458::FISHERI like my species the way it is&quot; &quot;A narrow view...Mon Nov 26 1990 16:327
They mentioned either in AvWeek or CNN the figure.  It amounted to several
million dollars.  I'm not quite sure how they figure that, unless it includes
dollars saved because of the 1 week shorter turnaround.  But that one sounds
like a lot of paper shuffling.  They still have to pay the people that were out
at EAFB waiting for it.

Burns
633.82Follow that shuttle!19458::FISHERI like my species the way it is&quot; &quot;A narrow view...Mon Nov 26 1990 16:336
It will be interesting to follow the flow of Atlantis.  For example, I would
expect that if the satellite had been loaded back in and the DOD wanted it
back soon, that we would see the orbiter to into the payload building quite
quickly.

Burns
633.83Astronaut Springer retiresADVAX::KLAESAll the Universe, or nothing!Wed Dec 12 1990 17:4647
From: [email protected] (Peter E. Yee)
Newsgroups: sci.space
Subject: Astronaut Springer retires from NASA, Marine Corps (Forwarded)
Date: 12 Dec 90 21:12:32 GMT
Sender: [email protected] (USENET Administration)
Organization: NASA Ames Research Center, Moffett Field, CA
 
Mark Hess/Ed Campion
Headquarters, Washington, D.C.                  December 12, 1990
(Phone:  202/453-8536)
 
Barbara Schwartz
Johnson Space Center, Houston
(Phone:  713/483-5111)
  
RELEASE:  90-159
 
ASTRONAUT SPRINGER RETIRES FROM NASA, MARINE CORPS
  
     Col. Robert C. Springer, selected as an astronaut in 1980 
and a mission specialist on two Space Shuttle flights, has 
retired from NASA and the U.S. Marine Corps.
 
     During his first space flight, STS-29 in March 1989, 
Springer and his crewmates deployed a NASA Tracking and Data 
Relay Satellite and performed numerous secondary experiments, 
including a Space Station "heat pipe" radiator experiment, two 
student experiments, a protein crystal growth experiment and a 
chromosome and plant cell division experiment.  Additionally, the 
crew took more than 4,000 photographs of the Earth using several 
types of cameras, including the IMAX 70-mm movie camera.
 
      Springer also flew on STS-38, a Department of Defense 
flight, which was launched on Nov. 15, 1990.
 
     Springer's technical assignments have included serving as a 
member of the support crew for STS-3, concept development studies 
for the Space Operations Center and the coordination of various 
aspects of the final development of the Remote Manipulator System 
for operational use.  He also worked in the Mission Control 
Center, Johnson Space Center, as spacecraft communicator for 
seven flights in 1984 and 1985.
 
     Springer announced he will work for Boeing Aerospace and 
Electronics Division in Huntsville, Ala., as the manager of the 
Space Station Freedom's element integration.